First Notice | | 7/31/2020 | 7/31/2020 | | DONE |
|
|
|
This permit finaled on the web by Brian McCoy
|
PubWorks Occupancy Approval | 7/21/2020 | 7/21/2020 | 7/21/2020 | | DONE |
Tiffany Lowery
|
|
|
|
Permanent Occupancy | | | 7/21/2020 | | DONE |
|
|
|
|
Telephone call | | | 7/20/2020 | | DONE |
|
|
|
emailed Kelly from Straight Line that they need a final Public Works inspection before we can issue this certificate of occupancy
|
Telephone call | | | 7/17/2020 | | DONE |
|
|
|
Kelly from SLBS emailed the sign off card requesting a c of o. However, there are unpaid PRK fees. I have emailed Kelly the fees due.
|
BLD-Final | 7/15/2020 | 7/15/2020 | 7/15/2020 | P | PASS |
Jim Storey
|
|
|
Tom screened Phone #: ###-#### need fir permit closed..
|
FIRE-Final Inspection | 7/14/2020 | 7/15/2020 | 7/15/2020 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, no fire alarm modifications, fire extinguishers are placed with current inspection tags. Final life fire safety inspection is complete, signatures provided on permit sign off card.
SCREENED // Tom Phone #: ###-####
|
BLD-Foundation | 6/16/2020 | 6/17/2020 | 6/17/2020 | A | PASS |
Jim Storey
|
|
|
screened - 9am pour// Tom Phone #: ###-####
|
BLD-Footing | 6/10/2020 | 6/11/2020 | 6/11/2020 | A | PASS |
Jim Storey
|
|
|
screened // tom Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 6/10/2020 | | DONE |
|
|
|
plan mod
|
BLD-Ceiling Grid Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 | P | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-####
|
OVERRIDE | | | 5/27/2020 | | |
|
|
|
|
Plan assigned to (JG) | 5/20/2020 | 5/20/2020 | 5/27/2020 | | PASS |
Javier Guzman
|
|
|
05/27 plan mod Fleet Street - Suite #140 pend pw grade
|
Routing - PUBLIC WORKS | 5/21/2020 | | 5/27/2020 | | PASS |
Morgan Webb
|
|
|
please send to grading & Drainage in ePlan
|
Routing PW Drainage | 5/21/2020 | | 5/27/2020 | | PASS |
Brian Murphy
|
|
|
plan modification
c2.1and c3.1 approved
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/27/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/27/2020 | | DONE |
|
|
|
PLAN MOD
|
Routing - PLAN CHECK | 5/21/2020 | | 5/21/2020 | | PASS |
Javier Guzman
|
|
|
|
Plan Modification Accepted | | | 5/20/2020 | | DONE |
|
|
|
Changes were made to the drainage design at the dock, but we understand that there was an oversight and original civil design was never reviewed by public works.
|
BLD-Conference | 5/15/2020 | 5/18/2020 | 5/18/2020 | A | PASS |
Jim Storey
|
|
|
screened // Tom Phone #: ###-#### depth appears to be ok
|
BLD-Framing/Rough-in | 4/24/2020 | 4/27/2020 | 4/27/2020 | A | PASS |
Jim Storey
|
|
|
Tom - Firred out wall, Hardlids for bathrooms Phone #: ###-####
|
BLD-Framing/Rough-in | 4/2/2020 | 4/2/2020 | 4/2/2020 | P | PASS |
Jim Storey
|
|
|
tom Phone #: ###-####
|
BLD-Framing/Rough-in | 3/3/2020 | 3/3/2020 | 3/3/2020 | P | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/28/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/28/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 2/27/2020 | | |
|
|
|
|
Plan assigned to (JG) | 12/24/2019 | 12/24/2019 | 2/27/2020 | | PASS |
Javier Guzman
|
|
|
03/04 2nd rev, L3 Fleet Street ePlan
|
Routing - PLAN CHECK | 2/20/2020 | | 2/27/2020 | | PASS |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 2/20/2020 | | 2/27/2020 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by AHJ Engineers
|
Permit Ready to Issue | | | 2/27/2020 | | DONE |
|
|
|
ALL MET
Need
GC Form
Revised Cert of Value (for each permit)
DO NOT ISSUE WITHOUT BLD19-04942
|
Route to Impact Fee Review | 2/10/2020 | 2/13/2020 | 2/11/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 12/24/2019 | 12/24/2019 | 2/4/2020 | | PASS |
Greg Ruxton
|
|
|
Comments attached to case.
|
1st review completed | | | 2/4/2020 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 12/24/2019 | | 1/15/2020 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 12/24/2019 | | 1/14/2020 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan by AHJ Engineers
|
Routing PW Solid Waste | 12/31/2019 | | 1/3/2020 | | PASS |
Evan Carpenter
|
|
|
|
Routing - PLANNING | 12/24/2019 | | 12/31/2019 | | PASS |
Karla Nelson
|
|
|
|
Routing - PUBLIC WORKS | 12/24/2019 | | 12/31/2019 | | PASS |
Morgan Webb
|
|
|
NO NEW FEES
|
Routing - Erosion and Sediment | 12/24/2019 | | 12/27/2019 | | PASS |
Andy J. Long
|
|
|
No new exterior disturbance listed in scope, no ESC permit required.
|
Routing - Addressing | 12/24/2019 | | 12/26/2019 | | PASS |
Doug Chausow
|
|
|
Suite 140
|
Routing - MECHANICAL | 12/24/2019 | | 12/26/2019 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 12/24/2019 | | 12/24/2019 | | PASS |
Katelyn Menuge
|
|
|
|
Intake Approval | | | 12/19/2019 | | FAIL |
Javier Guzman
|
|
|
or prescreen review provide and upload the following:
• Provide a completed 520 application for the created new tenant space (one application is for Fleet and new application will be for the created Hayden tenant space which currently we have no record of this space being occupied by anyone), application can be found at https://www.cityofboise.org/departments/planning-and-development-services/building/building-permits/?category=all&search=all
|
Intake Approval | | | 12/19/2019 | | PASS |
|
|
|
|
Intake Approval | | | 12/13/2019 | | FAIL |
Javier Guzman
|
|
|
For prescreen review provide and upload the following:
• Provide a completed 520 checklist (as this will be routed as a Major T.I.)
• Provide items that are requested from the 520 checklist that apply to the project. Checklist can be found at https://www.cityofboise.org/departments/planning-and-development-services/building/building-permits/?category=all&search=all
• Per 520 checklist provide a notarized Drainage System Operation & Maintenance Plan Agreement (appendix J from Public Works Stormwater Manual)
• Provide a completed 520 application for the created new tenant space (one application is for Fleet and new application will be for the created Hayden tenant space which currently we have no record of this space being occupied by anyone), application can be found at https://www.cityofboise.org/departments/planning-and-development-services/building/building-permits/?category=all&search=all
• Per ePlan submittal standards the reserve the bottom right corner on the drawing plans for the City electronic stamps. Leave a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block on plan sheet S7.2 see ePlan standards at https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
|
Application received | | | 12/11/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 11 2019 10:57AM
|