BLD-Final | 6/11/2020 | 6/11/2020 | 6/11/2020 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Vaughn Pruett
|
DOC - Permit Finaled | 6/11/2020 | 6/11/2020 | 6/11/2020 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 4/29/2020 | 4/30/2020 | 4/30/2020 | A | PASS |
Dave Hannah
|
|
|
Screened- Brandon Phone #: ###-#### ok to cover c/n done
|
BLD-Framing/Rough-in | 4/24/2020 | 4/27/2020 | 4/27/2020 | A | PEND |
Dave Hannah
|
|
|
Screened- Brandon Phone #: ###-#### needs to strape garage door header c/n on site
|
BLD-Wall Bracing | 4/16/2020 | 4/17/2020 | 4/17/2020 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Vaughn Pruett
|
BLD-Foundation | 3/20/2020 | 3/20/2020 | 3/20/2020 | P | PASS |
Dave Hannah
|
|
|
wall // nate Phone #: ###-####
|
BLD-Footing | 3/18/2020 | 3/18/2020 | 3/19/2020 | P | PASS |
Dave Hannah
|
|
|
Nate Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/6/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/6/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 3/5/2020 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 2/11/2020 | 2/11/2020 | 3/5/2020 | | PASS |
Josh Bogle
|
|
|
02/18 garage, ePlan - 1st done
|
Telephone call | | | 3/5/2020 | | DONE |
|
|
|
Emailed GC and applicant to inform them not all the fees were paid and that we need an RP.
|
Routing - PLAN CHECK | 3/5/2020 | | 3/5/2020 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/5/2020 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy no
|
Permit Ready to Issue | | | 3/5/2020 | | DONE |
|
|
|
MET
Need RP
|
Routing - PLAN CHECK | 3/4/2020 | | 3/4/2020 | | FAIL |
Josh Bogle
|
|
|
plans are inconsistant
|
Routing - PLAN CHECK | 2/24/2020 | | 2/25/2020 | | FAIL |
Josh Bogle
|
|
|
no asked for corrections were provided
|
Plan Reviewer's activity | | | 2/24/2020 | | DONE |
Josh Bogle
|
|
|
accepted and routed resubmittal
|
1st review completed | | | 2/20/2020 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 2/11/2020 | | 2/20/2020 | | FAIL |
Josh Bogle
|
|
|
see notes in ePlan
|
Routing - PLANNING | 2/18/2020 | | 2/20/2020 | | PASS |
Michaella Owens
|
|
|
The conditions of approval that were done by KayCee Babb on DRH19-00272 are still in effect on this project. CDX Plywood cannot be used on the exterior, it must be wood or smooth fiber cement. Please revise to one of these materials. I see that you put hardi board (fiber cement) as trim- please specify that it is smooth. I saw in the legend that you still have metal roofing listed but I wasn’t able to find it in the drawing. If you are not using the metal roof (it is not allowed- reference DRH19-272’s conditions) then please remove it from the legend. Finally, please show in the elevations the garage door with the handles and the center trim piece which gives it the appearance of two instead of one.
|
Plan Reviewer's activity | | | 2/18/2020 | | DONE |
Josh Bogle
|
|
|
adding missing routings
|
Intake Approval | | | 2/11/2020 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/11/2020 | | DONE |
|
|
|
|
Intake Approval | | | 2/5/2020 | | FAIL |
|
|
|
Please wait to resubmit until after the appeal period for DRH20-00028 on February 10th at 5pm. (questions please contact Ted V at ###-####)
|
Intake Approval | | | 2/5/2020 | | FAIL |
|
|
|
2nd Prescreen- Please wait to resubmit after appeal period is over for DRH20-00028.
|
Application received | | | 2/4/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 4 2020 3:17PM
|