CHANGE STATUS TO (FNL) | | | 6/12/2020 | | DONE |
|
|
|
Per Dave Hannah, Permit Finaled
|
Letter of compliance/Occupancy | | | 6/12/2020 | | DONE |
|
|
|
|
BLD-Final | 6/10/2020 | 6/11/2020 | 6/11/2020 | P | PASS |
Dave Hannah
|
|
|
Screened- Kelly Phone #: ###-####
|
FIRE-Final Inspection | 6/10/2020 | 6/11/2020 | 6/11/2020 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete (FIR20-00201), no fire alarm modifications, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work is complete.
Kelly Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 5/18/2020 | 5/18/2020 | 5/18/2020 | P | PASS |
Jim Storey
|
|
|
Kelly *Screened* Phone #: ###-#### framing/ceilling ok final ok pending trades.
|
Issue PAID IN FULL permit | | | 3/19/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/19/2020 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 2/7/2020 | 2/7/2020 | 2/28/2020 | | PASS |
Carl D Madsen
|
|
|
St. Lukes Imaging Machine L-3
|
Routing - MECHANICAL | 2/7/2020 | | 2/28/2020 | | PASS |
Troy James
|
|
|
|
1st review completed | | | 2/28/2020 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/28/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/28/2020 | | DONE |
|
|
|
all met: weedops@slhs.org
Need
GC Form
Revised Cert of Value
|
Routing - PLUMBING | 2/7/2020 | | 2/10/2020 | | PASS |
Daryl Spivey
|
|
|
Per plan and NFPA 99
|
Routing - PLAN CHECK | 2/7/2020 | | 2/7/2020 | | PASS |
Carl D Madsen
|
|
|
|
Intake Approval | | | 2/7/2020 | | PASS |
|
|
|
|
Application received | | | 1/31/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 31 2020 10:34AM
|