BLD-Final | 5/7/2020 | 5/12/2020 | 5/12/2020 | P | PASS |
Dave Hannah
|
|
|
The on-site contact will be Mierins Rozentals ###-#### Phone #: ###-#### Inspection requested via web by BRS Permitting
|
DOC - Permit Finaled | 5/12/2020 | 5/11/2020 | 5/12/2020 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 4/28/2020 | 4/29/2020 | 4/29/2020 | A | PASS |
Tell Riley
|
|
|
Jay Walters is the onsite contact ###-#### Phone #: ###-#### Inspection requested via web by BRS Permitting//no changes to roof structure per engineer letter//layout in progress, appears to be in accordance with approved plans, 3 foot from eaves per plans//WIP//
|
BLD-Framing/Rough-in | 3/31/2020 | 4/1/2020 | 4/1/2020 | A | NH |
Dave Hannah
|
|
|
Taylor Barton is the onsite contact Phone #: ###-#### Inspection requested via web by BRS Permitting no one on site
|
Issue PAID IN FULL permit | | | 3/25/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/25/2020 | | DONE |
|
|
|
|
Plan assigned to (JG) | 2/27/2020 | 2/27/2020 | 3/24/2020 | | PASS |
Javier Guzman
|
|
|
03/17 L3 Solar Panels ePlan, pend fire
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/24/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/24/2020 | | DONE |
|
|
|
Need
GC Form
(applicant is GC)
|
Route to Impact Fee Review | 3/20/2020 | 3/23/2020 | 3/23/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 2/27/2020 | 2/27/2020 | 3/20/2020 | | PASS |
Joe Bruce
|
|
|
Attached comments to case.
|
1st review completed | | | 3/20/2020 | | DONE |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 2/27/2020 | | 3/19/2020 | | PASS |
Javier Guzman
|
|
|
|
Routing - Design Review | 2/27/2020 | | 2/28/2020 | | PASS |
KayCee Babb
|
|
|
Appeal period for CZC2000037 ends at 5pm on March 9, 2020.
Any work started prior to that date and time is at the applican'ts own risk. If an appeal is received, all work shall cease until a resolution has been found,.
|
Routing - ELECTRICAL | 2/27/2020 | | 2/27/2020 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 2/26/2020 | | PASS |
|
|
|
|
Intake Approval | | | 2/3/2020 | | FAIL |
Michael Hanson
|
|
|
02/03/2020
The Marcos Preciado Gutierrez install sheet must be 18x24.
|
Intake Approval | | | 1/28/2020 | | FAIL |
Michael Hanson
|
|
|
See red clouded markups on checklist for require corrections and documentations.
|
Application received | | | 1/23/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 23 2020 3:17PM
|