BLD-Energy code compliance | 8/11/2020 | 8/12/2020 | 8/12/2020 | A | PASS |
Mike Jordan
|
|
|
interior wall insulation to cover Phone #: ###-#### Inspection requested via web by todd smock
|
BLD-Framing/Rough-in | 8/11/2020 | 8/12/2020 | 8/12/2020 | A | PASS |
Mike Jordan
|
|
|
joist engineering and missed a34/lu hangers installed. Phone #: ###-#### Inspection requested via web by todd smock. Fireblocking has been installed.
|
BLD-Framing/Rough-in | 8/7/2020 | 8/10/2020 | 8/10/2020 | A | PASS |
Mike Jordan
|
|
|
Interior Wall rough in complete to sheet rock 1 side Phone #: ###-#### Inspection requested via web by todd smock. Ok to one side. Needs to complterte fireblocking.
|
BLD-Energy code compliance | 8/3/2020 | 8/5/2020 | 8/5/2020 | A | PASS |
Mike Jordan
|
|
|
Inspection requested for Exterior Wall Inspection to Cover Phone #: ###-#### Inspection requested via web by todd smock. Ok to sheet rock exterior walls only.
|
BLD-Framing/Rough-in | 8/5/2020 | 8/5/2020 | 8/5/2020 | A | PART |
Mike Jordan
|
|
|
Inspection requested for Exterior Wall Inspection to Cover Phone #: ###-#### Inspection requested via web by todd smock. Needs to complete lateral bracing on trusses, fire block furred walls and provide engineering from truss co. showing addditional load on bottom chord for added soffits ok.
|
BLD-Framing/Rough-in | 7/31/2020 | 8/3/2020 | 8/3/2020 | A | PART |
Mike Jordan
|
|
|
exterior wall electrical passed and need to insulate and rock monday. Phone #: ###-#### Inspection requested via web by todd smock. Ok to insulate exterior walls only. Needs to provide strap at double top plate break at plumbing penetration for roof drain. Needs to provide truss engineering on energy code inspection.
|
BLD-Framing/Rough-in | 7/27/2020 | 7/28/2020 | 7/28/2020 | P | NR |
Mike Jordan
|
|
|
walls are all roughed in per inspectors request to gain framing completion Phone #: ###-#### Inspection requested via web by todd smock
|
CHANGE STATUS TO (ISS) | | | 7/27/2020 | | DONE |
|
|
|
Plan Mod issued
|
OVERRIDE | | | 7/23/2020 | | |
|
|
|
|
Routing - PLAN CHECK | 7/23/2020 | | 7/23/2020 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/23/2020 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 7/23/2020 | | DONE |
|
|
|
Plan Mod - MET
|
Plan assigned to (M_H) | 7/8/2020 | | 7/23/2020 | | DONE |
Michael Hanson
|
|
|
07/22 plan mod - Chase bank
|
BLD-Framing/Rough-in | 7/20/2020 | 7/21/2020 | 7/21/2020 | A | PASS |
Mike Jordan
|
|
|
SCREENED // Todd Phone #: ###-####. Ok to cover exterior sheathing and roof.
|
BLD-Wall Bracing | 7/15/2020 | 7/17/2020 | 7/17/2020 | A | PART |
Mike Jordan
|
|
|
Todd - */Screened*/ Phone #: ###-####. Work in progress. Needs to install straps, holdowns and strap on roof. Will reschedule.
|
Plan Modification Accepted | | | 7/8/2020 | | DONE |
|
|
|
Interior revisions per latest client standards.
|
BLD-Concrete | 6/19/2020 | 6/22/2020 | 6/22/2020 | A | PART |
Mike Jordan
|
|
|
slab placement, bar, rigid insulation and vapor barrier special inspections. City for flatwork and inlets. Phone #: ###-#### Inspection requested via web by todd smock. Work in progress on installing reinforcement. Noted missed reinforcement from top of grade beam into slab. Will need RFI from engineer fro repair.
