BLD-Foundation | 7/31/2020 | 8/3/2020 | 8/3/2020 | A | PART |
Brandon Shaw
|
|
|
Work in progress... Pending special inspection...
|
BLD-Footing | 7/27/2020 | 7/28/2020 | 7/28/2020 | A | PART |
Brandon Shaw
|
|
|
Speciakl inspector to be on site for rebar and concrete pour...
|
CHANGE STATUS TO (ISS) | | | 7/1/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 6/30/2020 | | |
|
|
|
|
Plan assigned to (JAR) | 6/9/2020 | 6/9/2020 | 6/30/2020 | | DONE |
Julie Romig
|
|
|
07/02 - 2nd Rev - 1st Rev Comp - Plan Mod Barber Valley Urgent Care
|
Routing PW Drainage | 6/26/2020 | | 6/30/2020 | | PASS |
Brian Murphy
|
|
|
Signed off per ePlanReview
|
Permit Ready to Issue | | | 6/30/2020 | | |
|
|
|
Plan Mod MEt
|
Routing - Design Review | 6/11/2020 | | 6/24/2020 | | PASS |
Josh Wilson
|
|
|
|
Routing - FIRE | 6/11/2020 | 6/11/2020 | 6/19/2020 | | PASS |
Erika Akin
|
|
|
Plan mod does not impact previous approval or FD access.
|
Routing - PLANNING | 6/11/2020 | | 6/18/2020 | | PASS |
David Moser
|
|
|
|
Routing - PLAN CHECK | 6/10/2020 | | 6/18/2020 | | PASS |
Julie Romig
|
|
|
|
Routing PW Flood Plain | 6/15/2020 | | 6/17/2020 | | CANC |
Jason C. Taylor
|
|
|
Approved LOMR on File. No floodplain review required. If you have any questions, please call Jason Taylor at ###-####.
|
Routing PW Solid Waste | 6/15/2020 | | 6/16/2020 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Environmental | 6/15/2020 | | 6/16/2020 | | PASS |
Zach Conde
|
|
|
PER ZACH: Passed on ePlan with no comments. Please pass on Tidemark
|
Routing - PUBLIC WORKS | 6/11/2020 | | 6/15/2020 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Drainage | 6/15/2020 | | 6/15/2020 | | FAIL |
Brian Murphy
|
|
|
NEED SIGNED APENDIX J IN PDF
|
Routing PW Street Lights | 6/15/2020 | | 6/15/2020 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 6/15/2020 | | 6/15/2020 | | PASS |
DeAnn Brown
|
|
|
|
Plan Modification Accepted | | | 6/9/2020 | | DONE |
|
|
|
Plan Mod: Erik Chudy; Shifting Building 14' to the south to avoid existing utilities
|
Issue PAID IN FULL permit | | | 4/14/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/14/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 3/6/2020 | | |
|
|
|
|
Plan assigned to (JAR) | 12/12/2019 | 12/17/2019 | 3/6/2020 | | DONE |
Julie Romig
|
|
|
4th Rev - 1st Rev Comp - 502 Barber Station Urgent Care
|
Routing - PLAN CHECK | 3/2/2020 | | 3/6/2020 | | PASS |
Julie Romig
|
|
|
Per Julie's email on 3/6/2020
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2020 | | DONE |
Julie Romig
|
|
|
|
Permit Ready to Issue | | | 3/6/2020 | | DONE |
|
|
|
met korey@bvadev.com
NEED
ACHD
GC
REVISED VALUE
|
Routing Off Site - STRUCTURAL | 3/2/2020 | | 3/3/2020 | | PASS |
Julie Romig
|
|
|
4th Review Stapley
|
Routing PW Sewer Design | 3/2/2020 | | 3/3/2020 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Drainage | 3/2/2020 | | 3/2/2020 | | PASS |
Brian Murphy
|
|
|
|
Routing Off Site - STRUCTURAL | 2/20/2020 | | 2/28/2020 | | FAIL |
Julie Romig
|
|
|
Stapley 3rd Rev
|
Routing PW Drainage | 2/20/2020 | | 2/27/2020 | | FAIL |
Brian Murphy
|
|
|
NEED APENDX J
|
Routing PW Sewer Design | 2/20/2020 | | 2/27/2020 | | FAIL |
DeAnn Brown
|
|
|
Still waiting on signed easements for sewer main extension that will serve this building. Resubmit after applicant has received a sewer plan approval letter.
|
Routing - Design Review | 2/20/2020 | | 2/26/2020 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLAN CHECK | 2/20/2020 | | 2/20/2020 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 2/3/2020 | | 2/18/2020 | | FAIL |
Julie Romig
|
|
|
|
Routing PW Sewer Design | 2/3/2020 | | 2/10/2020 | | FAIL |
DeAnn Brown
|
|
|
Still waiting on easement documents for sewer main extension that will serve this building. Resubmit after applicant has received a sewer plan approval letter.
|
Routing Off Site - STRUCTURAL | 2/3/2020 | | 2/6/2020 | | FAIL |
Julie Romig
|
|
|
|
Routing PW Drainage | 2/3/2020 | | 2/5/2020 | | FAIL |
Brian Murphy
|
|
|
need o/s trap o and m apnx j
|
Route to Impact Fee Review | 1/23/2020 | 1/26/2020 | 1/24/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 12/17/2019 | 12/17/2019 | 1/23/2020 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLAN CHECK | 12/17/2019 | | 1/23/2020 | | FAIL |
Julie Romig
|
|
|
|
1st review completed | | | 1/23/2020 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLUMBING | 12/17/2019 | | 12/27/2019 | | PASS |
Dan Ediger
|
|
|
Per Plans and ISPC
|
Routing PW Drainage | 12/18/2019 | | 12/24/2019 | | FAIL |
Brian Murphy
|
|
|
need site o and m for this site and apdx j.
|
Routing - Design Review | 12/17/2019 | | 12/23/2019 | | PASS |
Josh Wilson
|
|
|
|
Routing - MECHANICAL | 12/17/2019 | | 12/20/2019 | | PASS |
Troy James
|
|
|
|
Routing PW Street Lights | 12/18/2019 | | 12/20/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLANNING | 12/17/2019 | | 12/20/2019 | | PASS |
David Moser
|
|
|
|
Routing PW Solid Waste | 12/18/2019 | | 12/20/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Flood Plain | 12/18/2019 | | 12/19/2019 | | PASS |
Jason C. Taylor
|
|
|
Approved LOMR on File. No floodplain review required. If you have any questions, please call Jason Taylor at ###-####.
|
Routing PW Environmental | 12/18/2019 | | 12/18/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing - Addressing | 12/17/2019 | | 12/18/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/17/2019 | | 12/18/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 12/17/2019 | | 12/18/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Certified RP listed. Need to provide dewatering plan for utilitty installation. Site preparation inspection is required.
|
Routing PW Sewer Design | 12/18/2019 | | 12/18/2019 | | FAIL |
DeAnn Brown
|
|
|
Sewer main extension required to serve this building has not yet been approved by City of Boise.
|
Plan Reviewer's activity | | | 12/12/2019 | | PASS |
|
|
|
Plan intake review approved
|
Intake Approval | | | 12/12/2019 | | PASS |
|
|
|
|
Intake Approval | | | 12/10/2019 | | FAIL |
|
|
|
(12-10-19) Refer to the circled items in the Plan Intake Checklist. Resolve each item as directed. CJW
|
Application received | | | 12/9/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 9 2019 8:54AM
|
Routing Off Site - STRUCTURAL | 12/17/2019 | | 2/23/2019 | | FAIL |
Julie Romig
|
|
|
Stapley
|