BLD-Energy code compliance | 8/13/2020 | 8/13/2020 | 8/13/2020 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Wall cover | 8/13/2020 | 8/13/2020 | 8/13/2020 | P | PASS |
Dave Hannah
|
|
|
Shaun *screened Phone #: ###-####
|
BLD-Framing/Rough-in | 8/10/2020 | 8/11/2020 | 8/11/2020 | A | PASS |
Brandon Shaw
|
|
|
Shaun - */Screened/* Phone #: ###-####
|
BLD-Wall Bracing | 6/18/2020 | 6/19/2020 | 6/19/2020 | A | PART |
Brandon Shaw
|
|
|
First floor only...
|
BLD-Foundation | 4/15/2020 | 4/16/2020 | 4/16/2020 | A | PASS |
Jim Storey
|
|
|
late am preferred - screened // Gary Phone #: ###-####
|
BLD-Footing | 4/13/2020 | 4/13/2020 | 4/13/2020 | P | PART |
Tony Young
|
|
|
*screened* Access in alley, after 2pm - Gary Phone #: ###-####.. work in progress,, setbacks appear ok
|
Issue PAID IN FULL permit | | | 1/29/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 1/28/2020 | | |
|
|
|
|
Meeting | | | 1/28/2020 | | DONE |
|
|
|
gave to josh to add in covered patio value
|
Routing - PLAN CHECK | 1/23/2020 | | 1/28/2020 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 1/28/2020 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 1/28/2020 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/28/2020 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Permit Ready to Issue | | | 1/28/2020 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 12/10/2019 | | 1/28/2020 | | PASS |
Josh Bogle
|
|
|
*12/18 ADU, paper - 1st done
|
Routing - PLANNING | 1/23/2020 | | 1/24/2020 | | PASS |
Nicolette Womack
|
|
|
|
Plan resubmittals received | | | 1/22/2020 | | DONE |
|
|
|
Two copies of Patio Cover Calculations, Three copies of site plan, Two copies of sheets 0.0, A1.0, A2.0, S1.0, S2.0, S2.1, S3.0, SD1.0 and SD2.0 taken to Josh
|
1st review completed | | | 12/26/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 12/13/2019 | | 12/26/2019 | | FAIL |
Josh Bogle
|
|
|
see e-mail to Shaun
|
Routing - MECHANICAL | | | 12/13/2019 | | PASS |
|
|
|
Mini Split, Owner to install energy star bath fan for mechanical ventilation.
|
Routing - PLANNING | 12/11/2019 | | 12/12/2019 | | FAIL |
Nicolette Womack
|
|
|
Not enough room for porch drawn on plans, making it attached to the main home, revise to include the main home. Driveway to the alley is required to be paved. Required to be owner occupied, title of plans says 'Benoit Garage' explain how project is being owner occupied.
|
Route to Impact Fee Review | 12/10/2019 | 12/13/2019 | 12/11/2019 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 12/10/2019 | | 12/11/2019 | | PASS |
Doug Chausow
|
|
|
ADU Address: 1329 S Division Ave
|
Routing - PUBLIC WORKS | 12/10/2019 | | 12/11/2019 | | PASS |
Candy A. Nichols
|
|
|
ADU
|
Plans ACCEPTED BY PLAN TECH | | | 12/10/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/10/2019 | | DONE |
|
|
|
|
Intake Approval | | | 12/10/2019 | | PASS |
|
|
|
|
Application received | | 12/10/2019 | | | |
|
|
|
|