BLD-Energy code compliance | 7/14/2020 | 7/15/2020 | 7/15/2020 | P | PASS |
Dave Hannah
|
|
|
call hour ahead- Brandon *screened* Phone #: ###-####
|
BLD-Framing/Rough-in | 7/10/2020 | 7/13/2020 | 7/13/2020 | P | PART |
Tony Young
|
|
|
Brandon Phone #: ###-####// needs mech pass,, fire blocking x 4 areas.. ceiling lines,, chase tops,, stair run,, ok to insulate
|
CHANGE STATUS TO (ISS) | | | 7/9/2020 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 6/30/2020 | 6/30/2020 | 7/8/2020 | | PASS |
Carl Westfall
|
|
|
plan mod - Firefusion Studio (routed to staff)
|
Routing PW Sewer Rating | 7/6/2020 | | 7/8/2020 | | PASS |
Morgan Webb
|
|
|
|
Plan Reviewer's activity | | | 7/8/2020 | | PASS |
|
|
|
Plan mod review approved
|
Permit Ready to Issue | | | 7/8/2020 | | DONE |
|
|
|
Plan mod
|
Routing - PLAN CHECK | 7/2/2020 | | 7/6/2020 | | PASS |
Carl Westfall
|
|
|
Back from Permits Desk. Routed to staff.
|
Routing - PLUMBING | 7/6/2020 | | 7/6/2020 | | PASS |
Daryl Spivey
|
|
|
Install plumbing per ISPC. No plumbing drawings submitted
|
Routing - PLAN CHECK | 6/30/2020 | | 7/2/2020 | | PASS |
Carl Westfall
|
|
|
Plan mod approved
|
Plan Modification Accepted | | | 6/30/2020 | | DONE |
|
|
|
Eliminate the proposed (4) floor drains in the basement and provide (3) waste line stubs for future plumbing fixture connections.
|
Issue PAID IN FULL permit | | | 4/8/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/8/2020 | | DONE |
|
|
|
|
Telephone call | | | 4/2/2020 | | DONE |
|
|
|
sent email to contractor, fees are still due for sewer
|
Permit Ready to Issue | | | 3/30/2020 | | DONE |
|
|
|
ALL MET (deliamdante@gmail.com)
Need
GC Form
Revised Cert of Value
MET
ACHD
|
Routing - FIRE | 3/27/2020 | 3/27/2020 | 3/27/2020 | | PASS |
Greg Ruxton
|
|
|
Comments attached to case. GJR
|
Plan assigned to (CJW) | 1/15/2020 | 1/27/2020 | 3/27/2020 | | PASS |
Carl Westfall
|
|
|
(1st done) 9 - 01/22/20 (L-2 - 7 days) (ePlan - 18 sheets) FireFusion Studio (routed to staff)
|
Routing - Design Review | 3/27/2020 | | 3/27/2020 | | PASS |
Michaella Owens
|
|
|
|
Routing - PLAN CHECK | 3/26/2020 | | 3/27/2020 | | PASS |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/27/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/26/2020 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 3/18/2020 | | 3/25/2020 | | PASS |
Carl Westfall
|
|
|
Chris Merrill (Stapley)
|
Plan resubmittals requested | | | 3/25/2020 | | DONE |
|
|
|
|
Routing - FIRE | 3/18/2020 | 3/18/2020 | 3/20/2020 | | FAIL |
Greg Ruxton
|
|
|
Attached comments to case and emailed architect.
|
Routing - Design Review | 3/18/2020 | | 3/19/2020 | | PASS |
Michaella Owens
|
|
|
|
Routing - PLAN CHECK | 3/17/2020 | | 3/18/2020 | | PASS |
Carl Westfall
|
|
|
Pending structural
|
Plan resubmittals received | | | 3/17/2020 | | DONE |
|
|
|
|
Route to Impact Fee Review | 3/10/2020 | 3/13/2020 | 3/11/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 1/15/2020 | 1/15/2020 | 3/10/2020 | | FAIL |
Greg Ruxton
|
|
|
01/27 L2 FireFusion Studio ePlan
|
1st review completed | | | 3/10/2020 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 3/10/2020 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/15/2020 | | 3/9/2020 | | FAIL |
Carl Westfall
|
|
|
|
Routing Off Site - STRUCTURAL | 1/15/2020 | | 1/29/2020 | | FAIL |
Carl Westfall
|
|
|
Chris Merrill (Stapley)
|
Routing - MECHANICAL | 1/15/2020 | | 1/22/2020 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 1/15/2020 | | 1/15/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/15/2020 | | 1/15/2020 | | PASS |
Morgan Webb
|
|
|
CREDIT GIVEN FOR DEMO
|
Routing - Erosion and Sediment | 1/15/2020 | | 1/15/2020 | | PASS |
Michael Zawacki
|
|
|
|
Routing - Design Review | 1/15/2020 | | 1/15/2020 | | PASS |
Michaella Owens
|
|
|
weather protection required over south and west entries at a depth of at least 5'
|
Intake Approval | | | 1/14/2020 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 1/9/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 9 2020 1:21PM
|