BLD-Energy code compliance | 7/2/2020 | 7/2/2020 | 7/2/2020 | P | PASS |
Tony Young
|
|
|
James Phone #: ###-####
|
BLD-Framing/Rough-in | 6/29/2020 | 6/30/2020 | 6/30/2020 | A | PASS |
Tony Young
|
|
|
james Phone #: ###-####
|
BLD-Wall Bracing | 5/14/2020 | 5/14/2020 | 5/14/2020 | P | PASS |
Tony Young
|
|
|
James *screened* Phone #: ###-####
|
BLD-Wall Bracing | 5/13/2020 | 5/14/2020 | 5/14/2020 | A | PART |
Tony Young
|
|
|
James *screened* Phone #: ###-####// work in progress
|
BLD-Wall Bracing | 5/12/2020 | 5/13/2020 | 5/14/2020 | P | NR |
Tony Young
|
|
|
James *screened* Phone #: ###-####
|
BLD-Foundation | 4/24/2020 | 4/27/2020 | 4/27/2020 | A | PASS |
Tony Young
|
|
|
screened // Pat Phone #: ###-####
|
BLD-Footing | 4/23/2020 | 4/24/2020 | 4/24/2020 | A | PASS |
Tony Young
|
|
|
Pat Phone #: ###-####
|
BLD-Footing | 4/16/2020 | 4/17/2020 | 4/20/2020 | P | CANC |
Tony Young
|
|
|
Screened- PAT Phone #: ###-####
|
BLD-Footing | 3/23/2020 | 3/24/2020 | 3/24/2020 | P | NR |
Dave Hannah
|
|
|
Pat Phone #: ###-####
|
Telephone call | | | 3/6/2020 | | DONE |
|
|
|
Possible large plan mod to change floorplan of the house to new plan. Permit already issued and will need to be reviewed by planning, mech, and plan check. New man J required and res check if thermal env. change.
|
Issue PAID IN FULL permit | | | 2/13/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/13/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 2/3/2020 | | |
|
|
|
|
Plan assigned to (J_N) | 1/15/2020 | 1/15/2020 | 2/3/2020 | | DONE |
Jenny Nelson
|
|
|
01/28 sfd L1 ePlan. 1st complete 01/22, 1 hour soffit, waiting for planning
|
Routing - PLAN CHECK | 2/3/2020 | | 2/3/2020 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/3/2020 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 2/3/2020 | | DONE |
|
|
|
|
Routing - PLANNING | 1/23/2020 | | 1/27/2020 | | PASS |
Leon Letson
|
|
|
|
1st review completed | | | 1/27/2020 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 1/15/2020 | | 1/23/2020 | | FAIL |
Jenny Nelson
|
|
|
1 hour soffit
|
Routing - MECHANICAL | 1/15/2020 | | 1/17/2020 | | FAIL |
Troy James
|
|
|
Floor plan for building does not match. Emailed the applicant to provide the correct floor plan for the job.
|
Routing - MECHANICAL | 1/17/2020 | | 1/17/2020 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 1/15/2020 | 1/18/2020 | 1/16/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Recd Pcfee & Taken To Pln CK | | | 1/15/2020 | | DONE |
|
|
|
|
Intake Approval | | | 1/15/2020 | | PASS |
|
|
|
|
Routing - PLANNING | 1/15/2020 | | 1/15/2020 | | DONE |
Sue Cummings
|
|
|
I sent to Leon
|
Routing - Addressing | 1/15/2020 | | 1/15/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/15/2020 | | 1/15/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 1/14/2020 | | FAIL |
|
|
|
need to upload electrical plan with the same name so that it can version over. Talked to applicant.
|
Intake Approval | | | 1/10/2020 | | FAIL |
|
|
|
1st Prescreen Review Comments:
1. Please upload ACCA approved Manual J for Furnace/HVAC system
2. Provide prescriptive energy table for insulation. (R-values and Fenestration requirements)
3. If there is an attic, please show attic access in drawing
|
Intake Approval | | | 1/10/2020 | | FAIL |
|
|
|
not all corrections were made. applicant called to have the task sent back to him
|
Intake Approval | | | 1/10/2020 | | FAIL |
|
|
|
new ele was wrong size and not named that same
|
Application received | | | 1/3/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 3 2020 10:51AM
|