PubWorks Occupancy Approval | 8/6/2020 | 8/6/2020 | 8/6/2020 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 7/31/2020 | 7/31/2020 | 7/31/2020 | P | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Ted Perry//see correction notice//need public works sign off as well//
|
FIRE-Final Inspection | 7/29/2020 | 7/29/2020 | 7/30/2020 | P | PASS |
Troy Cobbley
|
|
|
life safety passed. Phone #: ###-#### Inspection requested via web by Ted Perry
|
Zoning Approval | 7/29/2020 | 7/29/2020 | 7/29/2020 | | DONE |
Ethan Mansfield
|
|
|
Looks good for zoning!
|
BLD-Final | 7/28/2020 | 7/28/2020 | 7/28/2020 | P | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Ted Perry//need zoning and fire life safety finals prior to building final//
|
BLD-Energy code compliance | 6/18/2020 | 6/18/2020 | 6/18/2020 | A | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Ted Perry//insulation--architect changed and Ted will send email//1" closed cell foam-R7 and R15 batts in wall//room 2" closed cell foam R14 and R15 batts//ok pending architects letter//stairs still under constrution and will be as built by engineer--per Ted//trades ok--no mechanical was installed--let Ted know to contact plan review to remove from requirements//
|
BLD-Framing/Rough-in | 6/12/2020 | 6/12/2020 | 6/12/2020 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Ted Perry//1st floor ok, 2nd floor needs a35s installed-Ted will take photos//ted said nailing on exterior was completed prior to siding going on//ok to insulate//stairs still a WIP, need details from engineer//
|
BLD-Framing/Rough-in | 6/2/2020 | 6/3/2020 | 6/3/2020 | A | FAIL |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Ted Perry//cn left onsite with contracor//see details for framing//add nails and a35s for shear per plan//need alt design for stairs and landing as they do not reflect plans//
|
BLD-Framing/Rough-in | 6/2/2020 | 6/2/2020 | 6/2/2020 | P | CANC |
Tell Riley
|
|
|
|
BLD-Framing/Rough-in | 6/1/2020 | 6/2/2020 | 6/2/2020 | A | CANC |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Ted Perry
|
BLD-Footing | 4/27/2020 | 4/27/2020 | 4/27/2020 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Ted Perry//need to have electrical sign off on ground//footings WIP, main area bar ok pending specials//piers are still being installed-WIP//pour is pending specials approval//
|
Telephone call | | | 4/17/2020 | | DONE |
|
|
|
emailed the architect to see if she may have a better email, jeff's doesn't work, so i can let the GC know the rp expired in 2015 and need another name
|
Print Occupancy Form | | | 4/17/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/17/2020 | | DONE |
|
|
|
|
Telephone call | | | 4/8/2020 | | DONE |
|
|
|
emailed project engineer, Jeff Homan and let him know that the GCs license has expired and we cannot issue the permit until they have renewed.
|
OVERRIDE | | | 4/2/2020 | | |
|
|
|
|
Plan assigned to (JAR) | 2/13/2020 | 2/13/2020 | 4/2/2020 | | DONE |
Julie Romig
|
|
|
04/03 - 3rd Rev - 1st Rev Comp - **EXPEDITED SCHOOL REVIEW** Capital HS Concession/Pressbox
|
Routing Off Site - STRUCTURAL | 4/1/2020 | | 4/2/2020 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/2/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/2/2020 | | DONE |
|
|
|
RP EXPIRED 2015
MET: jeff@morganind.com
GC
NEED
RP
|
Routing - PLAN CHECK | 4/1/2020 | | 4/2/2020 | | PASS |
Julie Romig
|
|
|
|
Routing - FIRE | 4/1/2020 | 4/1/2020 | 4/1/2020 | | PASS |
Greg Ruxton
|
|
|
Comments attached to case.
