BLD-Framing/Rough-in | 8/10/2020 | 8/11/2020 | 8/11/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: 2088703262 >> Inspection requested via mobile web by Lucas Eells. All framing issues corrected. ok to insulate.
|
BLD-Framing/Rough-in | 8/3/2020 | 8/4/2020 | 8/4/2020 | A | FAIL |
Mike Jordan
|
|
|
Phone #: 2088703262 >> Inspection requested via mobile web by Lucas Eells. Fireblock at ceiling level 1st. an d2nd. floors between staggered stud 2hr. wall. Provide putty pads on back to back electrical boxes. Provide letter from engineer deleting straps. Remove all foam from top plates and firecaulk, also firecaulk penetrations. C/N posted.
|
BLD-Other | 6/18/2020 | 6/19/2020 | 6/19/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: 2088703262 >> Inspection requested via mobile web by Lucas Eells. 5/8 type x rock for fire walls at exterior locations and prerock areas.
|
BLD-Wall Bracing | 6/15/2020 | 6/16/2020 | 6/16/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: 2088703262 >> Inspection requested via mobile web by Lucas Eells. Exterior shear only ok. Also met with contractor to discuss firewall issues.
|
BLD-Wall Bracing | 6/10/2020 | 6/12/2020 | 6/12/2020 | A | PART |
Mike Jordan
|
|
|
Phone #: 2088703262 >> Inspection requested via mobile web by Lucas Eells. Needs to install all missed floor to floor straps, nail missed areas. Also noted issues with installed sheet rock for fire walls as well as continuity issues that need to be addressed prior to proceeding.
|
Fees Due Hold | 5/8/2020 | | 5/11/2020 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 5/7/2020 | | DONE |
|
|
|
Brandon requested the workflow to be opened for new Manual J's.
|
Routing - MECHANICAL | 5/7/2020 | | 5/7/2020 | | PASS |
Troy James
|
|
|
|
BLD-Foundation | 4/10/2020 | 4/13/2020 | 4/13/2020 | P | PART |
Mike Jordan
|
|
|
Pat *left voicemail* Phone #: ###-####
|
BLD-Footing | 4/9/2020 | 4/10/2020 | 4/10/2020 | P | PART |
Mike Jordan
|
|
|
screened // Pat Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/8/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/8/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 3/13/2020 | | |
|
|
|
|
Plan assigned to (RDP) | 2/20/2020 | 2/20/2020 | 3/13/2020 | | DONE |
Rob Patrick
|
|
|
1st Review Complete: 03/06 Failed...03/10 sfd L2 ePlan Townhouse
|
Telephone call | | | 3/13/2020 | | DONE |
|
|
|
emailed applicant to let them know we need a GC form before issuance
|
Routing - PLAN CHECK | 3/13/2020 | | 3/13/2020 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/13/2020 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 3/13/2020 | | DONE |
|
|
|
met: bsheltrown@hbarchitecture.com
Need GC Form
|
1st review completed | | | 3/6/2020 | | FAIL |
Rob Patrick
|
|
|
|
Routing - PLAN CHECK | 2/20/2020 | | 3/6/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Route to Impact Fee Review | 2/20/2020 | 2/23/2020 | 2/21/2020 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PUBLIC WORKS | 2/20/2020 | | 2/21/2020 | | PASS |
Candy A. Nichols
|
|
|
TOWNHOUSE
|
Plans ACCEPTED BY PLAN TECH | | | 2/20/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/20/2020 | | DONE |
|
|
|
|
Intake Approval | | | 2/20/2020 | | PASS |
|
|
|
|
Routing - MECHANICAL | 2/20/2020 | | 2/20/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 2/20/2020 | | 2/20/2020 | | PASS |
Josh Wilson
|
|
|
|
Routing - Addressing | 2/20/2020 | | 2/20/2020 | | PASS |
Doug Chausow
|
|
|
|
Application received | | | 2/18/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 18 2020 3:10PM
|