Permit Information
Permit NumberBLD19-04920
StatusIssued
Name STRAIGHT LINE BUILDING SOLUTIONS LL
Site Address 2611 S FRY ST
Project NameWest Airport Ind Park - Bldg D
Customer Number 
ePlanReviewYes
Description
(WEST AIRPORT INDUSTRIAL PARK – BLDG D – 1ST BUILDING FROM THE EAST – WAREHOUSE SHELL) (DRH18-00264 and DRH18-00332) The fire sprinkler system is used for building area increase and for fire area. To construct a new 28,416 square foot warehouse shell building (380’ x 75’ exterior dimensions). Work is to include concrete footings, concrete tilt-up wall panels, concrete floor slabs on grade, steel columns with steel baseplates and anchors, steel roof girder trusses, steel roof trusses, metal roof deck, insulation on top of the roof deck, single-ply TPO roof membrane, domed plastic skylights, wall insulation, exterior overhead doors, exterior storefront windows, exterior doors, exterior steel stairways with steel landings, two trash enclosures with steel gates, steel awnings with steel support tie-back rods, a keystone block retaining wall at the sloped grade, a 40 foot wide concrete apron at the loading dock area, and a 1-hr fire sprinkler riser room with an exterior door. Special inspection is required for soils, concrete, steel (including welding and bolting), and anchors post-installed in hardened concrete. Future roof top HVAC units weighing 750 pounds each were anticipated. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. This permit is not intended to establish a Certificate of Occupancy for any portion of this building. Separate permits are required to establish occupancy. A service sink and perhaps drinking fountains and two toilet rooms for each tenant space will be required. **MDH**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Concrete7/10/20207/13/20207/13/2020APART
DetailsMike Jordan
trash walls Phone #: ###-#### Inspection requested via web by Todd Landvatter
BLD-Concrete7/9/20207/9/20207/10/2020PPART
DetailsMike Jordan
ready at 3 Eric will be here to reinspect for MTI also. Phone #: ###-#### Inspection requested via web by Todd Landvatter. Ok to place concrete pending special inspection.
BLD-Concrete7/7/20207/9/20207/9/2020ANR
DetailsMike Jordan
rebar wall panels Phone #: ###-#### Inspection requested via web by Todd Landvatter
BLD-Footing7/7/20207/8/20207/8/2020APASS
DetailsMike Jordan
concrete at 11AM Phone #: ###-#### Inspection requested via web by Todd Landvatter. Footings for trash enclosures.
BLD-Concrete7/1/20207/7/20207/7/2020ACANC
DetailsMike Jordan
wall panel rebar Phone #: ###-#### >> Inspection requested via web by Todd Landvatter Inspection cancelled from web by: Todd Landvatter
BLD-Footing6/10/20206/11/20206/11/2020APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Todd Landvatter. west exterior footing.
BLD-Footing6/3/20206/4/20206/4/2020APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Todd Landvatter. Clearance issues have been resolved.
BLD-Footing6/2/20206/3/20206/3/2020AFAIL
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Todd Landvatter. Noted several areas with insufficient clearances and needs to clean out step footings areas.
BLD-Concrete5/31/20206/1/20206/1/2020APART
DetailsMike Jordan
wall panels rebar Phone #: ###-#### Inspection requested via web by Todd Landvatter
BLD-Other5/19/20205/21/20205/21/2020PPART
DetailsMike Jordan
steel rebar wall panels Phone #: ###-#### Inspection requested via web by Todd Landvatter. Work in progress. Inspected 3 random panels, ok. Ok to place concrete pending special inspection.
BLD-Foundation4/13/20204/13/20204/13/2020APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Todd Landvatter. Reinforcement for inteior slab on grade.
BLD-Footing4/3/20204/6/20204/6/2020APASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Todd Landvatter. Interior column pad footings ok.
BLD-Conference3/17/20203/17/20203/17/2020ADONE
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Todd Landvatter
Issue PAID IN FULL permit  2/27/2020 DONE
Inspection Record Card- Bld  2/27/2020 DONE
Telephone call  2/26/2020 DONE
Spoke with Brian informing him that he'll just need to shoot over a 302 and the name of the RP. Also informed him we would need a letter from ACHD about fees and inspection
OVERRIDE  2/20/2020  
Routing Off Site - STRUCTURAL2/20/2020 2/20/2020 PASS
DetailsMichael Hanson
KPFF
PLANS/APPL TAKEN TO FRONT DESK  2/20/2020 DONE
DetailsMichael Hanson
Permit Ready to Issue  2/20/2020 DONE
met
NEED
ACHD (see19-04921)
RP
GC FORM
REVISED VALUE
Plan assigned to (M_H)12/31/2019 2/20/2020 DONE
DetailsMichael Hanson
1st review completed - 02/07 #502 L3 ePlan - Building D New
Routing PW Drainage2/13/2020 2/13/2020 PASS
DetailsBrian Murphy
Route to Impact Fee Review2/11/20202/14/20202/12/2020 PASS
DetailsTravis P Black
Review requested for Commercial Permit
Routing - FIRE12/31/201912/31/20192/11/2020 PASS
DetailsGreg Ruxton
Fire code review attached to case. 02/07 #502 L3 ePlan - Building D New
1st review completed  2/11/2020 FAIL
DetailsMichael Hanson
Routing - PLAN CHECK12/31/2019 2/7/2020 PASS
DetailsMichael Hanson
Routing Off Site - STRUCTURAL12/31/2019 2/5/2020 FAIL
DetailsMichael Hanson
See corrections required in ePlan from KPFF engineering.
Routing PW Drainage1/2/2020 1/8/2020 FAIL
DetailsBrian Murphy
NEED FRY ST CIVILS
Routing PW Street Lights1/2/2020 1/7/2020 PASS
DetailsTom Marshall
Routing - PLANNING12/31/2019 1/7/2020 PASS
DetailsDavid Moser
See DRH18-00332
Routing - MECHANICAL12/31/2019 1/6/2020 PASS
DetailsTroy James
Routing PW Environmental1/2/2020 1/6/2020 PASS
DetailsRick Christenson
Routing PW Sewer Design1/2/2020 1/3/2020 PASS
DetailsDeAnn Brown
Sewer service built under GRD18-00063.
Routing PW Solid Waste1/2/2020 1/2/2020 PASS
DetailsEvan Carpenter
Routing - PLUMBING12/31/2019 1/2/2020 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - Addressing12/31/2019 1/2/2020 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS12/31/2019 1/2/2020 PASS
DetailsMorgan Webb
NO PLUMBING FIXTURES SHOWN ON PLANS.
Routing - Erosion and Sediment12/31/2019 1/2/2020 PASS
DetailsMichael Zawacki
RP needed.
Talked to engineer and using same swppp as previous phase. Maps will be updated at field level.
Routing - Design Review12/31/2019 1/2/2020 PASS
DetailsKatelyn Menuge
Intake Approval  12/30/2019 PASS
Intake Approval  12/23/2019 FAIL
DetailsJavier Guzman
For prescreen review provide and upload the following:
• Per checklist provide DR/Planning & Zoning letters of approval.
• Per ePlan submittal standards the reserve the bottom right corner on the drawing plans for the City electronic stamps. Leave a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block on all the structural “S” plan sheets. see ePlan standards at https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
Application received  12/20/2019 DONE
Application submitted via PDS Online on Dec 20 2019 4:49PM