Permit Information
Permit NumberBLD20-00474
StatusFinaled
Name FALASH & COMPANY INC
Site Address 415 E CRESTLINE DR
Project NameHennessey-Blackwelder Residenc
Customer Number 
ePlanReviewYes
Description
WUI - HILLSIDE Permit for a 40sq' addition enclosing an existing alcove on the rear of the house. Work involves some wall and beam changes on the interior. All work per plans, notations, attachments, engineering, local codes & ordinances. Separate electrical permit required. **JAB**.A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/14/20205/15/20205/15/2020APASS
DetailsBrandon Shaw
screened // greg Phone #: ###-####
DOC - Permit Finaled5/15/20205/15/20205/15/2020PPASS
DetailsBrandon Shaw
BLD-Framing/Rough-in4/14/20204/15/20204/15/2020APASS
DetailsBrandon Shaw
Screened- Greg Phone #: ###-####
BLD-Foundation3/27/20203/27/20203/27/2020PPART
DetailsTell Riley
Greg Phone #: ###-####//WIP//
BLD-Footing3/27/20203/27/20203/27/2020PPART
DetailsTell Riley
Call to be let in // Greg Phone #: ###-####//WIP//
PubWorks Subgrade Approval3/27/20203/27/20203/27/2020 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
BLD-Footing3/24/20203/25/20203/25/2020ANR
DetailsMike Jordan
call when on the way // craig Phone #: ###-####. Needs geo tech report submitted to public works for approval of sub grade.
Issue PAID IN FULL permit  3/5/2020 DONE
Inspection Record Card- Bld  3/5/2020 DONE
OVERRIDE  3/4/2020  
Permit Ready to Issue  3/4/2020 DONE
met
Plan assigned to (JAB) Josh2/21/20202/21/20203/3/2020 PASS
DetailsJosh Bogle
02/27 remodel, ePlan - 1st done
Routing - PLAN CHECK3/3/2020 3/3/2020 PASS
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  3/3/2020 PASS
DetailsJosh Bogle
ESC no - Energy yes
1st review completed  2/27/2020 FAIL
DetailsJosh Bogle
Routing - PLAN CHECK2/21/2020 2/27/2020 FAIL
DetailsJosh Bogle
see email to Mike
Routing - PLANNING2/21/2020 2/27/2020 PASS
DetailsSue Cummings
Routing - Erosion and Sediment2/21/2020 2/25/2020 PASS
DetailsMichael Zawacki
WAIVER APPROVED
Routing PW Grading-Hillside2/21/2020 2/21/2020 PASS
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.

Plans ACCEPTED BY PLAN TECH  2/21/2020 DONE
Recd Pcfee & Taken To Pln CK  2/21/2020 DONE
Intake Approval  2/21/2020 PASS
Routing - PUBLIC WORKS2/21/2020 2/21/2020 PASS
DetailsCandy A. Nichols
NO NEW PLUMBING
Application received  2/14/2020 DONE
Application submitted via PDS Online on Feb 14 2020 9:30AM