BLD-Wall Bracing | 6/18/2020 | 6/19/2020 | 6/19/2020 | A | PASS |
Dave Hannah
|
|
|
After 9 if possible Phone #: ###-#### Inspection requested via web by Scott Asin
|
BLD-Energy code compliance | 6/18/2020 | 6/19/2020 | 6/19/2020 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin
|
BLD-Wall Bracing | 6/17/2020 | 6/18/2020 | 6/18/2020 | A | PART |
Dave Hannah
|
|
|
After 9 if possible Phone #: ###-#### Inspection requested via web by Scott Asin ok to insulate int
|
BLD-Wall Bracing | 6/16/2020 | 6/17/2020 | 6/18/2020 | P | PART |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin
|
BLD-Framing/Rough-in | 6/16/2020 | 6/17/2020 | 6/18/2020 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin
|
BLD-Wall Bracing | 6/3/2020 | 6/4/2020 | 6/4/2020 | A | PART |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin ok to cover ext butt needs to install hold downs on inside
|
BLD-Foundation | 5/6/2020 | 5/7/2020 | 5/7/2020 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin
|
BLD-Footing | 5/4/2020 | 5/4/2020 | 5/4/2020 | P | PASS |
Brandon Shaw
|
|
|
Work in progress... Corrections SAT...
|
BLD-Footing | 5/1/2020 | 5/4/2020 | 5/4/2020 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Asin. Needs to remove all tree roots from within footings. Setbacks appear ok, but can not verify, no property line strung.
|
Issue PAID IN FULL permit | | | 5/1/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/1/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 4/29/2020 | | |
|
|
|
|
Plan assigned to (RDP) | 3/10/2020 | 3/10/2020 | 4/29/2020 | | DONE |
Rob Patrick
|
|
|
2nd Review Complete 04/07 Failed, Comments Not Addressed: 03/19 Failed: 03/24 Failed resubmital for Comments not addressed. 03/23 sfd L1 ePlan
|
Routing - Design Review | 4/29/2020 | | 4/29/2020 | | PASS |
KayCee Babb
|
|
|
To comply with redlines concerning street tree and perimeter wall material. It is recommended that the applicant work with Staff on the final wall product prior to installation to verify compliance.
|
Routing - PLAN CHECK | 4/29/2020 | | 4/29/2020 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/29/2020 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 4/29/2020 | | DONE |
|
|
|
MET
|
Routing - Design Review | 4/13/2020 | | 4/13/2020 | | FAIL |
KayCee Babb
|
|
|
Comments not Addressed.
|
Routing - PLAN CHECK | 4/13/2020 | | 4/13/2020 | | FAIL |
Rob Patrick
|
|
|
Comments not Addressed
|
Routing - PLANNING | 4/7/2020 | | 4/7/2020 | | FAIL |
KayCee Babb
|
|
|
Comply with changemarks, including ACHD approval, landscape conditions, and perimeter wall conditions.
|
Routing - PLAN CHECK | 4/7/2020 | | 4/7/2020 | | FAIL |
Rob Patrick
|
|
|
Comments not Addressed
|
Routing - PLANNING | 3/24/2020 | | 3/24/2020 | | FAIL |
KayCee Babb
|
|
|
Comply with conditions of approval of DRH19-00516, per attached changemarks.
|
Routing - PLAN CHECK | 3/24/2020 | | 3/24/2020 | | FAIL |
Rob Patrick
|
|
|
Comments Not Addressed
|
1st review completed | | | 3/19/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Routing - PLAN CHECK | 3/10/2020 | | 3/19/2020 | | FAIL |
Rob Patrick
|
|
|
Corrections Req'd
|
Routing - PUBLIC WORKS | 3/10/2020 | | 3/13/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Routing - MECHANICAL | 3/10/2020 | | 3/12/2020 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 3/10/2020 | 3/13/2020 | 3/11/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 3/10/2020 | | 3/11/2020 | | FAIL |
KayCee Babb
|
|
|
Comply with conditions of approval of DRH19-00516, per attached changemarks.
|
Routing - Addressing | 3/10/2020 | | 3/11/2020 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/10/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/10/2020 | | DONE |
|
|
|
|
Intake Approval | | | 3/10/2020 | | PASS |
|
|
|
|
Intake Approval | | | 2/25/2020 | | FAIL |
|
|
|
1. Drawings must be uploaded as individual files and not as a packet with the correct file names. (example: A1 Site Plan, Site Plan or Site Plan A1)
2. Please upload the Manual J.
|
Application received | | | 2/24/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 24 2020 11:40AM
|