BLD-Final | 5/20/2020 | 5/21/2020 | 5/21/2020 | A | PASS |
Dave Hannah
|
|
|
screened // Keith Phone #: ###-####
|
FIRE-Final Inspection | 5/20/2020 | 5/20/2020 | 5/20/2020 | P | PASS |
Jim Page
|
|
|
No fire sprinkler modifications, fire alarm inspection is complete (FIR20-00345), fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work is complete, signatures provided on permit sign off card.
screened // Keith Phone #: ###-####
|
BLD-Final | 4/21/2020 | 4/22/2020 | 4/23/2020 | A | NR |
Dave Hannah
|
|
|
Keith - Fire Life Safety in the morning as well. Phone #: ###-####
|
FIRE-Final Inspection | 4/21/2020 | 4/22/2020 | 4/22/2020 | A | FAIL |
Jim Page
|
|
|
Horn strobe on fire aalrm system was relocated, per IFC, section 105.7.6 a permit is required for fire alarm modifications. Current candela setting for relocated horn strobe is overspaced.
Keith Phone #: ###-####
|
BLD-Final | 4/20/2020 | 4/21/2020 | 4/21/2020 | A | NR |
Dave Hannah
|
|
|
screened - not that we''re aware of - can make sure no one is there when inspection takes place // Keith Phone #: ###-#### needs fire life saftey
|
BLD-Framing/Rough-in | 3/12/2020 | 3/13/2020 | 3/12/2020 | P | PASS |
Dave Hannah
|
|
|
Keith Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/6/2020 | | DONE |
|
|
|
|
Route to Impact Fee Review | 3/3/2020 | 3/6/2020 | 3/4/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (BJM) | 2/21/2020 | 2/21/2020 | 3/4/2020 | | DONE |
Brian McGowan
|
|
|
03/05- 518 L2- AGC interior Remodel- paper
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/4/2020 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 3/4/2020 | | DONE |
|
|
|
ALL MET
Need GC
|
Telephone call | | | 3/4/2020 | | DONE |
|
|
|
called Wayne to informed him that this is ready, what fees are and that GC form is needed
|
Inspection Record Card- Bld | | | 3/4/2020 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 3/3/2020 | | DONE |
Brian McGowan
|
|
|
Previous Permit was under Suite 101. The Tenant has always used Suite 100
|
Routing - PLAN CHECK | 3/3/2020 | | 3/3/2020 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 3/3/2020 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 3/3/2020 | | DONE |
Brian McGowan
|
|
|
|
Routing - Addressing | 2/21/2020 | | 2/21/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/21/2020 | | 2/21/2020 | | PASS |
Candy A. Nichols
|
|
|
NO NEW PLUMBING
|
Plans ACCEPTED BY PLAN TECH | | | 2/21/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/21/2020 | | DONE |
|
|
|
|
Intake Approval | | | 2/21/2020 | | PASS |
|
|
|
|
Application received | | 2/21/2020 | | | |
|
|
|
|