BLD-Final | 5/12/2020 | 5/12/2020 | 5/12/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
DOC - Permit Finaled | 5/12/2020 | 5/12/2020 | 5/12/2020 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 5/8/2020 | 5/8/2020 | 5/8/2020 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Joel Hirtle Inspection cancelled from web by: Joel Hirtle
|
BLD-Final | 5/4/2020 | 5/5/2020 | 5/5/2020 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Needs mech. final.
|
BLD-Energy code compliance | 3/19/2020 | 3/23/2020 | 3/23/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 3/18/2020 | 3/18/2020 | 3/18/2020 | P | PASS |
Mike Jordan
|
|
|
Joel Phone #: ###-####
|
Reopen Permit (ISS) | | | 3/18/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 3/17/2020 | | |
|
|
|
|
Plan assigned to (D_S) Debbie | 3/16/2020 | 3/16/2020 | 3/17/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 3/17/2020 | | 3/17/2020 | | PASS |
Debbie Sanine
|
|
|
|
Permit Ready to Issue | | | 3/17/2020 | | DONE |
|
|
|
Plan mod Approved
|
BLD-Framing/Rough-in | 3/16/2020 | 3/16/2020 | 3/16/2020 | P | FAIL |
Tell Riley
|
|
|
new set of plans are on site with new engineering, there is a note on the plans that spec our no tall wall engineering is needed due to the front porch and stairs act as a bracing for it. engineers did add several hold downs that have been installed. Phone #: ###-#### Inspection requested via web by Joel Hirtle//CN posted//need to submit changes to plan review for updated plans and engineering//new holddowns were not installed at time of inspection//
|
BLD-Framing/Rough-in | 3/11/2020 | 3/16/2020 | 3/16/2020 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Joel Hirtle Inspection cancelled from web by: Joel Hirtle
|
Plan Modification Accepted | | | 3/16/2020 | | DONE |
|
|
|
engineering for tall walls
|
BLD-Wall Bracing | 3/5/2020 | 3/5/2020 | 3/5/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Shannon Price
|
Fees Due Hold | 2/22/2020 | | 2/24/2020 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 2/20/2020 | | DONE |
|
|
|
plan mod- manual J
|
Routing - MECHANICAL | 2/20/2020 | | 2/20/2020 | | PASS |
Troy James
|
|
|
plan mod manual J
|
BLD-Foundation | 2/7/2020 | 2/10/2020 | 2/10/2020 | A | PART |
Tell Riley
|
|
|
victor Phone #: ###-####//WIP//blankets onsite//form temps ok where covered//
|
BLD-Footing | 2/6/2020 | 2/7/2020 | 2/7/2020 | A | PASS |
Mike Jordan
|
|
|
pour at 1pm // Victor Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/14/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/14/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 1/13/2020 | | |
|
|
|
|
Plan assigned to (D_S) Debbie | 1/7/2020 | 1/7/2020 | 1/13/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 1/7/2020 | | 1/13/2020 | | PASS |
Jenny Nelson
|
|
|
Per D_S review
|
1st review completed | | | 1/13/2020 | | DONE |
Debbie Sanine
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/13/2020 | | DONE |
Debbie Sanine
|
|
|
|
Permit Ready to Issue | | | 1/13/2020 | | DONE |
|
|
|
met
|
Routing - MECHANICAL | 1/7/2020 | | 1/10/2020 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 1/7/2020 | 1/10/2020 | 1/8/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 1/7/2020 | | 1/8/2020 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 1/7/2020 | | 1/8/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/7/2020 | | 1/7/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 1/7/2020 | | PASS |
|
|
|
|
Application received | | | 1/6/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 6 2020 4:56PM
|