BLD-Footing | 4/9/2020 | 4/9/2020 | 4/14/2020 | P | PART |
Tony Young
|
|
|
brad - rebar and footing inspec. screened for COVID19 questions. 9am pour time Phone #: ###-####// footing ok now,, pending special inspection report
|
PubWorks Subgrade Approval | 4/14/2020 | 4/14/2020 | 4/14/2020 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Footing | 4/8/2020 | 4/9/2020 | 4/9/2020 | A | NR |
Tony Young
|
|
|
brad - rebar and footing inspec. screened for COVID19 questions. 9am pour time Phone #: ###-####// needs hillside approval 1st
|
Issue PAID IN FULL permit | | | 3/19/2020 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 2/27/2020 | 2/27/2020 | 3/4/2020 | | PASS |
Carl D Madsen
|
|
|
Jacksons retaining wall
|
Routing - Design Review | 2/27/2020 | | 3/4/2020 | | PASS |
KayCee Babb
|
|
|
No separate Design Review required for maintenance of retaining wall. Repairs to match existing wall.
|
Routing - PLAN CHECK | 2/27/2020 | | 3/4/2020 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PUBLIC WORKS | 2/27/2020 | | 3/4/2020 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 3/4/2020 | | 3/4/2020 | | PASS |
Michael Zawacki
|
|
|
No esc needed. Work area is within gas station parking lot in area that is 100% impervious. Work is removal and repair of wall.
Good housekeeping will need to be followed, failure to maintain clean worksite will result in need of site specific esc plan.
|
Pending Assignment by CDM | 2/21/2020 | | 3/4/2020 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 3/4/2020 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/4/2020 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/4/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/4/2020 | | DONE |
|
|
|
MET
|
Inspection Record Card- Bld | | | 3/4/2020 | | DONE |
|
|
|
|
Telephone call | | | 3/4/2020 | | DONE |
|
|
|
Called and spoke with GC letting them know their permit is ready for pick up and the fees due.
|
Routing PW Grading-Hillside | 2/27/2020 | | 3/3/2020 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
|
Routing PW Flood Plain | 2/27/2020 | | 2/28/2020 | | PASS |
Jason C. Taylor
|
|
|
Project does not meet the Substantial Improvements section of Boise Floodplain Ordinance .No floodplain requirements. If you have any questions, please call Jason Taylor at ###-####.
|
Routing - Addressing | 2/27/2020 | | 2/27/2020 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 2/21/2020 | | PASS |
|
|
|
|
Application received | | 2/21/2020 | | | |
|
|
|
|