BLD-Energy code compliance | 8/10/2020 | 8/11/2020 | 8/11/2020 | A | PASS |
Mike Jordan
|
|
|
kenny *screened* Phone #: ###-####
|
BLD-Framing/Rough-in | 8/11/2020 | 8/11/2020 | 8/11/2020 | A | PASS |
Mike Jordan
|
|
|
kenny *screened* Phone #: ###-####
|
BLD-Energy code compliance | 8/7/2020 | 8/10/2020 | 8/10/2020 | A | NR |
Mike Jordan
|
|
|
screened // Kenny Phone #: ###-####
|
BLD-Framing/Rough-in | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | FAIL |
Mike Jordan
|
|
|
SCREEENED // Kenny Phone #: ###-####. Complete lateral bracing on A02 trusses. Complete all fire caulking. Install all missed fasteners on fire wall and all missing pieces of sheet rock on firewalls. Pending mech. rough in inspection.
|
BLD-Wall Bracing | 7/16/2020 | 7/16/2020 | 7/16/2020 | P | PASS |
Mike Jordan
|
|
|
Kenny *screened* Phone #: ###-####
|
BLD-Wall Bracing | 7/14/2020 | 7/14/2020 | 7/14/2020 | P | NR |
Mike Jordan
|
|
|
Shear .... SCREENED // Kenny Phone #: 208- ###-####
|
BLD-Other | 7/7/2020 | 7/8/2020 | 7/8/2020 | A | PASS |
Mike Jordan
|
|
|
screened - firewall // Kenny Phone #: ###-####. 1st. floor base layers of 5/8 type x rock for firewalls.
|
BLD-Other | 7/6/2020 | 7/7/2020 | 7/7/2020 | A | NR |
Mike Jordan
|
|
|
Fire wall- Kenny *screened* Phone #: ###-####
|
BLD-Foundation | 5/22/2020 | 5/26/2020 | 5/26/2020 | P | PASS |
Mike Jordan
|
|
|
rebar // shane Phone #: ###-####. Interior thickend footings.
|
BLD-Foundation | 4/21/2020 | 4/21/2020 | 4/21/2020 | P | CANC |
Mike Jordan
|
|
|
insulation // Kenny Phone #: ###-####
|
BLD-Energy code compliance | 4/21/2020 | 4/21/2020 | 4/21/2020 | P | PASS |
Mike Jordan
|
|
|
insulation // Kenny Phone #: ###-####. rigid insulation at interior side of stemwall under slab on grade
|
BLD-Foundation | 4/16/2020 | 4/17/2020 | 4/17/2020 | P | PART |
Mike Jordan
|
|
|
screened // Dane Phone #: ###-####
|
BLD-Footing | 4/15/2020 | 4/16/2020 | 4/16/2020 | P | PASS |
Mike Jordan
|
|
|
Screened- Dane Phone #: ###-####
|
Place hold on job | 3/20/2020 | | 3/27/2020 | | DONE |
Tiffany Carson-Herker
|
|
|
Waiting for signed permit
|
Issue PAID IN FULL permit | | | 3/19/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/19/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 3/18/2020 | | |
|
|
|
|
Plan assigned to (RDP) | 2/26/2020 | 2/26/2020 | 3/18/2020 | | DONE |
Rob Patrick
|
|
|
1st Review Complete and Bldg review is ok. 03/12 Failed for Mech Corrections. 03/16 L2 ePlan Townhouse
|
Routing - MECHANICAL | 3/18/2020 | | 3/18/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 3/18/2020 | | 3/18/2020 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/18/2020 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 3/18/2020 | | DONE |
|
|
|
DO NOT ISSUE UNTIL ALL 7 PERMITS PAID
|
Routing - PLAN CHECK | 2/26/2020 | | 3/12/2020 | | FAIL |
Rob Patrick
|
|
|
Bldg review complete and is ok. Failed for Mech corrections.
|
1st review completed | | | 3/12/2020 | | FAIL |
Rob Patrick
|
|
|
|
Route to Impact Fee Review | 2/26/2020 | 2/29/2020 | 2/27/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 2/26/2020 | | 2/27/2020 | | FAIL |
Troy James
|
|
|
|
Routing - PLANNING | 2/26/2020 | | 2/27/2020 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - Addressing | 2/26/2020 | | 2/26/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/26/2020 | | 2/26/2020 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 2/26/2020 | | PASS |
|
|
|
|
Application received | | 2/11/2020 | | | |
|
|
|
|