BLD-Framing/Rough-in | 7/8/2020 | 7/9/2020 | 7/9/2020 | A | PASS |
Tell Riley
|
|
|
Cody - /*Screened*/ Phone #: ###-####//plumbing permit added to BLD//ok to cover//
|
BLD-Framing/Rough-in | 7/7/2020 | 7/8/2020 | 7/8/2020 | A | NR |
Jim Storey
|
|
|
Cody *screeend* Phone #: ###-#### c/n need plm permits as required before.
|
BLD-Framing/Rough-in | 6/2/2020 | 6/3/2020 | 6/3/2020 | A | PART |
Tell Riley
|
|
|
cody Phone #: ###-####//need to add header over door per engineering//need insulation values specified and installed//all trades to face mount on rated walls/ceilings//need plumbing approval prior to cover//
|
CHANGE STATUS TO (ISS) | | | 5/29/2020 | | DONE |
|
|
|
|
(F) Reprint permit | | | 5/29/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/21/2020 | | DONE |
|
|
|
DO NOT ISSUE- plan mod approved
|
Plan assigned to (JG) | 4/29/2020 | 4/29/2020 | 5/20/2020 | | PASS |
Javier Guzman
|
|
|
05/15 Plan Mod Idaho Asian Plaza - Fire Riser ePlan
|
Routing - PLAN CHECK | 4/29/2020 | | 5/20/2020 | | PASS |
Javier Guzman
|
|
|
|
Routing - FIRE | 5/11/2020 | 5/11/2020 | 5/18/2020 | | PASS |
Erika Akin
|
|
|
Plan Mod Passed **JHB** Exterior walls of the fire riser room not required to be 1-hour fire rated. Fire Riser Interior walls and roof/ceiling assembly have 1-hour fire rating. 05/15 Plan Mod Idaho Asian Plaza - Fire Riser ePlan
|
BLD-Framing/Rough-in | 5/6/2020 | 5/7/2020 | 5/7/2020 | A | NR |
Mike Jordan
|
|
|
Call to meet // Cody Phone #: ###-####. Plan mod still under review...
|
Plan Reviewer's activity | | | 5/5/2020 | | DONE |
Javier Guzman
|
|
|
For plan mod prescreen review provide and upload the following:
• Provide a completed 522 plan mod application, application can be found at https://www.cityofboise.org/media/5655/522_planmod.pdf
|
Plan Modification Accepted | | | 4/29/2020 | | DONE |
|
|
|
The contractor changed out the type of assembly and I listed the exterior walls as being 1-hr rated which they do not need to be.
|
BLD-Framing/Rough-in | 4/16/2020 | 4/17/2020 | 4/17/2020 | A | FAIL |
Tell Riley
|
|
|
Cody **cleared**Phone #: ###-####//CN posted onsite near front door//
|
Inspection Record Card- Bld | | | 4/17/2020 | | DONE |
|
|
|
|
BLD-Foundation | 3/26/2020 | 3/26/2020 | 3/26/2020 | P | PASS |
Dave Hannah
|
|
|
rebar as late as possible // sadauge Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/2/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/2/2020 | | DONE |
|
|
|
|
Telephone call | | | 3/2/2020 | | DONE |
|
|
|
emailed permit to be signed to keith@datumconstruction.com EPLAN will need to be release
|
Plan assigned to (JG) | 1/7/2020 | 1/7/2020 | 2/21/2020 | | PASS |
Javier Guzman
|
|
|
02/27 3rd Rev L2 Idaho Asian Plaza - Fire Riser ePlan
|
Plan Reviewer's activity | | | 2/21/2020 | | DONE |
Javier Guzman
|
|
|
sent back to applicant: Per ePlan submittal standards the reserve the bottom right corner on the revised structural drawing plans for City approval stamps. leave a blank 4” x 4” space located 3” off the right sheet edge to allow for the title block. see ePlan standards at https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
|
Routing - PLAN CHECK | 2/21/2020 | | 2/21/2020 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/21/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/21/2020 | | DONE |
|
|
|
all met: gwalker@adpboise.com
Need
GC Form
Revised Cert of Value
|
Routing - PLAN CHECK | 2/10/2020 | | 2/14/2020 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 2/10/2020 | 2/10/2020 | 2/11/2020 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Route to Impact Fee Review | 1/21/2020 | 1/24/2020 | 1/22/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 1/7/2020 | 1/7/2020 | 1/21/2020 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
1st review completed | | | 1/21/2020 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 1/7/2020 | | 1/21/2020 | | FAIL |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 1/7/2020 | | 1/14/2020 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 1/7/2020 | | 1/7/2020 | | PASS |
Katelyn Menuge
|
|
|
No tenant proposed or approved.
|
Intake Approval | | | 1/3/2020 | | |
Javier Guzman
|
|
|
|
Intake Approval | | | 12/31/2019 | | FAIL |
Brian McGowan
|
|
|
Please provide or address the following for your Prescreen to be approved;
1. The proper form submitted should be a 502 for a New Commercial Addition
2. The Structural Sheets have the Engineers stamp and signature placed where the City Approval Stamp will go. Please relocate the Engineer's stamp.
|
Application received | | | 12/26/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 26 2019 9:22AM
|