BLD-Final | 3/16/2020 | 3/19/2020 | 3/19/2020 | P | PASS |
Dave Hannah
|
|
|
Doug Phone #: ###-####
|
FIRE-Final Inspection | 3/16/2020 | 3/19/2020 | 3/19/2020 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguisher will be placed in discussed location and has a current inspection tag. Final life fire safety inspection for area of work complete, signatures provided on permit sign off card.
Doug Phone #: ###-####
|
BLD-Framing/Rough-in | 1/24/2020 | 1/27/2020 | 1/27/2020 | P | PASS |
Dave Hannah
|
|
|
Doug Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/23/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/23/2020 | | DONE |
|
|
|
|
Plan assigned to (JG) | 12/31/2019 | 12/31/2019 | 1/22/2020 | | PASS |
Javier Guzman
|
|
|
01/21 2nd rev L1 Thrivent Financial ePlan
|
Routing - PLAN CHECK | 1/14/2020 | | 1/22/2020 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/22/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/22/2020 | | DONE |
|
|
|
NEED
GC FORM
REVISED VALUE
|
Route to Impact Fee Review | 1/7/2020 | 1/10/2020 | 1/8/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing PW Flood Plain | 12/31/2019 | | 1/3/2020 | | PASS |
Jason C. Taylor
|
|
|
Project does not meet the Substantial Improvements section of Boise Floodplain Ordinance .No floodplain requirements. If you have any questions, please call Jason Taylor at ###-####.
|
1st review completed | | | 1/3/2020 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 12/31/2019 | | 12/31/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - Addressing | 12/31/2019 | | 12/31/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/31/2019 | | 12/31/2019 | | PASS |
Morgan Webb
|
|
|
TALKED WITH CUSTOMER AND THE FIXTURES WERE EXISTING. NO NEW FEES.
|
Intake Approval | | | 12/30/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 12/24/2019 | | FAIL |
Javier Guzman
|
|
|
For prescreen review provide and upload the following:
• Per ePlan submittal standards the reserve the bottom right corner on the drawing plans for City approval stamps. Leave a blank 4” x 4” space located 3” off the right sheet edge to allow for the title block on the cover sheet A1.0. see ePlan standards at https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
|
Application received | | | 12/20/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 20 2019 11:34AM
|