BLD-Final | 5/21/2020 | 5/22/2020 | 5/22/2020 | A | PASS |
Dave Hannah
|
|
|
Screened- GARRET Phone #: ###-####
|
Zoning Approval | 5/13/2020 | 5/13/2020 | 5/13/2020 | | DONE |
Michaella Owens
|
|
|
|
FIRE-Final Inspection | 5/7/2020 | 5/7/2020 | 5/7/2020 | P | PASS |
Jim Page
|
|
|
No fire sprinkklers, no fire alarms. Final life fire safety inspection for area of work is complete, signature provided on permit sign off card.
screened // Garrett Phone #: ###-####
|
Inspection Record Card- Bld | | | 5/5/2020 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 3/9/2020 | 3/9/2020 | 3/10/2020 | P | PASS |
Dave Hannah
|
|
|
call 30 mins ahead- Garret Phone #: ###-#### ext wall furring ok
|
Issue PAID IN FULL permit | | | 1/28/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/28/2020 | | DONE |
|
|
|
|
Route to Impact Fee Review | 1/22/2020 | 1/25/2020 | 1/22/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (M_H) | 1/10/2020 | | 1/22/2020 | | DONE |
Michael Hanson
|
|
|
01/22 #518 L2 ePlan - Dawson Taylor Facade remodel
|
Routing - PLAN CHECK | 1/10/2020 | | 1/22/2020 | | PASS |
Michael Hanson
|
|
|
|
1st review completed | | | 1/22/2020 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/22/2020 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 1/22/2020 | | DONE |
|
|
|
ALL MET NEED (garrett@alpineidaho.com & matthew@brsarchitects.com)
GC
MET
Revised Certificate of Value
|
Routing - Design Review | 1/10/2020 | | 1/10/2020 | | PASS |
Michaella Owens
|
|
|
|
Intake Approval | | | 1/9/2020 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 1/7/2020 | | FAIL |
Julie Romig
|
|
|
Upload drawing sheets as individual files named per the City of Boise naming conventions (ie A101_Cover). PDF package has been deleted from ePlanReview.
|
Application received | | | 1/3/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 3 2020 1:15PM
|