|
BLD-Footing | 6/15/2020 | 6/16/2020 | 6/16/2020 | A | CANC |
Mike Jordan
|
|
|
rigid insulation interior stem wall Phone #: ###-#### Inspection requested via web by todd smock
|
BLD-Energy code compliance | 6/16/2020 | 6/16/2020 | 6/16/2020 | A | PASS |
Mike Jordan
|
|
|
rigid insulation interior stem wall Phone #: ###-#### Inspection requested via web by todd smock
|
BLD-Grading Inspection | 6/11/2020 | 6/11/2020 | 6/11/2020 | P | CANC |
Mike Jordan
|
|
|
Require city inspection of seepage bed, engineer will sign off on this as well when onsite Phone #: ###-#### Inspection requested via web by todd smock. Needs to contact public Works.
|
BLD-Footing | 6/4/2020 | 6/8/2020 | 6/8/2020 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Tim Freer. Perimeter footings, will have special inspection. Needs to provide vertical reinforcement at 16 oc,
|
Plan assigned to (M_H) | 5/22/2020 | | 6/8/2020 | | DONE |
Michael Hanson
|
|
|
06/05 Plan Mod - Chase Bank revisions and ACHD standards
No review conducted. MH 06/08
|
CHANGE STATUS TO (ISS) | | | 5/27/2020 | | DONE |
|
|
|
will apply for plan mod at a better date. see email in documents
|
Plan Modification Accepted | | | 5/22/2020 | | DONE |
|
|
|
******applicant no longer following through and delete the plan assigned to task 5-27-2020********
Plan Modification for interior revisions and corrections based on ACHD standards
|
Issue PAID IN FULL permit | | | 5/4/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/4/2020 | | DONE |
|
|
|
|
Telephone call | | | 5/1/2020 | | DONE |
|
|
|
Let contractor know via email that we still need an RP and fees to be paid before we can issue
|
OVERRIDE | | | 4/30/2020 | | |
|
|
|
|
Permit Ready to Issue | | | 4/30/2020 | | DONE |
|
|
|
met
NEED
RP
MET ACHD
MET GC
MET Revised Certificate of Value
|
Plan assigned to (M_H) | 1/21/2020 | | 4/29/2020 | | DONE |
Michael Hanson
|
|
|
1st review completed - 02/21 #502 L3 ePlan - Chase Bank
|
Routing PW Drainage | 4/29/2020 | | 4/29/2020 | | FAIL |
Jason C. Taylor
|
|
|
Need signed and notarized appendix J. Jason Taylor ###-####
|
Routing Off Site - A.C.H.D | 4/29/2020 | | 4/29/2020 | | PASS |
Michael Hanson
|
|
|
See attached approval letter.
|
Routing PW Drainage | 4/29/2020 | | 4/29/2020 | | PASS |
Jason C. Taylor
|
|
|
|
Routing Off Site - STRUCTURAL | 3/18/2020 | | 4/21/2020 | | PASS |
Michael Hanson
|
|
|
per ePlan approval by AHJ engineering
|
Routing PW Sewer Design | 4/6/2020 | | 4/6/2020 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Sewer Design | 4/6/2020 | | 4/6/2020 | | PASS |
DeAnn Brown
|
|
|
|
Routing - PLUMBING | 4/3/2020 | | 4/3/2020 | | PASS |
Daryl Spivey
|
|
|
See redline note P2. If RPBP is installed adequate drainage shall be installed to accomodate it. DCVA is an approved device for service protection.
|
Routing - FIRE | 3/27/2020 | 3/27/2020 | 3/27/2020 | | PASS |
Greg Ruxton
|
|
|
Comments attached to case.
|
Routing PW Drainage | 3/25/2020 | | 3/25/2020 | | FAIL |
Jason C. Taylor
|
|
|
See changemarks in ePlan.
|
Routing PW Solid Waste | 3/19/2020 | | 3/19/2020 | | PASS |
Evan Carpenter
|
|
|
|
Routing - Design Review | 3/18/2020 | | 3/18/2020 | | PASS |
Katelyn Menuge
|
|
|
|
Routing PW Street Lights | 3/18/2020 | | 3/18/2020 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLUMBING | 3/18/2020 | | 3/18/2020 | | FAIL |
Daryl Spivey
|
|
|
See redline note P2.1. If RPBP is installed adequate drainage must be available for RPBP drain.
