Permit Information
Permit NumberBLD19-04858
StatusFinaled
Name INTERMOUNTAIN WIND & SOLAR LLC
Site Address 700 E CURLING DR
Project NameTom Turner PV Solar
Customer Number 
ePlanReviewYes
Description
Permit for 365sq' of roof-mounted, grid-tied Photo-voltaic panels with micro-inverters; 21 panels in 1 array.. All racking, modules, and other listed equipment must be installed by a certified installer. All work per plans, manufacturer’s specs, & local code. Separate electrical permit required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/6/20203/9/20203/9/2020PDONE
DetailsTony Young
Plans left on site Phone #: ###-#### Inspection requested via web by Kilee Russell
DOC - Permit Finaled3/9/20203/9/20203/9/2020PPASS
DetailsTony Young
done
BLD-Framing/Rough-in2/27/20203/5/20203/5/2020PPEND
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Kilee Russell,, no frame needed to existing structure
BLD-Framing/Rough-in2/27/20203/5/20202/27/2020PCANC
DetailsTony Young
Phone #: ###-#### >> Inspection requested via web by Kilee Russell Inspection cancelled from web by: Kilee Russell
Plan assigned to (JAB) Josh1/3/20201/3/20201/8/2020 PASS
DetailsJosh Bogle
01/09 PV, ePlan - 1st done
Routing - PLAN CHECK1/8/2020 1/8/2020 PASS
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  1/8/2020 DONE
DetailsJosh Bogle
ESC no - Energy no
Permit Ready to Issue  1/8/2020 DONE
Issue PAID IN FULL permit  1/8/2020 DONE
Inspection Record Card- Bld  1/8/2020 DONE
Routing - PLAN CHECK1/3/2020 1/6/2020 FAIL
DetailsJosh Bogle
fire access width unclear - no UL listing on panels
Routing - PLANNING1/3/2020 1/6/2020 PASS
DetailsJeff Lowe
1st review completed  1/6/2020 FAIL
DetailsJosh Bogle
Intake Approval  1/3/2020 PASS
Intake Approval  12/17/2019 FAIL
12/17/19 Second Prescreen
Both Engineering letters have the wrong IRC/IBC code year. The one labeled Tom Turner Roof Evaluation is 2018 and the one labeled ID UR 40 Engineering states its 2012 IRC.
Please update the engineering information to state the 2015 IRC code.
Application received  12/16/2019 DONE
Application submitted via PDS Online on Dec 16 2019 10:55AM
Intake Approval  12/16/2019 FAIL
During prescreen it was noticed that you have 2018 IRC on the drawings and Roof evaluation document. We are not in the 2018 IRC code year yet. Can you please correct the code year information to the 2015 IRC code year and resubmit.