BLD-Final | 7/20/2020 | 7/20/2020 | 7/20/2020 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
DOC - Permit Finaled | 7/20/2020 | 7/20/2020 | 7/20/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 7/20/2020 | 7/20/2020 | 7/20/2020 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.86
|
PubWorks Occupancy Approval | 7/20/2020 | 7/20/2020 | 7/20/2020 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department Jason Taylor ###-####.
|
BLD-Final | 7/17/2020 | 7/17/2020 | 7/17/2020 | P | NR |
Brandon Shaw
|
|
|
Need PW approval...
|
BLD-Other | 4/13/2020 | 4/13/2020 | 4/13/2020 | P | PASS |
Dave Hannah
|
|
|
Soffit. Can you do this morning when you inspect 22-2 HN? Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Energy code compliance | 4/3/2020 | 4/6/2020 | 4/6/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Framing/Rough-in | 4/1/2020 | 4/2/2020 | 4/2/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Wall Bracing | 3/5/2020 | 3/5/2020 | 3/5/2020 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Kyle Seick
|
BLD-Foundation | 2/17/2020 | 2/18/2020 | 2/18/2020 | A | PASS |
Jim Storey
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 2/14/2020 | 2/14/2020 | 2/14/2020 | A | PASS |
Brandon Shaw
|
|
|
Work in progress... Frost protection is required...
|
BLD-Footing | 2/13/2020 | 2/13/2020 | 2/14/2020 | P | NR |
Dave Hannah
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
PubWorks Subgrade Approval | 2/13/2020 | 2/13/2020 | 2/13/2020 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 1/30/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/30/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 1/27/2020 | | |
|
|
|
|
Plan assigned to (D_S) Debbie | 1/7/2020 | 1/7/2020 | 1/27/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 1/27/2020 | | 1/27/2020 | | PASS |
Jenny Nelson
|
|
|
Per D_S review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/27/2020 | | DONE |
Debbie Sanine
|
|
|
|
Permit Ready to Issue | | | 1/27/2020 | | DONE |
|
|
|
met
|
Routing PW Grading-Hillside | 1/7/2020 | | 1/16/2020 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
1st review completed | | | 1/16/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 1/7/2020 | | 1/16/2020 | | FAIL |
Jenny Nelson
|
|
|
Per D_S reivew
|
Routing - MECHANICAL | 1/7/2020 | | 1/13/2020 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 1/7/2020 | 1/7/2020 | 1/9/2020 | | PASS |
Mark Stumbaugh
|
|
|
No Fire Sprinkler Required.
New SFH
|
Routing - PLANNING | 1/7/2020 | | 1/9/2020 | | PASS |
Sue Cummings
|
|
|
|
Route to Impact Fee Review | 1/7/2020 | 1/10/2020 | 1/8/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 1/7/2020 | | 1/8/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - Erosion and Sediment | 1/7/2020 | | 1/8/2020 | | PASS |
Michael Zawacki
|
|
|
|
Routing - PUBLIC WORKS | 1/7/2020 | | 1/7/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/7/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/7/2020 | | DONE |
|
|
|
|
Intake Approval | | | 1/7/2020 | | PASS |
|
|
|
|
Application received | | | 12/30/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 30 2019 10:03AM
|
Intake Approval | | | 12/30/2019 | | FAIL |
|
|
|
Please upload erosion narrative in documents folder (only ESC plan was uploaded)
|