BLD-Framing/Rough-in | 7/31/2020 | 8/3/2020 | 8/3/2020 | A | PASS |
Jim Storey
|
|
|
Chris */Screened*/ *inspection is taking place in non occupied part of the residence. Phone #: ###-####
|
BLD-Energy code compliance | 7/30/2020 | 7/30/2020 | 7/30/2020 | P | PART |
Jim Storey
|
|
|
Chris *screened* Phone #: ###-#### airseal done
|
BLD-Framing/Rough-in | 7/30/2020 | 7/30/2020 | 7/30/2020 | P | PASS |
Jim Storey
|
|
|
Chris *screened* Phone #: ###-####
|
BLD-Wall Bracing | 7/20/2020 | 7/20/2020 | 7/20/2020 | P | PASS |
Jim Storey
|
|
|
Chris *screened* (addtion to home, other part is occupancied* Phone #: ###-####
|
OVERRIDE | | | 6/18/2020 | | |
|
|
|
|
Plan assigned to (J_N) | 5/27/2020 | 5/27/2020 | 6/18/2020 | | DONE |
Jenny Nelson
|
|
|
1st complete 06/02 res plan mod - applicant sending more plans with updates
|
CHANGE STATUS TO (ISS) | | | 6/18/2020 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/18/2020 | | 6/18/2020 | | PASS |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 6/18/2020 | | DONE |
|
|
|
plan mod approved
|
Routing - PLANNING | 6/17/2020 | | 6/17/2020 | | PASS |
Sue Cummings
|
|
|
No ADU approved with this permit
|
Routing - PLANNING | 6/12/2020 | | 6/15/2020 | | PASS |
Sue Cummings
|
|
|
No ADU approved with this permit
|
Plan Reviewer's activity | | | 6/12/2020 | | DONE |
Jenny Nelson
|
|
|
Other changes made to design - resent to planning to make sure latest changes are still ok
|
Routing - PLAN CHECK | 6/12/2020 | | 6/12/2020 | | FAIL |
Jenny Nelson
|
|
|
Deck cantilevered over 1/4 of joist span
|
BLD-Conference | 6/2/2020 | 6/3/2020 | 6/3/2020 | A | PASS |
Jim Storey
|
|
|
Chris *screeend* Phone #: ###-#### floor ok to cover insulated
|
Plan Reviewer's activity | | | 6/3/2020 | | DONE |
Jenny Nelson
|
|
|
Talked with applicant- doing another redesign in addition to deck - will hold off on this plan mod until new plans are ready to upload and do all at once. JJN
|
Routing - PLAN CHECK | 5/27/2020 | | 6/3/2020 | | FAIL |
Jenny Nelson
|
|
|
Sent back to applicant to upload additional changes
|
Routing - PLANNING | 5/27/2020 | | 5/27/2020 | | PASS |
Sue Cummings
|
|
|
|
Plan Modification Accepted | | | 5/21/2020 | | DONE |
|
|
|
Plan mod requested by applicant to modify the deck. Paper to ePlan, original files uploaded.
Route to JAB & Planning as needed
|
BLD-Other | 5/13/2020 | 5/13/2020 | 5/13/2020 | P | PASS |
Jim Storey
|
|
|
Screened- pile inspection- Zack Phone #: ###-####
|
BLD-Footing | 5/11/2020 | 5/12/2020 | 5/12/2020 | P | PART |
Dave Hannah
|
|
|
Zach *screened* Phone #: ###-#### bearing wall ftg ok
|
Routing Walk-In (Zoning) | 12/19/2019 | 12/19/2019 | 12/19/2019 | P | DONE |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 12/19/2019 | 12/19/2019 | 12/19/2019 | P | PASS |
Jenny Nelson
|
|
|
|
1st review completed | | | 12/19/2019 | | DONE |
Jenny Nelson
|
|
|
|
Inspection Record Card- Bld | | | 12/19/2019 | | DONE |
Jenny Nelson
|
|
|
|
Case Summary (BLD) | | | 12/19/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/19/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 12/19/2019 | | DONE |
|
|
|
Need RP
|
Issue PAID IN FULL permit | | | 12/19/2019 | | DONE |
|
|
|
|
Application received | | 12/19/2019 | | | |
|
|
|
|