Permit NumberBLD20-00594
StatusIssued
Name WESTERN IDAHO BUILDERS
Site Address 1660 W HILL RD
Project NameRetaining Wall
Customer Number 
ePlanReviewNo
Description
JACKSONS STORE #20) Permit for the construction of a new retaining wall at the S.W corner of the building to replace a failing section of retaining wall. CDM
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Footing4/9/20204/9/20204/14/2020PPART
DetailsTony Young
brad - rebar and footing inspec. screened for COVID19 questions. 9am pour time Phone #: ###-####// footing ok now,, pending special inspection report
PubWorks Subgrade Approval4/14/20204/14/20204/14/2020 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
BLD-Footing4/8/20204/9/20204/9/2020ANR
DetailsTony Young
brad - rebar and footing inspec. screened for COVID19 questions. 9am pour time Phone #: ###-####// needs hillside approval 1st
Issue PAID IN FULL permit  3/19/2020 DONE
Plan assigned to (CDM)2/27/20202/27/20203/4/2020 PASS
DetailsCarl D Madsen
Jacksons retaining wall
Routing - Design Review2/27/2020 3/4/2020 PASS
DetailsKayCee Babb
No separate Design Review required for maintenance of retaining wall. Repairs to match existing wall.
Routing - PLAN CHECK2/27/2020 3/4/2020 PASS
DetailsCarl D Madsen
Routing - PUBLIC WORKS2/27/2020 3/4/2020 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment3/4/2020 3/4/2020 PASS
DetailsMichael Zawacki
No esc needed. Work area is within gas station parking lot in area that is 100% impervious. Work is removal and repair of wall.
Good housekeeping will need to be followed, failure to maintain clean worksite will result in need of site specific esc plan.
Pending Assignment by CDM2/21/2020 3/4/2020 PASS
DetailsCarl D Madsen
1st review completed  3/4/2020 DONE
PLANS/APPL TAKEN TO FRONT DESK  3/4/2020 DONE
Case Summary (BLD)  3/4/2020 DONE
Permit Ready to Issue  3/4/2020 DONE
MET
Inspection Record Card- Bld  3/4/2020 DONE
Telephone call  3/4/2020 DONE
Called and spoke with GC letting them know their permit is ready for pick up and the fees due.
Routing PW Grading-Hillside2/27/2020 3/3/2020 PASS
DetailsMelissa Jannusch

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.

Routing PW Flood Plain2/27/2020 2/28/2020 PASS
DetailsJason C. Taylor
Project does not meet the Substantial Improvements section of Boise Floodplain Ordinance .No floodplain requirements. If you have any questions, please call Jason Taylor at ###-####.
Routing - Addressing2/27/2020 2/27/2020 PASS
DetailsDoug Chausow
Intake Approval  2/21/2020 PASS
Application received 2/21/2020