BLD-Ceiling Grid Inspection | 8/3/2020 | 8/3/2020 | 8/3/2020 | P | PASS |
Dave Hannah
|
|
|
Dameion *screened* Phone #: ###-####
|
BLD-Wall cover | 7/13/2020 | 7/14/2020 | 7/14/2020 | A | CANC |
Dave Hannah
|
|
|
Looking to cover except soffit above roll up security grill. Phone #: ###-#### Inspection requested via web by Dameion Maupin
|
BLD-Wall cover | 5/4/2020 | 5/4/2020 | 5/4/2020 | P | PASS |
Brandon Shaw
|
|
|
Energy... OK to cover...
|
BLD-Energy code compliance | 4/27/2020 | 4/28/2020 | 4/29/2020 | P | PASS |
Dave Hannah
|
|
|
Air seal inspection Phone #: ###-#### Inspection requested via web by Dameion Maupin
|
BLD-Foundation | 3/26/2020 | 3/27/2020 | 3/27/2020 | P | PART |
Dave Hannah
|
|
|
under slab/ rebar // Shane Phone #: ###-#### crew working on wire mess v/b installed edge reenforcment in
|
Issue PAID IN FULL permit | | | 3/9/2020 | | DONE |
|
|
|
|
Telephone call | | | 3/6/2020 | | DONE |
|
|
|
Email to Michael at Prusik. Permit is ready, fees are due. All req. docs met
|
Plan assigned to (M_H) | 1/24/2020 | | 3/5/2020 | | DONE |
Michael Hanson
|
|
|
2nd review completed - 02/20 #520 L3 ePlan - Casanova Pizzeria TI
|
Routing - MECHANICAL | 3/5/2020 | | 3/5/2020 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/5/2020 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 3/5/2020 | | DONE |
|
|
|
ALL MET
Need:
GC
Revised Value
|
Routing - PLAN CHECK | 3/2/2020 | | 3/2/2020 | | PASS |
Michael Hanson
|
|
|
|
Routing - MECHANICAL | 3/2/2020 | | 3/2/2020 | | FAIL |
Troy James
|
|
|
Left message with mechanical engineer.
|
Route to Impact Fee Review | 2/24/2020 | 2/27/2020 | 2/26/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 2/24/2020 | | FAIL |
Michael Hanson
|
|
|
See changemark for correction required regarding accessible restroom count.
|
Routing - PLAN CHECK | 1/24/2020 | | 2/24/2020 | | FAIL |
Michael Hanson
|
|
|
See changemark for correction required regarding accessible restroom count.
|
Routing - FIRE | 1/24/2020 | 1/24/2020 | 2/21/2020 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - MECHANICAL | 1/24/2020 | | 2/3/2020 | | FAIL |
Troy James
|
|
|
See eplan changemarks
|
Routing - PLUMBING | 1/24/2020 | | 2/3/2020 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PUBLIC WORKS | 1/24/2020 | | 1/27/2020 | | PASS |
Morgan Webb
|
|
|
|
Routing - Addressing | 1/24/2020 | | 1/27/2020 | | PASS |
Laura Hunter
|
|
|
|
Intake Approval | | | 1/24/2020 | | PASS |
Jenny Nelson
|
|
|
Prescreen approved by JJN
|
Intake Approval | | | 1/23/2020 | | FAIL |
Jenny Nelson
|
|
|
CDHD application filled out ready to be sent to their office or document with CDHD approval
|
Intake Approval | | | 1/22/2020 | | FAIL |
Jenny Nelson
|
|
|
1. Completed CDHD form
2. Site specific fire flow letter
|
Application received | | | 1/17/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 17 2020 10:58AM
|