BLD-Foundation | 7/30/2020 | 7/30/2020 | 7/30/2020 | P | CANC |
Mike Jordan
|
|
|
FIRE WALL - screened // Kenny Phone #: ###-####
|
BLD-Wall cover | 7/30/2020 | 7/30/2020 | 7/30/2020 | P | PASS |
Mike Jordan
|
|
|
FIRE WALL - screened // Kenny Phone #: ###-####
|
BLD-Wall Bracing | 7/28/2020 | 7/29/2020 | 7/29/2020 | A | PASS |
Mike Jordan
|
|
|
Screened- Kenny Phone #: ###-####
|
BLD-Wall Bracing | 7/28/2020 | 7/28/2020 | 7/28/2020 | P | FAIL |
Mike Jordan
|
|
|
Kenny- */Screened*/ Phone #: ###-####
|
BLD-Foundation | 6/4/2020 | 6/5/2020 | 6/5/2020 | P | PASS |
Mike Jordan
|
|
|
Shane Phone #: ###-####. Interior thickend footings.
|
BLD-Foundation | 4/27/2020 | 4/28/2020 | 4/28/2020 | A | CANC |
Mike Jordan
|
|
|
*screened* +insulation - kenny Phone #: ###-####
|
BLD-Energy code compliance | 4/28/2020 | 4/28/2020 | 4/28/2020 | A | PASS |
Mike Jordan
|
|
|
*screened* +insulation - kenny Phone #: ###-####. Rigid insulation on stemwall under slab on grade.
|
BLD-Foundation | 4/23/2020 | 4/24/2020 | 4/24/2020 | A | PART |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Foundation | 4/22/2020 | 4/23/2020 | 4/23/2020 | P | PART |
Mike Jordan
|
|
|
Dane **cleared** Phone #: ###-####
|
BLD-Footing | 4/21/2020 | 4/22/2020 | 4/22/2020 | P | PASS |
Mike Jordan
|
|
|
Screened- DANE Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/27/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/27/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 3/25/2020 | | |
|
|
|
|
Plan assigned to (RDP) | 3/2/2020 | 3/2/2020 | 3/25/2020 | | DONE |
Rob Patrick
|
|
|
1st Review Complete and Bldg review is ok. 03/17 Failed for Mech Corrections. 03/19 L2 ePlan Townhouse
|
Routing - Erosion and Sediment | 3/25/2020 | | 3/25/2020 | | PASS |
Michael Zawacki
|
|
|
|
Routing - PLAN CHECK | 3/25/2020 | | 3/25/2020 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/25/2020 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 3/25/2020 | | DONE |
|
|
|
MET
DO NOT ISSUE WITHOUT BLD20-00374, BLD20-00###-####0
|
Routing - MECHANICAL | 3/20/2020 | | 3/20/2020 | | PASS |
Troy James
|
|
|
|
1st review completed | | | 3/17/2020 | | FAIL |
Rob Patrick
|
|
|
Mechanical Corrections Req'd
|
Routing - PLAN CHECK | 3/2/2020 | | 3/17/2020 | | FAIL |
Rob Patrick
|
|
|
Mechanical Corrections Req'd
|
Route to Impact Fee Review | 3/2/2020 | 3/5/2020 | 3/3/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 3/2/2020 | | 3/2/2020 | | FAIL |
Troy James
|
|
|
|
Routing - PLANNING | 3/2/2020 | | 3/2/2020 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - Addressing | 3/2/2020 | | 3/2/2020 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 3/2/2020 | | 3/2/2020 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/2/2020 | | DONE |
|
|
|
|
Intake Approval | | | 3/2/2020 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/2/2020 | | DONE |
|
|
|
|
Application received | | 2/14/2020 | | | |
|
|
|
|
Application received | | 2/14/2020 | | | |
|
|
|
|