BLD-Final | 6/16/2020 | 6/17/2020 | 6/17/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 6/17/2020 | 6/17/2020 | 6/17/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 6/17/2020 | 6/17/2020 | 6/17/2020 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.41
|
PubWorks Occupancy Approval | 6/17/2020 | 6/17/2020 | 6/17/2020 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department Jason Taylor ###-####.
|
BLD-Final | 6/10/2020 | 6/10/2020 | 6/10/2020 | A | NR |
Brandon Shaw
|
|
|
Need PW hillside approval...
|
BLD-Blower Door Test Results | 6/10/2020 | 6/10/2020 | 6/10/2020 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 3.41
|
BLD-Framing/Rough-in | 3/5/2020 | 3/5/2020 | 3/5/2020 | P | PASS |
Brandon Shaw
|
|
|
If plans are missing, make sure the siders did not steal them Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 3/4/2020 | 3/4/2020 | 3/4/2020 | P | FAIL |
Brandon Shaw
|
|
|
No city approved plans on site...
|
BLD-Other | 3/2/2020 | 3/3/2020 | 3/3/2020 | P | PASS |
Brandon Shaw
|
|
|
Soffit Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Wall Bracing | 2/13/2020 | 2/14/2020 | 2/14/2020 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 2/13/2020 | 2/13/2020 | 2/13/2020 | P | NR |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Wall Bracing | 2/12/2020 | 2/13/2020 | 2/13/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Foundation | 1/21/2020 | 1/22/2020 | 1/22/2020 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 1/17/2020 | 1/17/2020 | 1/17/2020 | P | PASS |
Brandon Shaw
|
|
|
Work in progress... Frost protection is required...
|
PubWorks Subgrade Approval | 1/17/2020 | 1/17/2020 | 1/17/2020 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 1/3/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/3/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 12/30/2019 | | |
|
|
|
|
Plan assigned to (D_S) Debbie | 12/19/2019 | 12/19/2019 | 12/30/2019 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 12/30/2019 | | 12/30/2019 | | PASS |
Jenny Nelson
|
|
|
Per D_S review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/30/2019 | | DONE |
Debbie Sanine
|
|
|
|
Permit Ready to Issue | | | 12/30/2019 | | DONE |
|
|
|
met
|
1st review completed | | | 12/26/2019 | | FAIL |
Debbie Sanine
|
|
|
|
Routing PW Grading-Hillside | 12/18/2019 | | 12/26/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Routing - PLAN CHECK | 12/18/2019 | | 12/23/2019 | | FAIL |
Jenny Nelson
|
|
|
WUI compliant soffit
|
Routing - Addressing | 12/18/2019 | | 12/23/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/18/2019 | | 12/23/2019 | | PASS |
Candy A. Nichols
|
|
|
|
Route to Impact Fee Review | 12/18/2019 | 12/21/2019 | 12/19/2019 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plan assigned to (J_N) | 12/18/2019 | 12/18/2019 | 12/19/2019 | | DEFR |
|
|
|
|
Routing - FIRE | 12/18/2019 | 12/18/2019 | 12/19/2019 | | PASS |
Lee G Meredith
|
|
|
Sprinklers are not required.
|
Routing - MECHANICAL | 12/18/2019 | | 12/19/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 12/18/2019 | | 12/18/2019 | | PASS |
Jeff Lowe
|
|
|
|
Intake Approval | | | 12/18/2019 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 12/18/2019 | | 12/18/2019 | | PASS |
Michael Zawacki
|
|
|
|
Application received | | | 12/17/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 17 2019 8:15AM
|