BLD-Final | 6/2/2020 | 6/2/2020 | 6/2/2020 | P | PASS |
Mike Jordan
|
|
|
Call For Access Phone #: ###-#### Inspection requested via web by Allen Jones
|
BLD-Blower Door Test Results | 6/2/2020 | 6/2/2020 | 6/2/2020 | P | DONE |
Mike Jordan
|
|
|
4.8
|
DOC - Permit Finaled | 6/2/2020 | 6/2/2020 | 6/2/2020 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 6/1/2020 | 6/1/2020 | 6/1/2020 | P | FAIL |
Mike Jordan
|
|
|
Call for Access Phone #: ###-#### Inspection requested via web by Allen Jones. Needs MEP finals and firecaulk penetrations in garage.
|
BLD-Wall Bracing | 4/3/2020 | 4/3/2020 | 4/3/2020 | P | PASS |
Brandon Shaw
|
|
|
hook twice and the workers will clear the area per allan // inteior Phone #: ###-####
|
BLD-Energy code compliance | 4/1/2020 | 4/1/2020 | 4/1/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Allen Jones
|
BLD-Framing/Rough-in | 4/1/2020 | 4/1/2020 | 4/1/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Allen Jones
|
BLD-Framing/Rough-in | 3/30/2020 | 3/30/2020 | 3/30/2020 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Allen Jones. Complete lateral bracing on A08 truss. Ok to insulate. Correction notice posted.
|
BLD-Wall Bracing | 3/11/2020 | 3/11/2020 | 3/11/2020 | P | PASS |
Mike Jordan
|
|
|
Louis Phone #: ###-####
|
BLD-Foundation | 2/27/2020 | 2/27/2020 | 2/27/2020 | P | PASS |
Mike Jordan
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 2/26/2020 | 2/26/2020 | 2/26/2020 | P | PASS |
Jim Storey
|
|
|
As early as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
(F) Reprint permit | | | 2/20/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/20/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 2/14/2020 | | |
|
|
|
|
Plan assigned to (D_S) Debbie | 2/12/2020 | 2/12/2020 | 2/14/2020 | | DONE |
Debbie Sanine
|
|
|
02/12- L1 SFD ePlan
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/14/2020 | | DONE |
Debbie Sanine
|
|
|
|
Permit Ready to Issue | | | 2/14/2020 | | DONE |
|
|
|
met
|
Issue PAID IN FULL permit | | | 2/14/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/14/2020 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 1/29/2020 | | 2/14/2020 | | PASS |
Jenny Nelson
|
|
|
|
1st review completed | | | 2/14/2020 | | DONE |
Debbie Sanine
|
|
|
|
Plan assigned to (BJM) | 1/29/2020 | 1/29/2020 | 2/12/2020 | | DEFR |
Brian McGowan
|
|
|
02/12- L1 SFD ePlan
|
Routing - PLANNING | 1/29/2020 | | 1/31/2020 | | PASS |
Crystal Rain
|
|
|
|
Route to Impact Fee Review | 1/29/2020 | 2/1/2020 | 1/30/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 1/29/2020 | | 1/30/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 1/29/2020 | | 1/29/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Routing - MECHANICAL | 1/29/2020 | | 1/29/2020 | | PASS |
Troy James
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/29/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/29/2020 | | DONE |
|
|
|
|
Intake Approval | | | 1/29/2020 | | PASS |
|
|
|
|
Intake Approval | | | 1/27/2020 | | FAIL |
|
|
|
Please rotate Floor calcs, footing cals & truss calcs (unless you would like to upload those into the documents folder), will need to rotate Site plan, truss layouts to the correct orientation. Also the Site plan, Floor Layout, Truss Layout do not meet the minimum size (18x24) Same for the (3) cals if you keep them in the drawings folder
|
Application received | | | 1/26/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 26 2020 10:14AM
|