Telephone call | | | 7/31/2020 | | DONE |
|
|
|
racking permit BLD20-00953 still needs to be finaled before we can sign off for fire life safety.
|
FIRE-Final Inspection | 7/29/2020 | 7/30/2020 | 7/30/2020 | A | PART |
Jim Page
|
|
|
Per conversation with Joe Bruce, Fire Section Supervisor, racking permit needs to be finaled before life fire safety for this permit can be signed off, refer to notes entered on 02JULY2020.
Rod- */Screened*/ Phone #: ###-####
|
BLD-Final | 7/29/2020 | 7/30/2020 | 7/30/2020 | A | PASS |
Jim Storey
|
|
|
Need Life Safety and TI Final Phone #: ###-#### Inspection requested via web by Rod Baxter final ok
|
Temporary Occupancy | 7/7/2020 | 10/5/2020 | 7/7/2020 | | DONE |
Gabe Brenner
|
|
|
|
PubWorks Occupancy Approval | 7/6/2020 | 7/6/2020 | 7/6/2020 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 7/1/2020 | 7/2/2020 | 7/2/2020 | P | PART |
Brandon Shaw
|
|
|
30 day Temp C of O is approved, see Fire/Life entry...
|
BLD-Other | 7/1/2020 | 7/2/2020 | 7/2/2020 | A | CANC |
Brandon Shaw
|
|
|
TCO/Life Safety Call Rod Baxter when onsite Please. Phone #: ###-#### Inspection requested via web by Rod Baxter
|
FIRE-Final Inspection | 7/1/2020 | 7/2/2020 | 7/2/2020 | A | PART |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, partial placement of fire extinguishers is complete (racking is not completed or inspected, fire extinguishers will be placed in areas still needing racking completion), exit signage is attached to racking in numerous areas, as stated racking needs to be completed , once racking is completed the remaining exit signs can be installed for life fie safety. 30 day TCO authorized for life fire safety, final sign off is contingent upon racking install, life fire safety inspection and completion for racking permit, final placement for ALL fire extinguishers as well as exit signage.
Rod Phone #: ###-####
|
Print Occupancy Form | | | 7/1/2020 | | DONE |
|
|
|
|
BLD-Ceiling Grid Inspection | 6/11/2020 | 6/12/2020 | 6/12/2020 | A | PASS |
Jim Storey
|
|
|
Call Rod Baxter upon arrival to site. Thanks Phone #: ###-#### Inspection requested via web by Rod Baxter
|
BLD-Framing/Rough-in | 5/18/2020 | 5/19/2020 | 5/19/2020 | A | PASS |
Jim Storey
|
|
|
Call Rod Baxter upon arrival to site Phone #: ###-#### Inspection requested via web by Rod Baxter
|
BLD-Framing/Rough-in | 5/14/2020 | 5/15/2020 | 5/15/2020 | P | NR |
Jim Storey
|
|
|
Call Rod Baxter when onsite Phone #: ###-#### Inspection requested via web by Rod Baxter
|
BLD-Framing/Rough-in | 5/7/2020 | 5/8/2020 | 5/8/2020 | A | PASS |
Jim Storey
|
|
|
call Rod Baxter when onsite Phone #: ###-#### Inspection requested via web by Rod Baxter demizing wal ok// office ok pending restarooms.
|
Issue PAID IN FULL permit | | | 4/3/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/3/2020 | | DONE |
|
|
|
|
Plan assigned to (JG) | 2/7/2020 | 2/7/2020 | 4/2/2020 | | PASS |
Javier Guzman
|
|
|
04/01 2nd rev L3 Verde ePlan
|
Routing - PLAN CHECK | 3/26/2020 | | 4/2/2020 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/2/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/2/2020 | | DONE |
|
|
|
ALL MET email dakotamcmahon@esiconstruction.com
NEED
GC
REVISED VALUES
|
Routing - MECHANICAL | 3/26/2020 | | 3/27/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 3/26/2020 | | 3/26/2020 | | PASS |
Daryl Spivey
|
|
|
Vent all fixtures and floor drains as required by ISPC.
Provide tempered water to lavs 407.3 ISPC.
|
Plan Reviewer's activity | | | 3/24/2020 | | DONE |
Javier Guzman
|
|
|
sent back to applicant for the following:
1. all resubmittals must use the EXACT same file name as the original so that the new resubmitted sheets can version per ePlan submittal standards found at https://www.cityofboise.org/departments/planning-and-development-services/eplanreview/eplanreview-documents/
2. Per ePlan submittal standards the reserve the bottom right corner on the drawing plans for the City electronic stamps. Leave a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block. see ePlan standards at https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
|
Route to Impact Fee Review | 3/9/2020 | 3/12/2020 | 3/10/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 3/9/2020 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 2/7/2020 | | 3/9/2020 | | FAIL |
Javier Guzman
|
|
|
|
Routing PW Environmental | 2/10/2020 | | 3/4/2020 | | PASS |
Zach Conde
|
|
|
|
Routing - FIRE | 2/7/2020 | 2/7/2020 | 3/3/2020 | | PASS |
Greg Ruxton
|
|
|
Attached comments to case.
|
Routing - Design Review | 2/12/2020 | | 2/12/2020 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - MECHANICAL | 2/7/2020 | | 2/12/2020 | | FAIL |
Troy James
|
|
|
Emailed comments to applicant.
|
Routing - PLANNING | 2/7/2020 | | 2/12/2020 | | PASS |
David Moser
|
|
|
|
Routing - PLUMBING | 2/7/2020 | | 2/11/2020 | | FAIL |
Daryl Spivey
|
|
|
Venting shown on plan PL101A not approved. Vent as required by ISPC.
|
Routing - PUBLIC WORKS | 2/7/2020 | | 2/11/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Routing - Addressing | 2/7/2020 | | 2/7/2020 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 2/6/2020 | | PASS |
|
|
|
|
Application received | | | 2/4/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 4 2020 4:36PM
|