BLD-Other | 7/21/2020 | 7/22/2020 | 7/22/2020 | A | PASS |
Mike Jordan
|
|
|
*Screened* Robert - rebar between party of two permits, complete together Phone #: ###-####. Interior footing ok.
|
BLD-Foundation | 6/12/2020 | 6/15/2020 | 6/15/2020 | P | PASS |
Mike Jordan
|
|
|
On site contact is Robert at ###-#### Phone #: ###-#### Inspection requested via web by Scott Henderson
|
BLD-Footing | 5/27/2020 | 5/28/2020 | 5/28/2020 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 5/19/2020 | 5/22/2020 | 5/21/2020 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Scott Henderson Inspection cancelled from web by: Scott Henderson
|
BLD-Footing | 5/19/2020 | 5/21/2020 | 5/19/2020 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Scott Henderson Inspection cancelled from web by: Scott Henderson
|
BLD-Footing | 5/15/2020 | 5/20/2020 | 5/19/2020 | P | CANC |
Mike Jordan
|
|
|
Same inspection as requested for BLD19-04353. This is one building with property line down the middle, therefore 2 separate permits. Phone #: ###-#### >> Inspection requested via web by Scott Henderson Inspection cancelled from web by: Scott Henderson
|
Issue PAID IN FULL permit | | | 4/17/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/17/2020 | | DONE |
|
|
|
|
Plan assigned to (JG) | 12/20/2019 | 12/20/2019 | 4/8/2020 | | PASS |
Javier Guzman
|
|
|
04/14 4th rev, 502 Office Building at Businesspark Ln
|
Routing - PLAN CHECK | 4/8/2020 | | 4/8/2020 | | PASS |
Javier Guzman
|
|
|
|
Routing - Design Review | 4/8/2020 | | 4/8/2020 | | PASS |
Katelyn Menuge
|
|
|
signed off in ePlan by DR Katelyn Menuge
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/8/2020 | | DONE |
|
|
|
all met: chuck@maxey-tookey.com
Need ACHD
Need GC
Need Revised Values
|
Routing - Design Review | 3/26/2020 | | 4/3/2020 | | FAIL |
Katelyn Menuge
|
|
|
Failed in ePlan by DR Katlyn Menuge
|
Routing - PLAN CHECK | 3/26/2020 | | 4/3/2020 | | PASS |
Javier Guzman
|
|
|
|
Routing - Design Review | 3/5/2020 | | 3/24/2020 | | FAIL |
Katelyn Menuge
|
|
|
Signed off in ePlan by DR Katelym M
|
Routing - PLAN CHECK | 3/5/2020 | | 3/24/2020 | | FAIL |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 3/5/2020 | | 3/9/2020 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 12/30/2019 | 1/2/2020 | 12/31/2019 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 12/20/2019 | | 12/30/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | 12/20/2019 | | 12/30/2019 | | PASS |
Morgan Webb
|
|
|
signed off in ePlan
|
1st review completed | | | 12/30/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 12/20/2019 | 12/20/2019 | 12/27/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - Addressing | 12/20/2019 | | 12/24/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - Erosion and Sediment | 12/20/2019 | | 12/20/2019 | | PASS |
Andy J. Long
|
|
|
Signed off in ePlan by Andy Long
|
Routing Off Site - STRUCTURAL | 12/20/2019 | | 12/20/2019 | | PASS |
Javier Guzman
|
|
|
Signed off in ePlan by AHJ Engineers
|
Routing PW Drainage | 12/20/2019 | | 12/20/2019 | | PASS |
Brian Murphy
|
|
|
Signed off in ePlan by Brian Murphy
|
Routing PW Street Lights | 12/20/2019 | | 12/20/2019 | | PASS |
Tom Marshall
|
|
|
Signed off in ePlan by Tom Marshall
|
Routing PW Sewer Design | 12/20/2019 | | 12/20/2019 | | PASS |
DeAnn Brown
|
|
|
Signed off in ePlan by DeAnn Brown
|
Routing PW Solid Waste | 12/20/2019 | | 12/20/2019 | | PASS |
Evan Carpenter
|
|
|
Signed off in ePlan by Evan Carpenter
|
Routing - MECHANICAL | 12/20/2019 | | 12/20/2019 | | PASS |
Troy James
|
|
|
Signed off in ePlan by Troy James
|
Routing - PLUMBING | 12/20/2019 | | 12/20/2019 | | PASS |
Daryl Spivey
|
|
|
Signed off in ePlan by Daryl Spivey
|
Routing - PLANNING | 12/20/2019 | | 12/20/2019 | | PASS |
Karla Nelson
|
|
|
signed off in ePlan by Karla Nelson
|
Routing - Design Review | 12/20/2019 | | 12/20/2019 | | FAIL |
Katelyn Menuge
|
|
|
Failed in ePlan by KBM
|
Intake Approval | | | 12/20/2019 | | PASS |
Javier Guzman
|
|
|
|
Application received | | 12/20/2019 | | | |
|
|
|
|