2. Changemark note on C5.10 not resolved
|
Routing - MECHANICAL | 3/18/2020 | | 3/18/2020 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 2/26/2020 | 2/29/2020 | 2/27/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 1/13/2020 | 1/21/2020 | 2/26/2020 | | FAIL |
Greg Ruxton
|
|
|
Comments attached to case. Emailed architect.
|
1st review completed | | | 2/26/2020 | | FAIL |
Michael Hanson
|
|
|
|
Routing Off Site - STRUCTURAL | 1/21/2020 | | 2/24/2020 | | FAIL |
Michael Hanson
|
|
|
AHJ
|
Routing - PLAN CHECK | 1/21/2020 | | 2/24/2020 | | PASS |
Michael Hanson
|
|
|
|
Routing - MECHANICAL | 1/21/2020 | | 1/30/2020 | | FAIL |
Troy James
|
|
|
Talked to mechanical engineer.
|
Routing - PLUMBING | 1/21/2020 | | 1/29/2020 | | FAIL |
Daryl Spivey
|
|
|
See changemark on C5.10 utility plan
|
Routing PW Drainage | 1/21/2020 | | 1/28/2020 | | FAIL |
|
|
|
new pave to existing c.b.
to achd. ground water seperation 5feet to freedraining note need stamp civil and no not for construction
|
Routing PW Solid Waste | 1/21/2020 | | 1/27/2020 | | FAIL |
|
|
|
This property is required to provide for solid waste service, unless the company is hauling their own waste to a proper disposal location (e.g., landfill). See the Solid Waste Design Standards for more information.
|
Routing - Design Review | 1/21/2020 | | 1/24/2020 | | FAIL |
Katelyn Menuge
|
|
|
Need six bicycle parking spaces and additional street trees.
|
Routing - Addressing | 1/21/2020 | | 1/23/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - Erosion and Sediment | 1/21/2020 | | 1/23/2020 | | PASS |
Michael Zawacki
|
|
|
RP needed.
|
Routing - PUBLIC WORKS | 1/21/2020 | | 1/22/2020 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Street Lights | 1/21/2020 | | 1/22/2020 | | FAIL |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 1/21/2020 | | 1/22/2020 | | FAIL |
DeAnn Brown
|
|
|
See changemarks. The existing sewer service line for the lot is a 4", not 8". And some notes do not apply.
|
Routing - PLANNING | 1/21/2020 | | 1/22/2020 | | PASS |
Kevin Holmes
|
|
|
Passed, meets requirements of CUP19-00073.
|
Intake Approval | | | 1/13/2020 | | PASS |
Jenny Nelson
|
|
|
|
Intake Approval | | | 1/9/2020 | | FAIL |
Jenny Nelson
|
|
|
Please upload sheet M4.0 as indicated on checklist or let me know where heating and cooling load calculations and mechanical ventilation systems are, I couldn't find them.
|
Intake Approval | | | 1/7/2020 | | FAIL |
Jenny Nelson
|
|
|
1. Filled out submittal checklist
2. Owners signature on 310 Special Inspection Form
|
Application received | | | 1/3/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 3 2020 12:54PM
|
Routing PW Sewer Design | 3/18/2020 | | | | FAIL |
|
|
|
There is a note on the utility sheet that says the sewer service line for the proposed building is an "EX 8" sanitary sewer line". This pipeline is actually a 4" sewer service pipeline. Please revise this note or remove.
|