Permit NumberBLD20-00370
StatusIssued
Name STEPHENS LUKE B
Site Address 9290 W HALSTEAD DR
Project NameStephens
Customer Number 
ePlanReviewNo
Description
Permit for the addition of a garage RV bay to include: new footing and foundation, slab, tall walls and door. - All work per plans, notes, engineering, & local code. Separate electrical, plumbing & mechanical permits if required. **RDP**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Wall Bracing7/17/20207/17/20207/17/2020PPASS
DetailsTell Riley
Luke - */Screened Call for access, no one at jobsite*/ Phone #: ###-####//interior side of 2 sided wall shear at garage front//nailing ok per engineering//
BLD-Framing/Rough-in6/11/20206/11/20206/11/2020PPART
DetailsTell Riley
call for access // Luke Phone #: ###-####//add strapping to front wall take photos and installed shear panel//add bracing to girder truss//provide engineering ok for single king stud in place of 2 king studs listed on engineering//ok to insulate//
BLD-Wall Bracing6/5/20206/5/20206/5/2020PPASS
DetailsTony Young
Luke *screeend* Phone #: ###-####/// ok after nailing off more in areas noted with paint
BLD-Foundation3/9/20203/10/20203/10/2020APART
DetailsTell Riley
Pat Phone #: ###-####//still need to set bolts and hold downs//otherwise ok -- WIP//
BLD-Footing3/6/20203/6/20203/6/2020PPART
DetailsTell Riley
Based on PDS online mapping in relation to property,site measument is 20+ feet to side walk to addition- 15 feet required, which based on approved site plan is more than 15 to property in relation to PDS mapping on side setbacks//front and rear maintain existing// dig out for 3x3 pads as discussed//
BLD-Footing3/5/20203/5/20203/5/2020PCANC
DetailsTell Riley
Chris Phone #: ###-####//spoke with Chris, needs to locate side pin for setback verification--asked to cancel//
Routing Walk-In (Zoning)2/6/20202/6/20202/6/2020APASS
DetailsKayCee Babb
Meets setbacks and minimum garage dimensions. Driveway not to exceed 33' in width, as proposed.
Routing Walk-In (BLD)2/6/20202/6/20202/6/2020ADONE
DetailsRob Patrick
Plan assigned to (RDP)2/6/20202/6/20202/6/2020 DONE
DetailsRob Patrick
PLANS/APPL TAKEN TO FRONT DESK  2/6/2020 DONE
DetailsRob Patrick
Permit Ready to Issue  2/6/2020 DONE
Issue PAID IN FULL permit  2/6/2020 DONE
Routing - PLAN CHECK2/6/2020 2/6/2020 PASS
DetailsRob Patrick
1st review completed  2/6/2020 DONE
DetailsRob Patrick
Inspection Record Card- Bld  2/6/2020  
Case Summary (BLD)  2/6/2020 DONE
DetailsRob Patrick
Application received 2/6/2020