BLD-Final | 7/23/2020 | 7/23/2020 | 7/23/2020 | P | PASS |
Brandon Shaw
|
|
|
screened - call for access // Brett Phone #: ###-####
|
DOC - Permit Finaled | 7/23/2020 | 7/23/2020 | 7/23/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 7/23/2020 | 7/23/2020 | 7/23/2020 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 1.87
|
BLD-Framing/Rough-in | 4/24/2020 | 4/29/2020 | 4/29/2020 | A | CANC |
Brandon Shaw
|
|
|
Brett Phone #: ###-####
|
BLD-Energy code compliance | 4/24/2020 | 4/28/2020 | 4/28/2020 | A | PASS |
Jim Storey
|
|
|
Brett Phone #: ###-####
|
BLD-Framing/Rough-in | 4/21/2020 | 4/22/2020 | 4/22/2020 | A | PART |
Brandon Shaw
|
|
|
See Mec20-01544 enrty date 04-21-2020, fireplace inserts on back order... OK to insulate...
|
BLD-Conference | 4/3/2020 | 4/3/2020 | 4/3/2020 | P | DONE |
Brandon Shaw
|
|
|
cleared // Brett Phone #: ###-####
|
BLD-Wall Bracing | 3/31/2020 | 4/1/2020 | 4/1/2020 | A | PASS |
Brandon Shaw
|
|
|
shear // brett Phone #: ###-####
|
BLD-Foundation | 2/20/2020 | 2/24/2020 | 2/24/2020 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 2/19/2020 | 2/20/2020 | 2/20/2020 | P | PASS |
Dave Hannah
|
|
|
Sebration Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/12/2020 | | DONE |
|
|
|
|
Telephone call | | | 2/11/2020 | | DONE |
|
|
|
left a message for Brett informing him permit is ready and the fees due
|
OVERRIDE | | | 2/10/2020 | | |
|
|
|
|
Case Summary (BLD) | | | 2/10/2020 | | DONE |
Debbie Sanine
|
|
|
|
Plan Reviewer's activity | | | 2/10/2020 | | DONE |
Debbie Sanine
|
|
|
Took a little longer to sign-off (JJN out of office).
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/10/2020 | | DONE |
Debbie Sanine
|
|
|
|
Inspection Record Card- Bld | | | 2/10/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/10/2020 | | DONE |
|
|
|
met
|
Plan assigned to (D_S) Debbie | | | 2/10/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - FIRE | 1/30/2020 | 1/30/2020 | 2/5/2020 | | PASS |
Lee G Meredith
|
|
|
02/13 (paper plans) Big Springs Construction 205 E. Parkway Dr.
Since the builder has provided a hammerhead turn around for fire apparatus, sprinklers are not required.
|
1st review completed | | | 2/3/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 1/28/2020 | | 2/3/2020 | | PASS |
Jenny Nelson
|
|
|
Per D_S review
|
Routing - MECHANICAL | 1/26/2020 | | 1/28/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 1/24/2020 | | 1/27/2020 | | PASS |
Sue Cummings
|
|
|
|
Route to Impact Fee Review | 1/23/2020 | 1/26/2020 | 1/24/2020 | | PASS |
Travis P Black
|
|
|
Can not find the parcel in the GIS system, the building permit may have been assigned a temporary parcel number
|
Routing - Addressing | 1/23/2020 | | 1/24/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/23/2020 | | 1/24/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/23/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/23/2020 | | DONE |
|
|
|
|
Intake Approval | | | 1/23/2020 | | PASS |
|
|
|
|
Application received | | 1/23/2020 | | | |
|
|
|
|