BLD-Footing | 6/10/2020 | 6/11/2020 | 6/11/2020 | A | PASS |
Brandon Shaw
|
|
|
Screened - Rebar - Shon Phone #: ###-####
|
OVERRIDE | | | 6/9/2020 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/9/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/9/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/9/2020 | | DONE |
|
|
|
|
Telephone call | | | 2/20/2020 | | DONE |
|
|
|
6-9-2020 Shun called in to schedule inspection and was inform that GC form is needed and permit needs to be Isue JCA//spoke with Shun to informed him what is needed for permit to be issue- RP, GC and fees
|
OVERRIDE | | | 2/19/2020 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 2/7/2020 | 2/7/2020 | 2/19/2020 | | PASS |
Josh Bogle
|
|
|
02/13 pool, paper
|
Routing - PLAN CHECK | 2/7/2020 | | 2/19/2020 | | PASS |
Josh Bogle
|
|
|
|
Elevation Cert Rec'd-Prelim | | | 2/19/2020 | | DONE |
|
|
|
|
Routing PW Flood Plain | 2/19/2020 | | 2/19/2020 | | PASS |
Jason C. Taylor
|
|
|
EC #1 Recieved (Old) will work for submittal. New EC will be required before final occupancy approved. Jason Taylor ###-####.
|
1st review completed | | | 2/19/2020 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 2/19/2020 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 2/19/2020 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/19/2020 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy no
|
Permit Ready to Issue | | | 2/19/2020 | | DONE |
|
|
|
met: Shon Miles Shon@h2opooldesigns.com
Need GC Form
met
RP
|
Plan resubmittals received | | | 2/18/2020 | | DONE |
|
|
|
elevation certificate and plan taken to Taylor's desk
|
Routing PW Flood Plain | 2/11/2020 | | 2/11/2020 | | FAIL |
Jason C. Taylor
|
|
|
Need elevation certificate and plans modified to show that pool equipment is 1ft over BFE as shown on new FEMA maps.
Jason Taylor ###-####.
|
Routing - PUBLIC WORKS | 2/7/2020 | | 2/11/2020 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 2/7/2020 | | 2/11/2020 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 2/10/2020 | | 2/10/2020 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 2/7/2020 | | PASS |
|
|
|
|
Application received | | 2/7/2020 | | | |
|
|
|
|