BLD-Final | 4/29/2020 | 4/30/2020 | 4/30/2020 | A | PASS |
Tony Young
|
|
|
Brian **cleared** Phone #: ###-####
|
DOC - Permit Finaled | 4/30/2020 | 4/30/2020 | 4/30/2020 | P | PASS |
Tony Young
|
|
|
|
BLD-Blower Door Test Results | 4/30/2020 | 4/30/2020 | 4/30/2020 | P | PASS |
Tony Young
|
|
|
Brian **cleared** Phone #: ###-####// 2.2
|
CHANGE STATUS TO (ISS) | | | 4/28/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 4/27/2020 | | |
|
|
|
|
Plan assigned to (RDP) | 4/20/2020 | 4/20/2020 | 4/27/2020 | | DONE |
Rob Patrick
|
|
|
Plan Mod ePlan
|
Routing - PLAN CHECK | 4/27/2020 | | 4/27/2020 | | PASS |
Rob Patrick
|
|
|
No added charge. No Bldg review required.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/27/2020 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 4/27/2020 | | DONE |
|
|
|
plan mod approved Do not issue
|
Routing - MECHANICAL | 4/20/2020 | | 4/21/2020 | | PASS |
Troy James
|
|
|
plan mod- manual J
|
Plan Modification Accepted | | | 4/20/2020 | | DONE |
|
|
|
manual j
|
BLD-Foundation | 1/28/2020 | 1/29/2020 | 1/29/2020 | P | PASS |
Dave Hannah
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru
|
BLD-Footing | 1/20/2020 | 1/21/2020 | 1/21/2020 | P | PART |
Tell Riley
|
|
|
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru//setbacks set by surveyor//rebar per plans//need to install ufer ground//
|
Issue PAID IN FULL permit | | | 12/23/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 12/18/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 12/18/2019 | | DONE |
|
|
|
NEED
GC Form
|
Plan assigned to (RDP) | 12/9/2019 | 12/9/2019 | 12/17/2019 | | DONE |
Rob Patrick
|
|
|
12/20 SFD L1 ePlan...12/11 Failed; 12/16 Failed; for the same reason as BLD19-04776.
|
Routing - PLANNING | 12/17/2019 | | 12/17/2019 | | PASS |
Sue Cummings
|
|
|
Corrections make!
|
Routing - PLAN CHECK | 12/17/2019 | | 12/17/2019 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/17/2019 | | DONE |
Rob Patrick
|
|
|
|
Routing - PLANNING | 12/16/2019 | | 12/16/2019 | | FAIL |
Sue Cummings
|
|
|
Needs a side yard setback on the south side
|
Routing - PLAN CHECK | 12/16/2019 | | 12/16/2019 | | FAIL |
Rob Patrick
|
|
|
12/16 Failed for the same reason as BLD19-04776.
|
Routing - FIRE | 12/11/2019 | 12/11/2019 | 12/11/2019 | | PASS |
Lee G Meredith
|
|
|
SFH
Sprinklers are not required. No written review comments.
|
1st review completed | | | 12/11/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Routing - PLAN CHECK | 12/9/2019 | | 12/11/2019 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Routing - Addressing | 12/9/2019 | | 12/10/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/9/2019 | | 12/10/2019 | | PASS |
Candy A. Nichols
|
|
|
|
Route to Impact Fee Review | 12/7/2019 | 12/10/2019 | 12/9/2019 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 12/9/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/9/2019 | | DONE |
|
|
|
|
Intake Approval | | | 12/9/2019 | | PASS |
|
|
|
per Tisha ok to route and do not route to MEC
|
Routing - PLANNING | 12/9/2019 | | 12/9/2019 | | FAIL |
Sue Cummings
|
|
|
Parking area needs to be 40 ft. deep. 20 setback (from the edge of the common drive) and 20 parking space.
|
Application received | | | 12/6/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 6 2019 6:34PM
|