Second Notice | | 7/19/2020 | 7/20/2020 | | DONE |
|
|
|
This permit finaled on the web by Drew Moorhouse
|
First Notice | | 5/22/2020 | 7/9/2020 | | DONE |
|
|
|
mailed 7-9-2020
|
Permanent Occupancy | | | 5/12/2020 | | DONE |
|
|
|
|
BLD-Final | 5/11/2020 | 5/11/2020 | 5/11/2020 | P | PASS |
Tell Riley
|
|
|
I would like to meet you onsite to review.
Dana McCarter ###-#### Phone #: ###-#### Inspection requested via web by Drew Moorhouse//final ok see notes below//add second microwave that is in an accessible location or lower the one onsite//letter from architect needs to be submitted and added to documents for project//
|
FIRE-Final Inspection | 5/8/2020 | 5/11/2020 | 5/11/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
I would like to meet you onsite.
Thanks, Dana Phone #: ###-#### Inspection requested via web by Drew Moorhouse
|
FIRE-Final Inspection | 5/7/2020 | 5/8/2020 | 5/8/2020 | A | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to sign off when the project related fire alarm permit is finaled.
I would like to meet onsite to review any corrections if need be.
Thanks, Dana McCarter ###-#### Phone #: ###-#### Inspection requested via web by Drew Moorhouse
|
BLD-Conference | 4/29/2020 | 4/30/2020 | 4/30/2020 | P | DONE |
Tell Riley
|
|
|
meet Drew ###-####//discuss med gas room, need architect to approve as built design, 2x6 wall does not extend to underside of roof deck, although shaft is lined with 2 layers 5/8 typ X, walls below are 2x6 with 5/8 type x on both sides//does not match plans//
|
BLD-Ceiling Grid Inspection | 4/28/2020 | 4/29/2020 | 4/29/2020 | P | PASS |
Tell Riley
|
|
|
I would like to meet you onsite to review any correction if need be.
Thanks, Drew Moorhouse McCarter-Moorhouse ###-####
Phone #: ###-#### Inspection requested via web by Drew Moorhouse// fix insulation above exam area//add clips to wall connections in back room, other wise ok to cover grid//will meet Drew thursday regarding med gas room and fire wall//
|
Change Expiration Date Only | | | 4/9/2020 | | DONE |
|
|
|
Permit issued by mistake 4/9/20, updating expiration date to match last inspection
|
Print Occupancy Form | | | 4/9/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/7/2020 | | DONE |
|
|
|
DO NOT ISSUE- plan mod approved
|
Plan assigned to (M_H) | 3/25/2020 | | 4/6/2020 | | DONE |
Michael Hanson
|
|
|
04/01 plan mod - Clarification made to the construction of the med gas room
|
Routing - PLAN CHECK | 3/31/2020 | | 4/6/2020 | | PASS |
Michael Hanson
|
|
|
Plan mod review fee = 1 hour
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/6/2020 | | DONE |
Michael Hanson
|
|
|
|
Plan Modification Accepted | | | 3/25/2020 | | DONE |
|
|
|
plan mod 1
|
BLD-Framing/Rough-in | 3/16/2020 | 3/16/2020 | 3/16/2020 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Drew Moorhouse//wall cover only//do not cover med gas room, or area needing sprinklers moved//
|
BLD-Conference | 3/13/2020 | 3/16/2020 | 3/16/2020 | A | DONE |
Tell Riley
|
|
|
We would like to meet onsite at 10AM Phone #: ###-#### Inspection requested via web by Drew Moorhouse
|
BLD-Conference | 3/13/2020 | 3/13/2020 | 3/13/2020 | P | DONE |
Tell Riley
|
|
|
requested by Mech inspector to look at med gas room//CN posted for contractor to contact me for conference regarding med gas room ratings and construction//
|
BLD-Framing/Rough-in | 3/2/2020 | 3/3/2020 | 3/3/2020 | A | NR |
Brandon Shaw
|
|
|
Need grades...
|
Meeting | | | 3/3/2020 | | DONE |
|
|
|
*Address was wrong when applicant applied for permit and it was not caught untill the plumbing inspector went out for inspection so the permit was issued to the wrong address, Doug in addressing clarify it with the architect see email in documents, permit was re-printed and email to contractor to sign.
|
(F) Reprint permit | | | 3/3/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/3/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/19/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/19/2020 | | DONE |
|
|
|
|
CHANGE ISSUED DATE | | | 2/19/2020 | | DONE |
|
|
|
Permit issued by mistake 4/9/20, updating issue date to original
|
Telephone call | | | 2/11/2020 | | DONE |
|
|
|
emailed fees to contractor
|
Plan assigned to (M_H) | 12/30/2019 | | 2/7/2020 | | DONE |
Michael Hanson
|
|
|
3rd review completed - 01/09 #518 L2 ePlan - Dr. Paige Schmidt
|
Routing - PLAN CHECK | 2/7/2020 | | 2/7/2020 | | PASS |
Michael Hanson
|
|
|
2 hour plan review fee
|
Permit Ready to Issue | | | 2/7/2020 | | DONE |
|
|
|
MET DREW@MCCARTER-MOORHOUSE.COM
NEED
GC FORM
REVISED VALUE
|
Routing - FIRE | 2/5/2020 | 2/5/2020 | 2/5/2020 | | PASS |
Greg Ruxton
|
|
|
Attached revised comments to case. Issues resolved.
|
Routing - PLAN CHECK | 2/5/2020 | | 2/5/2020 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePlan for corrections required.
|
Routing - PLAN CHECK | 2/4/2020 | | 2/4/2020 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePLan for corrections required.
|
Routing - PLAN CHECK | 1/24/2020 | | 1/24/2020 | | FAIL |
Michael Hanson
|
|
|
|
Route to Impact Fee Review | 1/14/2020 | 1/17/2020 | 1/15/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 1/14/2020 | | FAIL |
Michael Hanson
|
|
|
|
Routing - FIRE | 12/30/2019 | 12/30/2019 | 1/13/2020 | | FAIL |
Greg Ruxton
|
|
|
Attached comments to case and emailed architect.
|
Routing - PLAN CHECK | 12/30/2019 | | 1/8/2020 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePlan for corrections required.
|
Routing PW Environmental | 1/2/2020 | | 1/6/2020 | | PASS |
Rick Christenson
|
|
|
Passed with required amalgam separator as shown.
|
Routing - PUBLIC WORKS | 12/30/2019 | | 1/2/2020 | | PASS |
Morgan Webb
|
|
|
WEST BOISE SEWER DISTRICT
|
Routing - MECHANICAL | 12/30/2019 | | 12/30/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 12/30/2019 | | 12/30/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan , ISPC and NFPA99
|
Routing - Addressing | 12/30/2019 | | 12/30/2019 | | PASS |
Doug Chausow
|
|
|
Corrected address: 7800 W Ustick Rd, Ste 100
|
Intake Approval | | | 12/27/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 12/23/2019 | | FAIL |
Javier Guzman
|
|
|
For prescreen review provide and upload the following:
• Per ePlan submittal standards the reserve the bottom right corner on the drawing plans for the City electronic stamps. Leave a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block on plan sheet A2.1, A0.1 see ePlan standards at https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
• Provide a suspended acoustic ceiling detail section on plans
• Per checklist provide Fire Resistive Assembly Penetrations details for the rated medical gas wall penetration
• Per checklist provide and show Portable Fire Extinguisher locations
|
Application received | | | 12/18/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 18 2019 1:16PM
|