Permit Information
Permit NumberBLD19-04985
StatusIssued
Name TODD CAMPBELL CONSTRUCTION
Site Address 13864 W MEADOWDALE ST
Project NameTodd Campbell Office Building
Customer Number 
ePlanReviewYes
Description
(TODD CAMPBELL OFFICE BUILDING - shell and interior build out) Permit to construct a new 6,260 sqft. building and related site improvements. No occupancy allowed under this permit. Future tenants shall apply for certificate of occupancy prior to occupying either vacant space. Scope of work includes: construction of a reinforced concrete foundation with crawlspace, construction of wood stud framed exterior and interior walls, P.E. roof trusses, two accessible restrooms, one non-accessible 2nd floor restroom, a kitchen, installation of new windows and doors, new electrical, new mechanical, new plumbing, site work, and interior finishes. Interior finishes are to be in compliance with Ch. 8 of the 2015 IBC. New structures are required to be fully accessible in compliance with A117.4-2009. The building is not fire sprinkled. Note: Special Inspections Required see form 310. **MDH**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Foundation8/10/20208/11/20208/11/2020PPART
DetailsTell Riley
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate //work in progress....adding 2nd bar for 2 bars in top of wall, cutting verts for clearance//
BLD-Footing8/9/20208/10/20208/10/2020APART
DetailsTell Riley
Phone #: 6971241 >> Inspection requested via mobile web by Heron //footings ok,, setbacks ok on sides and front//rear has a 1' pop out into setback, talked with contractor on phone, they will be deleting the popout, a plan modification will be completed//WIP on footings and rear pending plan modification approval//
BLD-Footing8/6/20208/7/20208/7/2020PCANC
DetailsTell Riley
Phone #: 2086971241 >> Inspection requested via mobile web by heron Inspection cancelled via mobile web on Friday, August 07, 2020.
BLD-Footing8/4/20208/4/20208/4/2020PFAIL
DetailsTell Riley
need small documents and form 310 for special inspections//site plan shows rear setback of 10 feet minimum, current site conditions set at 8'//talked with general contractor, will need to submit for 8' setback or meet minimums on site plan A101//
Plan assigned to (M_H)2/11/2020 7/21/2020 DONE
DetailsMichael Hanson
3rd review completed - 03/18 #502 L3 ePlan - Todd Campbell Office Bldg
BLD-Other7/13/20207/14/20207/14/2020ACANC
DetailsBrandon Shaw
Erosion inspection Phone #: ###-#### Inspection requested via web by Todd Campbell
Issue PAID IN FULL permit  7/13/2020 DONE
Inspection Record Card- Bld  7/13/2020 DONE
OVERRIDE  7/1/2020  
Routing Off Site - STRUCTURAL6/29/2020 7/1/2020 PASS
DetailsMichael Hanson
AHJ
PLANS/APPL TAKEN TO FRONT DESK  7/1/2020 DONE
DetailsMichael Hanson
Permit Ready to Issue  7/1/2020 DONE
ALL MET Dean Waite
ACHD
GC Form
Revised Cert of Value

met: RP
Routing Off Site - STRUCTURAL6/2/2020 6/9/2020 FAIL
DetailsMichael Hanson
AHJ
Routing - FIRE6/4/20206/4/20206/4/2020 PASS
DetailsGreg Ruxton
Attached comments to case.
Routing PW Drainage5/22/2020 5/22/2020 PASS
DetailsBrian Murphy
existing pad siteparking lots,stormwater system commercial sub approval
Routing Off Site - STRUCTURAL5/13/2020 5/22/2020 FAIL
DetailsMichael Hanson
AHJ
Routing - FIRE5/15/20205/15/20205/15/2020 FAIL
DetailsGreg Ruxton
Attached comments to case and emailed architect.
Routing - Design Review5/14/2020 5/14/2020 PASS
DetailsKayCee Babb
Per DRH19-00471
Routing - PLANNING5/14/2020 5/14/2020 PASS
DetailsNicolette Womack
Route to Impact Fee Review3/25/20203/28/20203/26/2020 PASS
DetailsTravis P Black
Review requested for Commercial Permit
1st review completed  3/25/2020 FAIL
DetailsMichael Hanson
Routing - FIRE2/11/20202/11/20203/24/2020 FAIL
DetailsGreg Ruxton
Attached comments to case and emailed architect. GR
Routing Off Site - STRUCTURAL2/11/2020 3/23/2020 FAIL
DetailsMichael Hanson
AHJ
Routing - PLAN CHECK2/11/2020 3/23/2020 PASS
DetailsMichael Hanson
Routing PW Drainage2/12/2020 2/21/2020 FAIL
NEED DRAINAGE REPORT OAND M APNDX J
Routing PW Environmental2/12/2020 2/18/2020 PASS
DetailsRick Christenson
Routing - MECHANICAL2/11/2020 2/14/2020 PASS
DetailsChad Schwendiman
Routing PW Solid Waste2/12/2020 2/13/2020 PASS
DetailsEvan Carpenter
Sharing solid waste service with the property to the east.
Routing PW Street Lights2/12/2020 2/13/2020 PASS
DetailsTom Marshall
Routing PW Sewer Design2/12/2020 2/12/2020 PASS
DetailsDeAnn Brown
Routing - Design Review2/11/2020 2/12/2020 FAIL
DetailsKayCee Babb
Submittal did not comply with conditions of approval of DRH19-00471. Cross access/shared parking agreement needs to be provided. Landscape plan needs to show proposed and existing trees to verify plan compliance. Accessible parking stall/ramp needs to be the same on all plans.
Routing - Addressing2/11/2020 2/12/2020 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS2/11/2020 2/12/2020 PASS
DetailsCandy A. Nichols
Routing - PLUMBING2/11/2020 2/12/2020 PASS
DetailsDaryl Spivey
Per plan and ISPC
Routing - PLANNING2/11/2020 2/11/2020 FAIL
DetailsNicolette Womack
As conditioned by DR, required to provide a shared parking agreement.
Routing - Erosion and Sediment2/11/2020 2/11/2020 PASS
DetailsMichael Zawacki
RP needed. Site prep required. Plan ok due to nonenviromental location.
Intake Approval  2/6/2020 PASS
DetailsMichael Hanson
Intake Approval  1/27/2020 FAIL
DetailsMichael Hanson
01/22/2020
See red mark ups that are now clouded as unresolved on the 502 checklist for corrections required to pass prescreen.
Intake Approval  1/7/2020 FAIL
DetailsMichael Hanson
See red mark ups on 502 checklist provided.
Application received  12/31/2019 DONE
Application submitted via PDS Online on Dec 31 2019 10:43AM