BLD-Wall Bracing | 4/22/2020 | 4/23/2020 | 4/23/2020 | A | PASS |
Mike Jordan
|
|
|
Melissa **cleared** Phone #: ###-####
|
BLD-Wall Bracing | 4/20/2020 | 4/22/2020 | 4/22/2020 | A | FAIL |
Mike Jordan
|
|
|
new build screened Shear // Melissa Phone Phone #: ###-####. Provide the city set of approved plans. Noted several areas missing fasteners, need to nail off holddowns. Provide hot dipped galvanized nails into sill plate. Correction notice posted.
|
BLD-Footing | 3/9/2020 | 3/10/2020 | 3/9/2020 | A | PASS |
Mike Jordan
|
|
|
Hello, If at all possible I would really appreciate if you could come by this afternoon as we discussed on the phone a little bit ago. It would be really nice to be able to get the garage pad and porch poured today, which is the footings that are needing the inspection, if at all possible. Thank you! Phone #: ###-#### Inspection requested via web by Melissa Davies. Interior column pad footings and thickend foorings in garage.
|
BLD-Conference | 2/28/2020 | 2/28/2020 | 2/28/2020 | P | DONE |
Tell Riley
|
|
|
Would like an inspection, the foundation is poured and ready for backfill. Phone #: ###-#### Inspection requested via web by Melissa Davies//talked with Melissa, scheduled inspection for damp proofing//let her know city of Boise typically does not inspect the damp proofing prior to backfill//next inspection would be wall bracing//
|
BLD-Foundation | 2/20/2020 | 2/21/2020 | 2/21/2020 | P | PART |
Mike Jordan
|
|
|
wall // Sammie Phone #: ###-####
|
BLD-Footing | 2/19/2020 | 2/19/2020 | 2/19/2020 | P | PART |
Mike Jordan
|
|
|
|
BLD-Footing | 2/18/2020 | 2/19/2020 | 2/19/2020 | A | FAIL |
Mike Jordan
|
|
|
Sammie Phone #: ###-####. footing subgrade frozen. Concrete contractor will uncover footings to let thaw. Will reinspect in the pm.
|
Issue PAID IN FULL permit | | | 2/5/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/5/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 1/16/2020 | | |
|
|
|
|
Plan assigned to (RDP) | 1/6/2020 | 1/6/2020 | 1/16/2020 | | DONE |
Rob Patrick
|
|
|
01/17 sfd L1 ePlan...01/13 Failed
|
Routing - PLAN CHECK | 1/16/2020 | | 1/16/2020 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/16/2020 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 1/16/2020 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/6/2020 | | 1/13/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
1st review completed | | | 1/13/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Route to Impact Fee Review | 1/6/2020 | 1/9/2020 | 1/8/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 1/6/2020 | | 1/8/2020 | | PASS |
Sue Cummings
|
|
|
See redlines. Max. driveway width is 33 ft. in the front setback.
|
Routing - Addressing | 1/6/2020 | | 1/8/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/6/2020 | | 1/7/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Routing - MECHANICAL | 1/6/2020 | | 1/7/2020 | | PASS |
Troy James
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/6/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/6/2020 | | DONE |
|
|
|
|
Intake Approval | | | 1/6/2020 | | PASS |
|
|
|
|
Application received | | | 12/31/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 31 2019 3:51PM
|