Permanent Occupancy | | | 6/16/2020 | | DONE |
|
|
|
|
BLD-Final | 6/15/2020 | 6/15/2020 | 6/15/2020 | P | PASS |
Dave Hannah
|
|
|
Screened- Justin Phone #: ###-####
|
FIRE-Final Inspection | 6/15/2020 | 6/15/2020 | 6/15/2020 | A | PASS |
Jim Page
|
|
|
Knox box has been placed, final life fire safety inspection is complete, signature provided on permit sign off card.
|
Zoning Approval | 6/15/2020 | 6/15/2020 | 6/15/2020 | | PASS |
Kevin Holmes
|
|
|
|
FIRE-Final Inspection | 6/10/2020 | 6/11/2020 | 6/11/2020 | P | PART |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, last remaining item for life fire safety is the knox box install. 30 day TCO authorized, permit can be signed off for life fire safety after knox box is installed and scheduled for final inspection of knox box install.
Justin *screened* Phone #: ###-####
|
Plan Reviewer's activity | | | 5/14/2020 | | DONE |
Michael Hanson
|
|
|
Revised occupant load to more accurately reflect the use of each space.
|
Print Occupancy Form | | | 5/14/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 5/8/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/8/2020 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/29/2020 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 4/29/2020 | | DONE |
|
|
|
met: anne.pemberton@hotmail.comNEED-
Revised Value (anne said form to come after bids)
MET Anne Pemberton
ACHD
GC
|
Plan assigned to (M_H) | 3/16/2020 | | 4/29/2020 | | DONE |
Michael Hanson
|
|
|
1st review completed - 04/08 #520 L3 ePlan - Soleil Daycare
|
Routing - FIRE | 4/28/2020 | 4/28/2020 | 4/28/2020 | | PASS |
Greg Ruxton
|
|
|
Comments attached to case.
|
Routing - PLANNING | 4/28/2020 | | 4/28/2020 | | PASS |
Kevin Holmes
|
|
|
Passed, meets approval criteria of CUP19-00086
|
Routing Off Site - C.D.H | 3/16/2020 | | 4/20/2020 | | PASS |
Michael Hanson
|
|
|
Per mark ups an ePlan approved by Matt McDonald
|
Routing - MECHANICAL | 4/20/2020 | | 4/20/2020 | | PASS |
Troy James
|
|
|
|
Routing Off Site - A.C.H.D | 4/20/2020 | | 4/20/2020 | | FAIL |
Michael Hanson
|
|
|
Email has not been provided from ACHD with fees paid.
|
Routing - PLAN CHECK | 3/16/2020 | | 4/20/2020 | | PASS |
Michael Hanson
|
|
|
|
1st review completed | | | 4/20/2020 | | DONE |
|
|
|
|
Routing - FIRE | 3/16/2020 | 3/16/2020 | 4/17/2020 | | FAIL |
Greg Ruxton
|
|
|
Attached comments to case and emailed architect.
|
Routing - MECHANICAL | 3/16/2020 | | 3/19/2020 | | FAIL |
Troy James
|
|
|
Need mechanical ventilation analysis submitted.
|
Routing - PLUMBING | 3/16/2020 | | 3/18/2020 | | PASS |
Dan Ediger
|
|
|
per plans and ISPC
|
Routing - PLANNING | 3/16/2020 | | 3/17/2020 | | FAIL |
Kevin Holmes
|
|
|
Per CUP19-00086, one bicycle spaces shall be provided. The two perpendicular parking spaces along the alley do not meet dimensional requirements and need to be removed.
|
Routing - Addressing | 3/16/2020 | | 3/16/2020 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/16/2020 | | 3/16/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 3/12/2020 | | PASS |
|
|
|
|
Intake Approval | | | 2/25/2020 | | FAIL |
Michael Hanson
|
|
|
See mark ups on checklist for missing information that is required.
|
Application received | | | 2/7/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 7 2020 8:17AM
|