First Notice | | 7/20/2020 | 8/11/2020 | | DONE |
|
|
|
mailed 8-14-2020
|
Permanent Occupancy | | | 7/10/2020 | | DONE |
|
|
|
|
BLD-Final | 7/7/2020 | 7/8/2020 | 7/8/2020 | A | PASS |
Mike Jordan
|
|
|
Bubba *screened* Phone #: ###-####. Handrails for ramp have been installed. Ok for perm occ.
|
BLD-Final | 6/12/2020 | 6/15/2020 | 6/15/2020 | A | PART |
Mike Jordan
|
|
|
Bubba Phone #: ###-####. Ok for temp occ. Ramp from rear exit exceeds 5% slope and will require handrails.
|
BLD-Final | 6/11/2020 | 6/12/2020 | 6/12/2020 | P | PEND |
Mike Jordan
|
|
|
Bubba Phone #: ###-####. Need to verify slope of ramp on south side of building. Aslo needs public works sign off?
|
FIRE-Final Inspection | 6/11/2020 | 6/12/2020 | 6/12/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Phone #: ###-####
|
BLD-Final | 6/9/2020 | 6/11/2020 | 6/11/2020 | P | CANC |
Mike Jordan
|
|
|
Bubba Phone #: ###-####. Cancelled by contractor via phone call.
|
FIRE-Final Inspection | 6/9/2020 | 6/11/2020 | 6/11/2020 | A | FAIL |
Troy Cobbley
|
|
|
Need to repair west exit discharge light and provide testing, as discussed, for the duct smoke detectors.
Bubba Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 5/21/2020 | 5/22/2020 | 5/22/2020 | A | PASS |
Brandon Shaw
|
|
|
screened // Bubba Phone #: ###-####
|
BLD-Framing/Rough-in | 4/16/2020 | 4/16/2020 | 4/16/2020 | P | PASS |
Mike Jordan
|
|
|
Carven **cleared** Phone #: ###-####. Interior steel stud framed walls ok. hardlids and soffits ok pending MEP's rough in inspections.
|
Issue PAID IN FULL permit | | | 3/16/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/16/2020 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/26/2020 | | 2/26/2020 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/26/2020 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 2/26/2020 | | DONE |
|
|
|
MET BREANNA@ELDERJONES.COM
Need
GC Form
Revised Cert of Value
|
Routing - PLAN CHECK | 2/25/2020 | | 2/25/2020 | | FAIL |
Michael Hanson
|
|
|
Door hardware corrections required. See changemark on A011.
|
Plan assigned to (M_H) | 1/7/2020 | | 2/25/2020 | | DONE |
Michael Hanson
|
|
|
2nd review completed - 01/21 #518 L2 ePlan - HH Retail
|
Plan Reviewer's activity | | | 1/30/2020 | | DONE |
Michael Hanson
|
|
|
Discuseed corrections required with applicant prior to resubmittal via telephone call.
|
Route to Impact Fee Review | 1/24/2020 | 1/27/2020 | 1/27/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 1/7/2020 | 1/7/2020 | 1/24/2020 | | PASS |
Erika Akin
|
|
|
No comments attached
|
1st review completed | | | 1/24/2020 | | FAIL |
Michael Hanson
|
|
|
|
Routing Off Site - STRUCTURAL | 1/7/2020 | | 1/21/2020 | | PASS |
Michael Hanson
|
|
|
Per approval on ePlan by D. Haugland @ AHJ engineering.
|
Routing - PLAN CHECK | 1/7/2020 | | 1/21/2020 | | FAIL |
Michael Hanson
|
|
|
See changemarks for corrections required.
|
Routing - MECHANICAL | 1/7/2020 | | 1/16/2020 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 1/7/2020 | | 1/9/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/7/2020 | | 1/8/2020 | | PASS |
Morgan Webb
|
|
|
CREDIT FOR DEMO. NO NEW FEES
|
Routing - PLUMBING | 1/7/2020 | | 1/8/2020 | | PASS |
Dan Ediger
|
|
|
Per plans and ISPC
|
Routing - Design Review | 1/7/2020 | | 1/7/2020 | | PASS |
Michaella Owens
|
|
|
|
Intake Approval | | | 1/7/2020 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 12/24/2019 | | FAIL |
Javier Guzman
|
|
|
For prescreen review provide and upload the following:
• The uploaded engineering structural calculations is required to be stamped, signed and dated by an Idaho licensed engineer
• The uploaded structural “S” plan sheets are required to be stamped, signed and dated by an Idaho licensed engineer
• Provide engineering calculations for the new exterior CMU opening. engineering structural calculations are required to be stamped, signed and dated by an Idaho licensed engineer.
• Provide DR/Planning & Zoning letters of approval.
• Per ePlan submittal standards the reserve the bottom right corner on the drawing plans for City approval stamps. Leave a blank 4” x 4” space located 3” off the right sheet edge to allow for the title block on the cover sheet G000. see ePlan standards at https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
• Per ePlan submittal standards the reserve the bottom right corner on the drawing plans for the City electronic stamps. Leave a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block on plan sheet AD101, A011, A101, A211, A401, A402, A502, A503, A610, A611, G002, G004, E1.1, E1.0, M1.0, M2.0, P1.0 see ePlan standards at https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
• Provide and show location of the fire extinguishers
|
Application received | | | 12/20/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 20 2019 2:51PM
|
Second Notice | | 8/21/2020 | | | |
|
|
|
|