Second Notice | | 7/19/2020 | 8/11/2020 | | DONE |
|
|
|
mailed 8-11-2020
|
First Notice | | 6/7/2020 | 7/9/2020 | | DONE |
|
|
|
mailed 7-9-2020
|
Permanent Occupancy | | | 5/28/2020 | | DONE |
|
|
|
|
Temporary Occupancy | 5/22/2020 | 8/20/2020 | 5/22/2020 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 5/20/2020 | 5/21/2020 | 5/21/2020 | P | PEND |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Korey Hall ok for tco
|
FIRE-Final Inspection | 5/19/2020 | 5/20/2020 | 5/20/2020 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, mag locks release on general fire alarm, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work is complete, signatures provided on permit sign off card.
Phone #: ###-#### Inspection requested via web by Korey Hall
|
BLD-Ceiling Grid Inspection | 5/4/2020 | 5/5/2020 | 5/6/2020 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Korey Hall
|
BLD-Framing/Rough-in | 3/26/2020 | 3/26/2020 | 3/26/2020 | P | PASS |
Dave Hannah
|
|
|
Re-Inspection of in wall floor penetration fire caulking Phone #: ###-#### Inspection requested via web by Korey Hall
|
BLD-Framing/Rough-in | 3/25/2020 | 3/25/2020 | 3/25/2020 | P | NR |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Korey Hall needs to fire stop holes in floor
|
Issue PAID IN FULL permit | | | 3/19/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/19/2020 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 1/29/2020 | 2/21/2020 | 3/17/2020 | | PASS |
Carl Westfall
|
|
|
(1st done) 9 - 02/14/20 (L-3 - 15 days) (eplan - 30 sheets) New York Life (routed to staff)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/17/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/17/2020 | | DONE |
|
|
|
MET brooke@bvadev.com
ACHD
GC Form
Revised Cert of Value
|
Route to Impact Fee Review | 3/13/2020 | 3/16/2020 | 3/16/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 3/13/2020 | | 3/16/2020 | | PASS |
Carl Westfall
|
|
|
|
Routing - PUBLIC WORKS | 3/16/2020 | | 3/16/2020 | | PASS |
Morgan Webb
|
|
|
|
1st review completed | | | 3/13/2020 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 3/13/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/13/2020 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/29/2020 | | 3/13/2020 | | FAIL |
Carl Westfall
|
|
|
|
Routing - FIRE | 1/29/2020 | 1/29/2020 | 3/5/2020 | | PASS |
Greg Ruxton
|
|
|
Attached comments to case.
|
Routing - MECHANICAL | 1/29/2020 | | 2/4/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 1/29/2020 | | 2/4/2020 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PUBLIC WORKS | 1/29/2020 | | 1/31/2020 | | FAIL |
Morgan Webb
|
|
|
NEED DEMP PLAN WITH EXISTING PLUMBING FIXTURES SHOWN.
|
Routing - Addressing | 1/29/2020 | | 1/30/2020 | | PASS |
Doug Chausow
|
|
|
Suite 460
|
Intake Approval | | | 1/27/2020 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 1/24/2020 | | DONE |
Michael Hanson
|
|
|
breakroom sink floor plan 13/A410 does not match the detail 8/A410 showing centered sink. Just wanted to provide a FYI so that you are aware the 13/A410 detail needs updated.
|
Intake Approval | | | 1/22/2020 | | FAIL |
Michael Hanson
|
|
|
See clouded items on #520 checklist that indicate missing information that is required to pass prescreen.
|
Application received | | | 1/15/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 15 2020 4:25PM
|
Third Notice | | 8/16/2020 | | | |
|
|
|
|