Permanent Occupancy | | | 4/22/2020 | | DONE |
|
|
|
|
BLD-Final | 4/21/2020 | 4/21/2020 | 4/21/2020 | P | PASS |
Jim Storey
|
|
|
Robert Phone #: ###-####
|
FIRE-Final Inspection | 4/21/2020 | 4/21/2020 | 4/21/2020 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Alarm system repaired.
Robert Phone #: ###-####
|
BLD-Final | 4/20/2020 | 4/21/2020 | 4/21/2020 | A | DEFR |
Jim Storey
|
|
|
Robert Phone #: ###-#### to pm need fire
|
FIRE-Final Inspection | 3/9/2020 | 3/10/2020 | 3/10/2020 | A | FAIL |
Troy Cobbley
|
|
|
The door hardware and the annual inspection for the fire sprinkler system is ok but the fire alarm panel is in trouble with a phone line 2 fault. Robert Phone #: ###-####
|
BLD-Final | 3/5/2020 | 3/6/2020 | 3/9/2020 | P | CANC |
Jim Storey
|
|
|
Megan Phone #: ###-####
|
FIRE-Final Inspection | 3/5/2020 | 3/6/2020 | 3/6/2020 | A | FAIL |
Troy Cobbley
|
|
|
Remove deadbolt at the rear door, provide verification of annual inspection of the sprinkler inspection. I agreed that if the two above items are addressed I would give a temp. for life safety until the Dark Room is built. A permit for the addition of a sprinkler head will require a permit. I also noted that electrical and mechanical permits may be required due to the new equipment.
Megan Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/5/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/5/2020 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 2/7/2020 | | 2/14/2020 | | DONE |
Michael Hanson
|
|
|
02/13 #518 L1 Paper - AAI Inc.
|
Routing - PLAN CHECK | 2/14/2020 | | 2/14/2020 | | PASS |
Michael Hanson
|
|
|
|
1st review completed | | | 2/14/2020 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/14/2020 | | DONE |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 2/14/2020 | | DONE |
Michael Hanson
|
|
|
|
Print Occupancy Form | | | 2/14/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/14/2020 | | DONE |
|
|
|
ALL MET
Need
GC Form (or letter from parcel owner allowing tenant to act as the GC)
Revised Cert of Value
|
Telephone call | | | 2/14/2020 | | DONE |
|
|
|
called and left a message letting the applicant know the permit is ready for pickup and what forms we will need.
|
Routing - FIRE | 2/12/2020 | 2/7/2020 | 2/13/2020 | | FAIL |
Greg Ruxton
|
|
|
Comments attached to case. Emailed applicant.
|
Routing - PUBLIC WORKS | 2/7/2020 | | 2/12/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Routing PW Environmental | 2/11/2020 | | 2/11/2020 | | PASS |
Rick Christenson
|
|
|
|
Routing - Addressing | 2/10/2020 | | 2/10/2020 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 2/7/2020 | | PASS |
|
|
|
|
Application received | | 2/7/2020 | | | |
|
|
|
|