BLD-Final | 8/6/2020 | 8/6/2020 | 8/6/2020 | P | PASS |
Jim Storey
|
|
|
Shanel - */Screened*/ Phone #: ###-####
|
DOC - Permit Finaled | 8/6/2020 | 8/6/2020 | 8/6/2020 | P | PASS |
Jim Storey
|
|
|
|
Zoning Approval Temp | 8/3/2020 | 8/3/2020 | 8/3/2020 | | PASS |
Katelyn Menuge
|
|
|
Temporary BND20-00124
|
BLD-Framing/Rough-in | 5/6/2020 | 5/6/2020 | 5/6/2020 | P | PASS |
Jim Storey
|
|
|
firewall thur soffit/ ele mast removed from lay down parapet ok// framing ok
|
BLD-Framing/Rough-in | 5/4/2020 | 5/4/2020 | 5/4/2020 | P | PART |
Jim Storey
|
|
|
screened - Sanel Phone #: ###-#### joist repair at 2nd floor tub/ brace wed at mono truss/ nail interior sheer// remove meter mast fron roof with in 4ft of 2 hr fire wall.
|
BLD-Framing/Rough-in | 5/1/2020 | 5/4/2020 | 5/4/2020 | A | DEFR |
Jim Storey
|
|
|
screened - Sanel Phone #: ###-####
|
BLD-Framing/Rough-in | 4/30/2020 | 5/1/2020 | 5/1/2020 | P | NR |
Dave Hannah
|
|
|
*screened* Eric Phone #: ###-####
|
BLD-Wall Bracing | 4/20/2020 | 4/21/2020 | 4/21/2020 | A | PART |
Jim Storey
|
|
|
per Sanel - inspection already passed by Jim Storey - scheduled on wrong permit. Phone #: ###-#### fire wall not complet exterior of garage and house ok for sheer.
|
BLD-Wall Bracing | 4/6/2020 | 4/7/2020 | 4/7/2020 | A | PART |
Tell Riley
|
|
|
*Screened* - Sanel, detached garage Phone #: ###-####//ok per plans//exterior walls only//garage only//
|
BLD-Foundation | 3/22/2020 | 3/23/2020 | 3/23/2020 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Nick Louie
|
BLD-Footing | 3/18/2020 | 3/19/2020 | 3/19/2020 | A | PASS |
Jim Storey
|
|
|
Nick Phone #: ###-####
|
BLD-Footing | 3/18/2020 | 3/18/2020 | 3/18/2020 | P | PART |
Jim Storey
|
|
|
Sanel Phone #: ###-#### missing rebar at interior ft " E "
|
BLD-Footing | 3/16/2020 | 3/18/2020 | 3/18/2020 | A | CANC |
Jim Storey
|
|
|
Sanel Phone #: ###-####
|
Telephone call | | | 3/10/2020 | | DONE |
|
|
|
nick called, informed him the fees still due and that he would need to use Epay to show all permits/fees for the project
|
Issue PAID IN FULL permit | | | 3/10/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/10/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 3/9/2020 | | |
|
|
|
|
Telephone call | | | 3/9/2020 | | DONE |
|
|
|
emailed applicat/gc to inform them that not all the fees were paid and once the remaining fees are paid we can issue the permits
|
Permit Ready to Issue | | | 3/9/2020 | | DONE |
|
|
|
met
|
Plan assigned to (RDP) | 2/3/2020 | 2/3/2020 | 3/5/2020 | | DONE |
Rob Patrick
|
|
|
3rd Review Complete: 02/14 sfd L1 ePlan...02/14 Failed....03/04 Failed
|
Routing - Design Review | 3/5/2020 | | 3/5/2020 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - PLANNING | 3/5/2020 | | 3/5/2020 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - PLAN CHECK | 3/5/2020 | | 3/5/2020 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/5/2020 | | DONE |
Rob Patrick
|
|
|
|
Routing - PLAN CHECK | 3/4/2020 | | 3/4/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections req'd
|
Routing - Design Review | 3/4/2020 | | 3/4/2020 | | FAIL |
Katelyn Menuge
|
|
|
Upload the most recent cover sheet- version over existing using the same name.
|
Routing - PLAN CHECK | 3/4/2020 | | 3/4/2020 | | FAIL |
Rob Patrick
|
|
|
|
Routing - Design Review | 2/27/2020 | | 2/27/2020 | | FAIL |
Katelyn Menuge
|
|
|
See changemarks. Applicant needs to version drawings.
|
Routing - Design Review | 2/24/2020 | | 2/24/2020 | | FAIL |
Katelyn Menuge
|
|
|
See changemarks. Applicant needs to version drawings.
|
Routing - PLAN CHECK | 2/24/2020 | | 2/24/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections req'd
|
1st review completed | | | 2/14/2020 | | FAIL |
Rob Patrick
|
|
|
Failed for Planning Comments. Blding review is good
|
Routing - PLAN CHECK | 2/3/2020 | | 2/14/2020 | | FAIL |
Rob Patrick
|
|
|
Failed for Planning Comments. Blding review is good
|
Route to Impact Fee Review | 2/3/2020 | 2/6/2020 | 2/4/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 2/3/2020 | | 2/3/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 2/3/2020 | | 2/3/2020 | | FAIL |
Katelyn Menuge
|
|
|
Upload a recorded common wall agreement, letter from Idaho Power stating clearances are met, update drawings to meet changemarks.
|
Routing - Addressing | 2/3/2020 | | 2/3/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/3/2020 | | 2/3/2020 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/3/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/3/2020 | | DONE |
|
|
|
|
Intake Approval | | | 1/31/2020 | | FAIL |
|
|
|
1.All drawings must be uploaded as individual files and have files names that match what is on the plan. Example A1-.01 Site plan or Site Plan.
2. Please write the addresses on the site plan(s) or highlight which site if so which parcel.
3. Please see email that was sent about the sq ft not matching on the application and plans.
|
Telephone call | | | 1/31/2020 | | DONE |
|
|
|
deleted the file in drawing folder in Eplan because everything was in one file and applicant request for clarity, (per Tisha this is okay because is just prescreen)
|
Intake Approval | | | 1/31/2020 | | FAIL |
|
|
|
drawing size was incorrect
|
Application received | | | 1/23/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 23 2020 10:05PM
|