BLD-Other | 6/18/2020 | 6/19/2020 | 6/19/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: 2088703262 >> Inspection requested via mobile web by Lucas Eells. . 5/8 type x rock for fire walls at exterior locations and prerock areas.
|
BLD-Wall Bracing | 6/15/2020 | 6/16/2020 | 6/16/2020 | A | PASS |
Mike Jordan
|
|
|
Phone #: 2088703262 >> Inspection requested via mobile web by Lucas Eells. Exterior shear only ok. Also met with contractor to discuss firewall issues.
|
BLD-Wall Bracing | 6/11/2020 | 6/12/2020 | 6/12/2020 | A | PART |
Mike Jordan
|
|
|
Phone #: 2088703262 >> Inspection requested via mobile web by Lucas Eells. Needs to install all missed floor to floor straps, nail missed areas. Also noted issues with installed sheet rock for fire walls as well as continuity issues that need to be addressed prior to proceeding.
|
Plan Modification Accepted | | | 5/7/2020 | | DONE |
|
|
|
Brandon requested the workflow to be opened for new Manual J's.
|
Routing - MECHANICAL | 5/7/2020 | | 5/7/2020 | | PASS |
Troy James
|
|
|
|
BLD-Foundation | 4/15/2020 | 4/16/2020 | 4/16/2020 | P | PASS |
Mike Jordan
|
|
|
Pat **cleared** Phone #: ###-####
|
BLD-Footing | 4/13/2020 | 4/14/2020 | 4/14/2020 | P | PART |
Mike Jordan
|
|
|
Screened // Pat Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/8/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/8/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 3/13/2020 | | |
|
|
|
|
Plan assigned to (D_S) Debbie | 2/25/2020 | 2/25/2020 | 3/13/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 3/13/2020 | | 3/13/2020 | | PASS |
Debbie Sanine
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/13/2020 | | DONE |
Debbie Sanine
|
|
|
|
Permit Ready to Issue | | | 3/13/2020 | | DONE |
|
|
|
ISSUE WITH 20-00559, 00566 TO 00569
|
Routing - PLAN CHECK | 2/21/2020 | | 3/6/2020 | | FAIL |
Debbie Sanine
|
|
|
|
1st review completed | | | 3/5/2020 | | FAIL |
Debbie Sanine
|
|
|
|
Routing - Design Review | 2/26/2020 | | 2/26/2020 | | PASS |
Josh Wilson
|
|
|
|
Plan assigned to (J_N) | 2/21/2020 | 2/21/2020 | 2/25/2020 | | DEFR |
Jenny Nelson
|
|
|
03/11 townhouse L2 ePlan
|
Routing - PUBLIC WORKS | 2/21/2020 | | 2/25/2020 | | PASS |
Morgan Webb
|
|
|
|
Route to Impact Fee Review | 2/21/2020 | 2/24/2020 | 2/24/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 2/21/2020 | | 2/24/2020 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 2/21/2020 | | 2/24/2020 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/21/2020 | | DONE |
|
|
|
|
Intake Approval | | | 2/21/2020 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/21/2020 | | DONE |
|
|
|
|
Application received | | 2/20/2020 | | | |
|
|
|
|