|
Routing - ELECTRICAL | 4/1/2020 | | 4/1/2020 | | PASS |
Javier Guzman
|
|
|
|
Routing - FIRE | 3/18/2020 | 3/18/2020 | 3/24/2020 | | FAIL |
Greg Ruxton
|
|
|
Attached comments to case and emailed architect.
|
Routing - PLAN CHECK | 3/18/2020 | | 3/24/2020 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 3/18/2020 | | 3/23/2020 | | FAIL |
Julie Romig
|
|
|
AHJ
|
Routing - PLANNING | 3/18/2020 | | 3/20/2020 | | PASS |
Ethan Mansfield
|
|
|
|
Routing - ELECTRICAL | 3/18/2020 | | 3/18/2020 | | FAIL |
Daryl DeGrange
|
|
|
|
Route to Impact Fee Review | 2/26/2020 | 2/29/2020 | 2/27/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 2/26/2020 | | DONE |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 2/13/2020 | | 2/26/2020 | | FAIL |
Julie Romig
|
|
|
|
Routing - FIRE | 2/12/2020 | 2/13/2020 | 2/25/2020 | | FAIL |
Greg Ruxton
|
|
|
Comments attached to case. Emailed architect.
|
Routing Off Site - STRUCTURAL | 2/13/2020 | | 2/22/2020 | | PASS |
Julie Romig
|
|
|
AHJ
|
Routing PW Solid Waste | 2/13/2020 | | 2/18/2020 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Environmental | 2/13/2020 | | 2/18/2020 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 2/13/2020 | | 2/18/2020 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLANNING | 2/13/2020 | | 2/14/2020 | | FAIL |
Ethan Mansfield
|
|
|
Can't pass this without the CUP Mod. I am almost done with the CUP Mod, then the 10 day appeal period must lapse. Then I can pass. Cheers,
Ethan
|
Routing - Addressing | 2/13/2020 | | 2/14/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing PW Drainage | 2/13/2020 | | 2/14/2020 | | PASS |
Brian Murphy
|
|
|
LESS THAN 1000 SQFT
|
Routing PW Street Lights | 2/13/2020 | | 2/14/2020 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 2/13/2020 | | 2/14/2020 | | PASS |
DeAnn Brown
|
|
|
Project is located in West Boise Sewer District. Any alterations to site piping and sewer connections should be coordinated with West Boise Sewer District.
|
Routing - PUBLIC WORKS | 2/13/2020 | | 2/13/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Routing - Erosion and Sediment | 2/13/2020 | | 2/13/2020 | | PASS |
Michael Zawacki
|
|
|
RP needed. Small project, no prep inspection required.
|
Routing - ELECTRICAL | 2/13/2020 | | 2/13/2020 | | FAIL |
Daryl DeGrange
|
|
|
|
Routing - PLUMBING | 2/13/2020 | | 2/13/2020 | | PASS |
Dan Ediger
|
|
|
Per plans and ISPC
|
Intake Approval | | | 2/12/2020 | | PASS |
Julie Romig
|
|
|
|
Intake Approval | | | 1/30/2020 | | FAIL |
Julie Romig
|
|
|
Need: 1. Verification of Legal Lot or Parcel form signed by PDS subdivision staff.
2. CDHD - provide application or stamped/approved plans per checklist for new concession stand (or email from CDH stating that no review is required).
3. Form 310 completed by structural engineer and signed by owner for all required special inspections (including those listed on S0.02)
4. Planning and Zoning Letter of Approval
5. Energy COMcheck for Building Envelope (equipment buildings are only for housing equipment and not intended for human occupancy).
|
Application received | | | 1/23/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 23 2020 11:27AM
|
Agreement of Future work | 4/21/2020 | 4/21/2025 | | | |
Joe Bruce
|
|
|
(CAPITAL HIGH SCHOOL) Agreement to install a code compliant fire hydrant located within code requirements of the softball pressbox/concession stand within the next 5 years in conjunction with the parking lot replacement. See agreement attached to this case.
|