BLD-Final | 5/27/2020 | 5/28/2020 | 5/28/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
DOC - Permit Finaled | 5/28/2020 | 5/28/2020 | 5/28/2020 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 5/22/2020 | 5/22/2020 | 5/22/2020 | P | FAIL |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle/CN posted for sill less than 24" in bedroom above garage//need opening limit device IRC 312.2.1 ASTM 2090
|
BLD-Energy code compliance | 4/1/2020 | 4/3/2020 | 4/3/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 4/1/2020 | 4/3/2020 | 4/3/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. All issues have been resolved.
|
BLD-Framing/Rough-in | 3/27/2020 | 4/1/2020 | 4/1/2020 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Attic acces required in garage. Seal all penetrations in draft stop. Nail off all simpson hangars. (upstairs). Roll block floor joist at interior bearing walls and over main entry. Ok to insulate. Correction notice posted.
|
BLD-Framing/Rough-in | 3/26/2020 | 3/27/2020 | 3/27/2020 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Needs mech. and electrical rough in in inspections.
|
BLD-Wall Bracing | 3/16/2020 | 3/17/2020 | 3/17/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
Routing - MECHANICAL | 3/4/2020 | | 3/4/2020 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
Plan Modification Accepted | | | 3/3/2020 | | DONE |
|
|
|
Plan Mod Manual J per CBH Homes Gloria Martinez
|
BLD-Foundation | 2/20/2020 | 2/21/2020 | 2/21/2020 | P | PASS |
Mike Jordan
|
|
|
Jerry Phone #: ###-####
|
BLD-Footing | 2/19/2020 | 2/20/2020 | 2/20/2020 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: 28-###-####
|
Issue PAID IN FULL permit | | | 2/3/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/3/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 1/28/2020 | | |
|
|
|
|
Plan assigned to (RDP) | 1/22/2020 | 1/22/2020 | 1/28/2020 | | DONE |
Rob Patrick
|
|
|
02/04 sfd L1 ePlan
|
Routing - PLAN CHECK | 1/22/2020 | | 1/28/2020 | | PASS |
Rob Patrick
|
|
|
|
Routing - PLANNING | 1/22/2020 | | 1/28/2020 | | PASS |
Sue Cummings
|
|
|
|
1st review completed | | | 1/28/2020 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/28/2020 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 1/28/2020 | | DONE |
|
|
|
|
Routing - MECHANICAL | 1/22/2020 | | 1/24/2020 | | PASS |
Chad Schwendiman
|
|
|
|
Route to Impact Fee Review | 1/22/2020 | 1/25/2020 | 1/23/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 1/22/2020 | | 1/22/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/22/2020 | | 1/22/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/22/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/22/2020 | | DONE |
|
|
|
|
Intake Approval | | | 1/22/2020 | | PASS |
|
|
|
|
Intake Approval | | | 1/17/2020 | | FAIL |
|
|
|
sqft doesn't match
|
Application received | | | 1/16/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 16 2020 3:23PM
|