(FIREFUSION STUDIO – 1ST STORY AND BASEMENT) (CZC20-00006) (7-8-20 PLAN MODIFICATION TO ELIMINATE THE FORMERLY PROPOSED FOUR (4) FLOOR DRAINS WITH 4” DRAIN LINES IN THE BASEMENT AND TO PROVIDE THREE (3) WASTE LINE STUBS WITH 3” DRAIN LINES FOR FUTURE PLUMBING FIXTURE CONNECTIONS IN THE BASEMENT ALL DRAINING TO A SUMP PIT AND PUMP IN THE BASEMENT.) This building does not have a fire sprinkler system. To remodel an existing 6,943 square foot building to be used as an art gallery, art studio, retail sales on the 1st story, and storage and art studio in the basement (3,503 square feet 1st story and 3,440 square feet basement). Studio spaces on the 1st story will contain hot work operations including cutting, welding, grinding, kilns, and other similar activity. Work is to include lowering the basement floor level (new concrete perimeter retaining walls and new concrete slab on grade), a basement wall infill at an existing vault under the city sidewalk, new concrete footings, new steel columns with steel base plates and column caps, two new basement stairways, 1st story floor infills, interior nonbearing walls, two toilet rooms accessible to the disabled, roof structural upgrades to support new roof top HVAC equipment, new windows in existing openings in the North and West walls, re-pointing existing masonry walls, a new steel awning over the West exterior door, millwork, and finishes. Special Inspection is required for soils, concrete (including anchors post-installed in hardened concrete), and steel (including welding). The existing mezzanine, stairways, elevator, and toilet rooms will be demolished. The design for upgrading the South building entrance to be code compliant is a deferred submittal item. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. Separate operations permits are required from the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Energy code compliance7/14/20207/15/20207/15/2020PPASS
DetailsDave Hannah
call hour ahead- Brandon *screened* Phone #: ###-####
BLD-Framing/Rough-in7/10/20207/13/20207/13/2020PPART
DetailsTony Young
Brandon Phone #: ###-####// needs mech pass,, fire blocking x 4 areas.. ceiling lines,, chase tops,, stair run,, ok to insulate
CHANGE STATUS TO (ISS)  7/9/2020 DONE
Plan assigned to (CJW)6/30/20206/30/20207/8/2020 PASS
DetailsCarl Westfall
plan mod - Firefusion Studio (routed to staff)
Routing PW Sewer Rating7/6/2020 7/8/2020 PASS
DetailsMorgan Webb
Plan Reviewer's activity  7/8/2020 PASS
Plan mod review approved
Permit Ready to Issue  7/8/2020 DONE
Plan mod
Routing - PLAN CHECK7/2/2020 7/6/2020 PASS
DetailsCarl Westfall
Back from Permits Desk. Routed to staff.
Routing - PLUMBING7/6/2020 7/6/2020 PASS
DetailsDaryl Spivey
Install plumbing per ISPC. No plumbing drawings submitted
Routing - PLAN CHECK6/30/2020 7/2/2020 PASS
DetailsCarl Westfall
Plan mod approved
Plan Modification Accepted  6/30/2020 DONE
Eliminate the proposed (4) floor drains in the basement and provide (3) waste line stubs for future plumbing fixture connections.
Issue PAID IN FULL permit  4/8/2020 DONE
Print Occupancy Form  4/8/2020 DONE
Telephone call  4/2/2020 DONE
sent email to contractor, fees are still due for sewer
Permit Ready to Issue  3/30/2020 DONE
ALL MET (deliamdante@gmail.com)
Need
GC Form
Revised Cert of Value

MET
ACHD
Routing - FIRE3/27/20203/27/20203/27/2020 PASS
DetailsGreg Ruxton
Comments attached to case. GJR
Plan assigned to (CJW)1/15/20201/27/20203/27/2020 PASS
DetailsCarl Westfall
(1st done) 9 - 01/22/20 (L-2 - 7 days) (ePlan - 18 sheets) FireFusion Studio (routed to staff)
Routing - Design Review3/27/2020 3/27/2020 PASS
DetailsMichaella Owens
Routing - PLAN CHECK3/26/2020 3/27/2020 PASS
DetailsCarl Westfall
PLANS/APPL TAKEN TO FRONT DESK  3/27/2020 DONE
Plan resubmittals received  3/26/2020 DONE
Routing Off Site - STRUCTURAL3/18/2020 3/25/2020 PASS
DetailsCarl Westfall
Chris Merrill (Stapley)
Plan resubmittals requested  3/25/2020 DONE
Routing - FIRE3/18/20203/18/20203/20/2020 FAIL
DetailsGreg Ruxton
Attached comments to case and emailed architect.
Routing - Design Review3/18/2020 3/19/2020 PASS
DetailsMichaella Owens
Routing - PLAN CHECK3/17/2020 3/18/2020 PASS
DetailsCarl Westfall
Pending structural
Plan resubmittals received  3/17/2020 DONE
Route to Impact Fee Review3/10/20203/13/20203/11/2020 PASS
DetailsTravis P Black
Review requested for Commercial Permit
Routing - FIRE1/15/20201/15/20203/10/2020 FAIL
DetailsGreg Ruxton
01/27 L2 FireFusion Studio ePlan
1st review completed  3/10/2020 DONE
Plan resubmittals requested  3/10/2020 DONE
Routing - PLAN CHECK1/15/2020 3/9/2020 FAIL
DetailsCarl Westfall
Routing Off Site - STRUCTURAL1/15/2020 1/29/2020 FAIL
DetailsCarl Westfall
Chris Merrill (Stapley)
Routing - MECHANICAL1/15/2020 1/22/2020 PASS
DetailsTroy James
Routing - Addressing1/15/2020 1/15/2020 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS1/15/2020 1/15/2020 PASS
DetailsMorgan Webb
CREDIT GIVEN FOR DEMO
Routing - Erosion and Sediment1/15/2020 1/15/2020 PASS
DetailsMichael Zawacki
Routing - Design Review1/15/2020 1/15/2020 PASS
DetailsMichaella Owens
weather protection required over south and west entries at a depth of at least 5'
Intake Approval  1/14/2020 PASS
DetailsJavier Guzman
Application received  1/9/2020 DONE
Application submitted via PDS Online on Jan 9 2020 1:21PM