Print Occupancy Form | | | 8/7/2020 | | DONE |
|
|
|
|
Permanent Occupancy | | | 8/7/2020 | | DONE |
|
|
|
|
BLD-Final | 8/4/2020 | 8/4/2020 | 8/4/2020 | P | DONE |
Jim Storey
|
|
|
*Screened* Bob Phone #: ###-####
|
BLD-Final | 8/4/2020 | 8/4/2020 | 8/4/2020 | A | PASS |
Jim Storey
|
|
|
final ok
|
FIRE-Final Inspection | 8/3/2020 | 8/4/2020 | 8/4/2020 | A | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, no fire sprinklers, no fire alarms, duct detectors are stand-alone and functional with annuciators, fire extingiushers are placed with current inspection tags. Final life fire safety inspection complete, signature card not available at time of inspection.
Sean *screened* Phone #: ###-####
|
FIRE-Final Inspection | 7/31/2020 | 7/31/2020 | 7/31/2020 | P | FAIL |
Troy Cobbley
|
|
|
Remove deadbolt at the west door, provide exit discharge light at the south facing door per approved plans, install duct smoke detector per installation guide (narrow side) and provide testing, provide tagged and mounted fire extinguisher up stairs.
SCREENED // Bob Phone #: ###-####
|
BLD-Energy code compliance | 5/19/2020 | 5/21/2020 | 5/21/2020 | A | PASS |
Jim Storey
|
|
|
screeened / Bob Phone #: ###-####
|
BLD-Framing/Rough-in | 5/19/2020 | 5/21/2020 | 5/21/2020 | A | PASS |
Jim Storey
|
|
|
screeened / Bob Phone #: ###-####
|
BLD-Conference | 5/19/2020 | 5/20/2020 | 5/20/2020 | A | PASS |
Jim Storey
|
|
|
screeened / Bob Phone #: ###-####
|
Print Occupancy Form | | | 4/14/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 4/13/2020 | | DONE |
|
|
|
|
Plan assigned to (JG) | 2/12/2020 | 2/12/2020 | 4/8/2020 | | PASS |
Javier Guzman
|
|
|
04/08 2nd rev, L3 TreBar ePlan
|
Routing - PLAN CHECK | 3/26/2020 | | 4/8/2020 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/8/2020 | | DONE |
|
|
|
ALL MET
Need GC
Need Revised Values
|
Routing Off Site - STRUCTURAL | 3/26/2020 | | 4/7/2020 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by AHJ Engineers
|
Route to Impact Fee Review | 3/12/2020 | 3/15/2020 | 3/13/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 2/12/2020 | 2/12/2020 | 3/12/2020 | | PASS |
Erika Akin
|
|
|
No comments attached. The fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems.
|
1st review completed | | | 3/12/2020 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 2/12/2020 | | 3/12/2020 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLANNING | 2/12/2020 | | 2/20/2020 | | PASS |
Nicolette Womack
|
|
|
Allowed use, route to DR.
|
Routing - Design Review | 2/20/2020 | | 2/20/2020 | | PASS |
Michaella Owens
|
|
|
|
Routing - MECHANICAL | 2/12/2020 | | 2/18/2020 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLUMBING | 2/12/2020 | | 2/13/2020 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC
|
Routing - Addressing | 2/12/2020 | | 2/13/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/12/2020 | | 2/13/2020 | | PASS |
Candy A. Nichols
|
|
|
DREDIT FOR DEMO
|
Intake Approval | | | 2/12/2020 | | PASS |
|
|
|
|
Intake Approval | | | 2/5/2020 | | FAIL |
|
|
|
|
Application received | | | 2/3/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 3 2020 10:26AM
|
First Notice | | 8/17/2020 | | | |
|
|
|
|
Routing - PLANNING | 3/27/2020 | | | | PASS |
|
|
|
Allowed use, route to DR.
|