First Notice | | 6/11/2020 | 8/11/2020 | | DONE |
|
|
|
MAILED 8-14-2020
|
Print Statement | | | 8/10/2020 | | DONE |
|
|
|
|
First Notice | 6/1/2020 | 6/1/2020 | 7/9/2020 | | DONE |
Brandon Shaw
|
|
|
mailed 7-9-2020
|
BLD-Final | 6/1/2020 | 6/1/2020 | 6/1/2020 | P | PASS |
Brandon Shaw
|
|
|
MEC is finaled now- Will *screened* Phone #: ###-####
|
DOC - Permit Finaled | 6/1/2020 | 6/1/2020 | 6/1/2020 | P | PASS |
Brandon Shaw
|
|
|
|
Permanent Occupancy | | | 6/1/2020 | | DONE |
|
|
|
|
BLD-Final | 5/28/2020 | 5/29/2020 | 5/29/2020 | P | PART |
Brandon Shaw
|
|
|
See MEC20-01292... No other issues.... Temp C of O is approved...
|
FIRE-Final Inspection | 5/28/2020 | 5/29/2020 | 5/29/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. The electric stikes allow free egress. Will *screened* Phone #: ###-####
|
Temporary Occupancy | 5/29/2020 | 8/27/2020 | 5/29/2020 | | DONE |
Tiffany Carson-Herker
|
|
|
|
BLD-Final | 5/27/2020 | 5/28/2020 | 5/28/2020 | P | NR |
Mike Jordan
|
|
|
screened // Will Phone #: ###-####. Needs fire/life/safety final.
|
BLD-Framing/Rough-in | 4/9/2020 | 4/10/2020 | 4/10/2020 | A | PASS |
Mike Jordan
|
|
|
*screened* Will Phone #: ###-####. Interior wood framed walls and hardlids. Hardlids pending mech ri inspection.
|
Issue PAID IN FULL permit | | | 3/19/2020 | | DONE |
|
|
|
|
(F) Reprint permit | | | 3/19/2020 | | DONE |
|
|
|
|
(F) Reprint permit | | | 3/19/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/19/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/17/2020 | | DONE |
|
|
|
all met: robertf@alcarchitecture.com
NEED
ACHD -no fees/no inspection: See DOCs
GC Parcel Owner: See DOCs
Revised Certificate of value
|
Telephone call | | | 3/17/2020 | | DONE |
|
|
|
emailed Aaron at Rave Laundry asking him to verify that the values on the revised value (see DOCs) is accurate. It is for less than half of what the initial value was.
3/17/20: Eric from ALC said: I’ll jump in here, the numbers we provided initially were estimates based on historical values from other projects as well as RS means estimator.
Since permit submittal the owner has bid the project to his selected subcontractors and has provided those bid numbers instead of our estimated numbers.
Unfortunately we had values in our estimates that should not have been part of the construction values so we backed those numbers out. Additionally our estimates were much higher than actual values.
|
Plan assigned to (Joe) | 2/19/2020 | 2/19/2020 | 3/16/2020 | | PASS |
Joe Bruce
|
|
|
1st Rev Comp - 03/10 (520) Rave II Laundry, ePlan
|
Routing - PLAN CHECK | 3/12/2020 | | 3/16/2020 | | PASS |
Joe Bruce
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/16/2020 | | DONE |
|
|
|
|
Routing - Design Review | 3/12/2020 | | 3/12/2020 | | PASS |
Katelyn Menuge
|
|
|
|
Route to Impact Fee Review | 3/10/2020 | 3/13/2020 | 3/11/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Plan resubmittals received | | | 3/11/2020 | | DONE |
Joe Bruce
|
|
|
|
Routing - FIRE | 2/19/2020 | 2/19/2020 | 3/10/2020 | | PASS |
Joe Bruce
|
|
|
Attached comments to case. 03/10 L3 Rave Laundry
|
1st review completed | | | 3/10/2020 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 3/10/2020 | | DONE |
Joe Bruce
|
|
|
Sent ePlan case back to applicant.
|
Routing - PLAN CHECK | 2/19/2020 | | 3/9/2020 | | FAIL |
Joe Bruce
|
|
|
emailed comments to applicant.
|
Routing PW Environmental | 2/19/2020 | | 3/4/2020 | | PASS |
Zach Conde
|
|
|
|
Routing PW Solid Waste | 2/19/2020 | | 3/3/2020 | | PASS |
Evan Carpenter
|
|
|
|
Routing - MECHANICAL | 2/25/2020 | | 2/25/2020 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 2/19/2020 | | 2/24/2020 | | FAIL |
Troy James
|
|
|
Emailed corrections to applicant.
|
Routing - Addressing | 2/19/2020 | | 2/20/2020 | | PASS |
Doug Chausow
|
|
|
New address: 6873 W Fairview Ave
|
Routing - PUBLIC WORKS | 2/19/2020 | | 2/20/2020 | | PASS |
Candy A. Nichols
|
|
|
CONTACT WEST BOISE SEWER DISTRICT FOR FEES
|
Routing - Design Review | 2/19/2020 | | 2/19/2020 | | FAIL |
KayCee Babb
|
|
|
Zoning Certificate application required for Design Review of exterior alterations, including door modifications and installation of vent.
|
Routing PW Street Lights | 2/19/2020 | | 2/19/2020 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Drainage | 2/19/2020 | | 2/19/2020 | | PASS |
Brian Murphy
|
|
|
T.I. ONLY
|
Routing PW Sewer Design | 2/19/2020 | | 2/19/2020 | | PASS |
DeAnn Brown
|
|
|
Property is in West Boise Sewer District. Coordinate any sewer facility changes with West Boise Sewer District.
|
Routing - PLUMBING | 2/19/2020 | | 2/19/2020 | | PASS |
Daryl Spivey
|
|
|
per plan and ISPC.
|
Routing - PLANNING | 2/19/2020 | | 2/19/2020 | | PASS |
Ethan Mansfield
|
|
|
See email from Katelyn in DR.
Use is allowed.
|
Intake Approval | | | 2/12/2020 | | PASS |
|
|
|
|
Intake Approval | | | 2/10/2020 | | FAIL |
Julie Romig
|
|
|
Please upload sheet E2.0D Demo Plan with 4"x2" blank space and Cover sheet with 4"x4" blank space in lower right hand corner.
|
Intake Approval | | | 1/31/2020 | | FAIL |
Julie Romig
|
|
|
1. Design review approval letter for mechanical equipment on rooftop (dryer exhausts).
2. ESC Waiver Request letter for removal of more than 40 linear feet of interior concrete slab.
3. Leave a 4"x2" blank space in the lower right hand corner, located 3" off the right sheet edge, of all electrical drawings.
|
Application received | | | 1/15/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 15 2020 2:39PM
|
Second Notice | | 8/21/2020 | | | |
|
|
|
|