Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD20-00529
StatusFinaled
Name IRMINGER CONSTRUCTION INC
Site Address 10969 W TAHITI ST
Project NameSUEZ
Customer Number 
ePlanReviewYes
Description
**(SUEZ- EXTERIOR TANK INSTALLATION)** SPECIAL INSPECTIONS REQUIRED- Permit is to install a 11,359 gallon Bali Hai Chlorine Tank (10' dia x 21.75' overall length). Approval is contingent upon adhering to the approved plans on file. Work to include: Installation of foundation and Tank as per manufacturer specifications and provided engineering, abandonment procedures for the existing tank, associated plumbing and site work as required. **BJM**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice5/21/20205/21/20207/9/2020 DONE
DetailsBrandon Shaw
mailed 7-9-2020
BLD-Final5/21/20205/21/20205/21/2020APASS
DetailsBrandon Shaw
DOC - Permit Finaled5/21/20205/21/20205/21/2020PPASS
DetailsBrandon Shaw
BLD-Final5/19/20205/20/20205/20/2020AFAIL
DetailsBrandon Shaw
No permit or city approved plans, no access to site...
BLD-Footing4/15/20204/15/20204/15/2020PPART
DetailsTell Riley
Dave **Cleared** Phone #: ###-####//pending specials//setbacks measured based on siteplan and relation to exsiting building//
OVERRIDE  4/13/2020  
Route to Impact Fee Review4/10/20204/13/20204/13/2020 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Plan assigned to (BJM)3/12/20203/12/20204/13/2020 DONE
DetailsBrian McGowan
04/07- Suez Clorine Cntact Tank L-3
Issue PAID IN FULL permit  4/13/2020 DONE
Permit Ready to Issue  4/13/2020 DONE
Need
GC Form
Revised Value (see notes in fees, no fees due)
PLANS/APPL TAKEN TO FRONT DESK  4/10/2020 DONE
DetailsBrian McGowan
Routing Off Site - STRUCTURAL4/10/2020 4/10/2020 PASS
DetailsBrian McGowan
Routing - PLAN CHECK4/9/2020 4/9/2020 PASS
DetailsBrian McGowan
Routing - FIRE3/12/20203/12/20204/7/2020 PASS
DetailsGreg Ruxton
04/07 Suez Chlorine tank L3 GJR
1st review completed  4/7/2020 DONE
DetailsBrian McGowan
Routing - PLAN CHECK3/12/2020 4/3/2020 FAIL
DetailsBrian McGowan
All engineering must be in the 2015 Code cycle.
Routing - PLANNING3/12/2020 3/13/2020 PASS
DetailsKevin Holmes
Passed per CAA20-00017
Routing - Addressing3/12/2020 3/12/2020 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS3/12/2020 3/12/2020 PASS
DetailsCandy A. Nichols
NO NEW PLUMBING
Routing - Erosion and Sediment3/12/2020 3/12/2020 PASS
DetailsMichael Zawacki
Routing - Design Review3/12/2020 3/12/2020 PASS
DetailsJosh Wilson
No review required- not in Design Review overlay.
Routing - PLUMBING3/12/2020 3/12/2020 PASS
DetailsDaryl Spivey
Routing PW Drainage3/12/2020 3/12/2020 PASS
DetailsBrian Murphy
Intake Approval  3/11/2020 PASS
Application received  2/19/2020 DONE
Application submitted via PDS Online on Feb 19 2020 11:53AM
Intake Approval  2/19/2020 FAIL
1. Leave a 4"x4" blank space on the cover sheet G001 and a 4"x2" blank space on sheet C100. Locate blank space in the lower right hand corner, 3" off the right sheet edge.
2. ESC Waiver Request Letter.
Routing Off Site - STRUCTURAL3/12/2020   FAIL
DetailsBrian McGowan
AHJ- Code cycle must show or state 2015 IBC conformity.