Second Notice | | 5/17/2020 | 7/9/2020 | | DONE |
|
|
|
mailed 7-9-2020
|
First Notice | 5/4/2020 | 5/4/2020 | 5/7/2020 | | DONE |
Tony Young
|
|
|
mailed 5-8-2020
|
BLD-Final | 5/1/2020 | 5/4/2020 | 5/4/2020 | P | PASS |
Tony Young
|
|
|
Scott Phone #: ###-####
|
DOC - Permit Finaled | 5/4/2020 | 5/4/2020 | 5/4/2020 | P | PASS |
Tony Young
|
|
|
|
FIRE-Final Inspection | 5/1/2020 | 5/4/2020 | 5/4/2020 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for area of work is complete, signature card not available at time of inspection.
Scott Phone #: ###-####
|
BLD-Framing/Rough-in | 3/24/2020 | 3/24/2020 | 3/24/2020 | P | PASS |
Mike Jordan
|
|
|
Scott Phone #: ###-####. Interior wood framed walls only ok.
|
Issue PAID IN FULL permit | | | 3/23/2020 | | DONE |
|
|
|
|
Telephone call | | | 3/23/2020 | | DONE |
|
|
|
email permits and inspection card to GC at- slantefield@gmail.com Eplan needs to be release
|
(F) Reprint permit | | | 3/23/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/23/2020 | | DONE |
|
|
|
|
Plan assigned to (J_N) | 3/5/2020 | 3/5/2020 | 3/19/2020 | | DONE |
Jenny Nelson
|
|
|
1st complete 03/13 L2 Carl's Cycles Service ePlan - ceiling tile detail, lighting and mech information needed
|
Routing - PLAN CHECK | 3/19/2020 | | 3/19/2020 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/19/2020 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 3/19/2020 | | DONE |
|
|
|
ALL MET
Need GC
Need Revised Values
|
Route to Impact Fee Review | 3/11/2020 | 3/14/2020 | 3/12/2020 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 3/5/2020 | | 3/11/2020 | | FAIL |
Jenny Nelson
|
|
|
|
1st review completed | | | 3/11/2020 | | DONE |
Jenny Nelson
|
|
|
|
Intake Approval | | | 3/2/2020 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 2/25/2020 | | FAIL |
Julie Romig
|
|
|
1. Code Analysis/Building Data - add the following to the drawing:
2015 International Building Code
2015 International Fire Code
Type VB Construction
Square footage of remodel area
B Occupancy
Fully Fire Sprinklered
2. Key Plan showing the full building plan and identifies where this service area is located on the plan.
3. Door hardware schedule with locking function for each door.
|
Intake Approval | | | 2/6/2020 | | FAIL |
Julie Romig
|
|
|
Please refer to the ePlanReview submittal standards for drawing requirements and uploading the drawings.
https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
(Drawings must be minimum 18"x24" uploaded individually with stamping area)
On the drawings, please provide the following additional information (also see checklist with items circled and additional description):
- Code Analysis/Building Data
- Key plan - this needs to be a full building plan so it is clear where the new Service Writing Area is located, how it exits from the building, etc.
- "Fire Rated" walls and doors are called out in multiple locations. On the key plan clearly label locations of all rated walls and what type of walls these are (fire partitions, fire barriers, etc)
- Dimensioned Floor Plans: Location of new work - Clearly identify what the new walls are that are being constructed.
- If the 3'-6" x 7'-0" door is new, please provide hardware schedule for the door.
- Ceiling plan showing the extent of the new suspended ceiling.
- Locations of exit signs and emergency lighting
- Location of portable fire extinguishers.
|
Application received | | | 2/5/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 5 2020 10:57AM
|