BLD-Framing/Rough-in | 8/11/2020 | 8/11/2020 | 8/11/2020 | P | PASS |
Mike Jordan
|
|
|
Screeened- Steve Phone #: ###-####. Soffit framing.
|
BLD-Wall cover | 8/6/2020 | 8/6/2020 | 8/6/2020 | P | PASS |
Mike Jordan
|
|
|
SCREENED // Steve Phone #: ###-####. Interior shear wall ok.
|
BLD-Wall Bracing | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | FAIL |
Mike Jordan
|
|
|
*Screened* Shear wall - Steve Phone #: ###-####. Install missing fasteners.
|
BLD-Framing/Rough-in | 7/31/2020 | 8/3/2020 | 8/3/2020 | A | PASS |
Mike Jordan
|
|
|
screened / Steve Phone #: ###-####. Hold downs.
|
BLD-Energy code compliance | 7/27/2020 | 7/28/2020 | 7/28/2020 | A | PASS |
Mike Jordan
|
|
|
Steve *screened* Phone #: ###-####. Fireblocking and insulation at 2hr. firewall completed.
|
BLD-Framing/Rough-in | 7/24/2020 | 7/27/2020 | 7/27/2020 | A | PASS |
Mike Jordan
|
|
|
Stephen - */Screened*/ Phone #: ###-####. Fire blocking betwwen shaft wall and exising structure.
|
BLD-Framing/Rough-in | 7/15/2020 | 7/16/2020 | 7/16/2020 | A | PART |
Mike Jordan
|
|
|
screened // Steve Phone #: ###-####. 2hr. firewall. Need to fireblock at ceiling and floor levels airgap.
|
BLD-Energy code compliance | 6/24/2020 | 6/24/2020 | 6/24/2020 | P | PASS |
Mike Jordan
|
|
|
STEVE Phone #: ###-####
|
BLD-Framing/Rough-in | 6/24/2020 | 6/24/2020 | 6/24/2020 | P | PASS |
Mike Jordan
|
|
|
STEVE Phone #: ###-####. Addition only ok.
|
BLD-Energy code compliance | 6/18/2020 | 6/19/2020 | 6/19/2020 | A | CANC |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Wrong inspection scheduled.
|
BLD-Framing/Rough-in | 6/19/2020 | 6/19/2020 | 6/19/2020 | A | PART |
Mike Jordan
|
|
|
Mike Phone #: ###-####. Needs to complete lateral bracing on A01 trusses. Ok to insulate.
|
BLD-Framing/Rough-in | 6/8/2020 | 6/9/2020 | 6/9/2020 | A | CANC |
Mike Jordan
|
|
|
Screened- Steve Phone #: ###-####
|
BLD-Wall Bracing | 6/9/2020 | 6/9/2020 | 6/9/2020 | A | PASS |
Mike Jordan
|
|
|
Screened- Steve Phone #: ###-####. Exterior perimeter walls for addition ok.
|
BLD-Framing/Rough-in | 6/2/2020 | 6/3/2020 | 6/3/2020 | A | PASS |
Mike Jordan
|
|
|
steve Phone #: ###-####. ok to cover roof only.
|
BLD-Foundation | 5/21/2020 | 5/22/2020 | 5/22/2020 | A | PASS |
Brandon Shaw
|
|
|
*screened* Rebar - Steve Phone #: ###-####
|
BLD-Foundation | 5/11/2020 | 5/12/2020 | 5/12/2020 | P | PASS |
Mike Jordan
|
|
|
Steve *screened* Phone #: ###-####
|
BLD-Footing | 5/5/2020 | 5/7/2020 | 5/7/2020 | A | PASS |
Mike Jordan
|
|
|
Steve *screened* Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/17/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/17/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 4/13/2020 | | |
|
|
|
|
Plan assigned to (CJW) | 1/14/2020 | 2/24/2020 | 4/13/2020 | | PASS |
Carl Westfall
|
|
|
(1st done) 9 - 02/17/20 (New Building - 25 days) (eplan - 47 sheets) Southminister Presbyterian Church Addition (waiting for structural issues to be resolved)
|
Routing - PLAN CHECK | 4/9/2020 | | 4/13/2020 | | PASS |
Carl Westfall
|
|
|
Pending structural
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/13/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/13/2020 | | DONE |
|
|
|
ALL MET
MET RP
MET GC
MET Revised VAlue
|
Routing Off Site - STRUCTURAL | 4/7/2020 | | 4/13/2020 | | PASS |
Carl Westfall
|
|
|
Dave Haugland (AHJ)
|
Routing - FIRE | 4/7/2020 | 4/7/2020 | 4/8/2020 | | PASS |
Greg Ruxton
|
|
|
Comments attached to case.
|
Routing - PLANNING | 4/7/2020 | | 4/8/2020 | | PASS |
Ethan Mansfield
|
|
|
Change to exterior brick wainscot
|
Routing PW Street Lights | 4/7/2020 | | 4/8/2020 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLAN CHECK | 4/6/2020 | | 4/7/2020 | | FAIL |
Carl Westfall
|
|
|
Shear wall needs work. Taked to the Architect by telephone. He will Email revised Sheets.
|
Plan resubmittals received | | | 4/6/2020 | | DONE |
|
|
|
|
Route to Impact Fee Review | 3/17/2020 | 3/20/2020 | 3/17/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 1/23/2020 | | 3/17/2020 | | FAIL |
Carl Westfall
|
|
|
revised drawings required
|
1st review completed | | | 3/17/2020 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 3/17/2020 | | DONE |
|
|
|
|
Routing - FIRE | 1/14/2020 | 1/23/2020 | 3/12/2020 | | FAIL |
Greg Ruxton
|
|
|
Attached comments to case and emailed architect.
|
Routing Off Site - STRUCTURAL | 1/23/2020 | | 2/6/2020 | | FAIL |
Carl Westfall
|
|
|
AHJ
|
Routing - MECHANICAL | 1/23/2020 | | 1/30/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 1/23/2020 | | 1/29/2020 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PLANNING | 1/23/2020 | | 1/29/2020 | | PASS |
Ethan Mansfield
|
|
|
|
Routing - Addressing | 1/23/2020 | | 1/27/2020 | | PASS |
Laura Hunter
|
|
|
|
Routing PW Street Lights | 1/23/2020 | | 1/27/2020 | | FAIL |
Tom Marshall
|
|
|
|
Routing PW Drainage | 1/23/2020 | | 1/24/2020 | | PASS |
Brian Murphy
|
|
|
bld970 sqft < 1000 requirment
|
Routing PW Sewer Design | 1/23/2020 | | 1/23/2020 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Solid Waste | 1/23/2020 | | 1/23/2020 | | PASS |
Evan Carpenter
|
|
|
|
Routing - PUBLIC WORKS | 1/23/2020 | | 1/23/2020 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 1/23/2020 | | 1/23/2020 | | PASS |
Michael Zawacki
|
|
|
waiver approved
|
Intake Approval | | | 1/14/2020 | | PASS |
Julie Romig
|
|
|
|
Application received | | | 1/10/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 10 2020 11:42AM
|