FIRE-Final Inspection | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | FAIL |
Troy Cobbley
|
|
|
Need fire alarm notification modifications prior to a life safety sign off.
Tim -*/Screened*/ Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/31/2020 | 8/3/2020 | 8/3/2020 | A | PASS |
Mike Jordan
|
|
|
Randy *screened* Phone #: ###-####
|
BLD-Framing/Rough-in | 7/1/2020 | 7/1/2020 | 7/1/2020 | P | PASS |
Mike Jordan
|
|
|
Tim *screened* Phone #: ###-####. Interior steel stud framed walls.
|
Issue PAID IN FULL permit | | | 6/26/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/26/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/26/2020 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 1/7/2020 | 1/7/2020 | 6/25/2020 | | DONE |
Brian McGowan
|
|
|
06/27- 2nd Review Complete- 01/13 L1 GSA - USMS Office ePlan
|
Permit Ready to Issue | | | 6/25/2020 | | DONE |
|
|
|
met: tim@firstcallboise.com
NEED GC
MET REV VALUE
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/24/2020 | | DONE |
Brian McGowan
|
|
|
|
Telephone call | | | 6/24/2020 | | DONE |
|
|
|
First Call is a branch of EKC - Tim Hendrix is with both companies. Their Revised Values are in the DOCs
|
Routing - PLAN CHECK | 6/17/2020 | | 6/24/2020 | | PASS |
Brian McGowan
|
|
|
|
Telephone call | | | 6/23/2020 | | DONE |
|
|
|
Marianne from Erstad contacted us saying that the fees for BLD20-01759 should have been added to BLD20-00033. Contractor has submitted 306s to this effect. They have requested a refund.
|
Routing - PLAN CHECK | 6/18/2020 | | 6/18/2020 | | FAIL |
Brian McGowan
|
|
|
|
Routing - Addressing | 6/16/2020 | | 6/17/2020 | | PASS |
Doug Chausow
|
|
|
Suite 111
|
Plan Reviewer's activity | | | 1/31/2020 | | DONE |
Brian McGowan
|
|
|
Email from Marianne letting me know they are still working on the Permit but needed to make a few more adjustments.
|
Route to Impact Fee Review | 1/15/2020 | 1/18/2020 | 1/16/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 1/15/2020 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 1/7/2020 | | 1/15/2020 | | FAIL |
Brian McGowan
|
|
|
|
Routing - Addressing | 1/7/2020 | | 1/8/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/7/2020 | | 1/8/2020 | | PASS |
Morgan Webb
|
|
|
NO NEW PLUMBING
|
Intake Approval | | | 1/7/2020 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 1/6/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 6 2020 8:49AM
|
Routing - PUBLIC WORKS | 6/16/2020 | | | | |
|
|
|
I need the address verified again please. They requested altered addresses.
|